  • BOARD OF EDUCATION OF CALVERT COUNTY PLANNING & CONSTRUCTION REPORT

    November 7, 2019

    WORK IN PROGRESS

    Project Design Construction Northern High School Replacement

    GWWO Architects • Administration Building

    o Roofing complete o Window frame installation complete o HVAC equipment installed o Interior insulation and drywall work

    ongoing • Mary Harrison Center

    o Floor slab complete o Exterior brick complete o Interior block walls complete

    • Bus loop base paving ongoing • Bio-pond work ongoing • Landscaping around Classroom building

    complete • Site concrete in plaza and front of

    administration building ongoing

    J.A. Scheibel

    Misc. Security Projects Smolen Emr Ilkovitch Architects • Guided Vestibule Projects at 6 schools

    complete • Final round of security projects currently

    being surveyed

    J.A. Scheibel FHP Tectonics

    Beach Elementary School

    • Final feasibility study submitted to State • Planning request submitted in FY 2021 CIP • Design Services solicitation in development

  • BOARD OF EDUCATION OF CALVERT COUNTY PLANNING & CONSTRUCTION REPORT

    November 7, 2019

    Huntingtown High School Front Entrance & Gymnasium Entrance Arches

    CRA Associates • Punch list work ongoing

    Colossal Contractors

    Aging School Projects (ASP) – Partial Intercom Replacement at Plum Point Middle School & Mt. Harmony Elementary School

    In House Design • Work Complete

    Commercial Cabling & Sound

    Patuxent High School HVAC Replacement – Phase 2

    James Posey Associates • Phase 2 construction complete

    W.L. Gary Company

    Calvert Country School Systemic Renovation

    Alban Engineering • Project complete

    W.L. Gary Company

    Southern Middle School HVAC Equipment Replacement

    Alban Engineering • Previous Building Automation Controls

    Project scope combined into overall project scope.

    • Project phasing over 2 summers (2021/2022) • Design related work to begin in November

    TBD

    Mt. Harmony Elementary School Partial HVAC Replacement

    James Posey Associates • Design 95% complete

    TBD

    Northern High School/Northern Middle School Wastewater Treatment Plant

    Whitman Requardt & Associates • Design 95% complete

    TBD

    Video Surveillance Project - IDIQ Marathon Technology Solutions • Elementary School camera installation-100%

    Marathon Technology Solutions

  • BOARD OF EDUCATION OF CALVERT COUNTY PLANNING & CONSTRUCTION REPORT

    November 7, 2019

    School Security Grant Program -Round 2

    • Round 2 application-State review complete • CCPS awarded $175,000 in grant funding • Project surveys ongoing

    Misc. Existing Contracts

    Northern Middle School • Educational Specifications (Ed Specs) to be developed in 2020

    TBD

  • Northern High School Replacement

    June 2019

    October 2019

  • Northern High School Replacement

    Micro Bioretention Pond – June 2019 Micro Bioretention Pond – October 2019

  • Northern High School Replacement


Recommended