Transcript

China -- GEF World Bank Urban Transport Partnership Program

Procurement Plan (Draft)

By PMO, December 8, 2009

I. General

1. Project informationCountry: ChinaProject Name: GEF ChinaUrban Transport Partnership ProgramProject Executing Agency: Ministry of Finance, People’s Republic of ChinaProject Implementing Agency: Project Management Office

2. Period covered by this procurement planJune 30, 2009-2013

II. Goods, Works and Non-Consulting Services

1. Prior Review ThresholdPrior Review threshold on contract amount set at: greater than USD100,000 for corporate contractors.

2. Procurement Packages with Methods and Time Schedule(See Table attached below.)

52055

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

III. Selection of Consultants

1. Prior Review ThresholdPrior Review threshold on contractsset at: greater than USD100,000 for consultant firmsand greater than USD50,000 for individual consultants.

2. Procurement ThresholdsQCBS and QBS for all contractsgreater than USD200,000, CQSfor all contracts less than USD200,000; individual consultants (IC) be selected based oncomparison of at least 3 CVs; shortlist of only national consultants for all contracts less than USD300,000.

3. Consultancy Assignments with Selection Methods and Time Schedule

Summary of Procurement Plan of GEF CUTPP

Nov 2009

National/Pilot City

ContractNo.

Contract Name GEF Grants (000 USD)

WBReview pre-review / post-

review

ProcurementMethod

Date ofStartingBidding

ContractDuration(Months)

Leading MunicipalImplementation

Agency

NationalLevel

N1A

Development of aNational UrbanTransport Strategy

N1A1

Development of aNational UrbanTransport Strategy

700 Pre-review QCBS 2009-2013 48 National PMO

N1A2

Preparation of LegislativeChangesfor SustainableUrban Transport

300 Pre-review QCBS 2009-2013 48 National PMO

N1B

Training and Capacity BuildingEffortsat theNational Level

N1B1

Development of SustainableUrbanTransport Planning Guidelines

700 Pre-review QCBS 2009-2013 48 National PMO

N1B2Technical Training workshop andCapacity Building for SustainableUrban Transport (at homeandabroad)(multi-times)

1950 Post-review Training 2009-2013 48 National PMO

N1B3

Development of SustainableUrbanTransport Knowledge Base

600 Pre-review CQS/IC 2009-2013 48 National PMO

N1CDissemination and Awareness-Raising Activities

N1C1Establishment of aSustainableUrban Transport InformationDissemination Platform and theOfficial Web Platform for CUTPP

198 Pre-review COS 2009-2010 6 National PMO

N1C2 Establishment of SustainableUrbanTransport InformationDissemination Platform and PMOWebsitedesign, MIS design and ITservices(multi-timesand multi-specialists)

652 Pre-review CQS/IC 2009-2013 48 National PMO

N1C3Implementation of SustainableUrban Transport Public AwarenessCampaigns(multi-timesand multi-specialists)

900 Pre-review CQS/IC 2009-2013 48 National PMO

N1D

Monitoring and Evaluation(multi-timesand multi-specialists)

1000Pre-review/ Post-

reviewSOE/IC 2009-2013 48 National PMO

Total 7000

N3C1(1.1-1.n)

Domestic staff (multi-contracts) 550Pre-review/ Post-

reviewIC 2009-2013 48 National PMO

N3C2(2.1-2.n)

International and DomesticSpecialists on SustainableUrbanTransport Planning (multi-contracts)

43Pre-review/ Post-

reviewIC 2009-2013 48 National PMO

N3C3(3.1-3.n)

International and DomesticSpecialists on SustainableUrbanTransport Project Management(multi-contracts)

43Pre-review/ Post-

reviewIC 2009-2013 48 National PMO

N3C4PMO Project CIS and outreachmaterialsdesign and productionservices

14Pre-review/ Post-

reviewCQS/IC 2009-2013 48 National PMO

N3C5PMO Logisticsservices for largemeetingsand seminars

30Pre-review/ Post-

reviewSOE 2009-2013 48 National PMO

N3C6 Unforeseen costs 20 Post-review 2009-2013 48 National PMO

Total 700

N3G1(1.1-1.n)

PMO Office rent (multi-contracts) 98 Post-review Shopping 2009-2013 48 National PMO

N3G2(2.1-2.n)

PMO OfficeFurnitureand FacilitiesSupply (multi-contracts)

25Pre-review/ Post-

reviewShopping 2009-2013 48 National PMO

N3G3(3.1-3.n)

PMO OfficeEquipment Supply( ITequipment, computer, printer, photocopier) (multi-contracts)

45 Post-review Shopping 2009-2013 48 National PMO

N3G4 PMO Communication Services 25 Post-review 2009-2013 48 National PMO

N3G5 PMO International Travel Cost 54 Post-review 2009-2013 48 National PMO

N3G6 PMO Domestic Travel 40 Post-review 2009-2013 48 National PMO

N3G7 PMO Other activities (TBD) 13 Post-review Various 2009-2013 48 National PMO

Total 300

Total 8000

WH�PT1 Weihai Urban PTPlanning�procured� 189.2 Pre-review CQS 2009.1.25 6

Weihai GEF UrbanTransport DemonstrationProject Office

Weihai

WH�FS2 Feasibility Study of Green PTCorridor Demonstration Project

334.9 Pre-review QCBS 2009.8 6Weihai GEF UrbanTransport DemonstrationProject Office

WH�ITS3 Intelligent PT System Design andTraining

188.4 Pre-review CQS 2010.1 6Weihai GEF UrbanTransport DemonstrationProject Office

WH�ER4 Expert Evaluation and Review 37.5 Post-review SOE 2009.11 periodicallyWeihai GEF UrbanTransport DemonstrationProject Office

Total 750

JN-BRT1Study of Standardization Design ofJinan BRT Integrated Base

190 Pre-review CQ 2009.9 6 Jinan BusCompany

JN-BRT2Optimization Research of PublicTransit RouteNetwork Based on theBRT Network

460 Pre-review QCBS2009.8.3-

2009.10.3014 Jinan BusCompany

JN-BRT3BRT Intelligent Information SystemResearch

132 Pre-review CQ2009.12.1-2010.2.26

6 Jinan BusCompany

JN-BRT4Research on theProtection andDevelopment of Non-motorizedTransportation

100 Pre-review CQ2010.3.1-2010.5.31

6 Jinan BusCompany

Jinan

JN-BRT5Techniqueand ApplicationResearch of Environment FriendlyBus

70 Post-review CQ2010.6.1-2010.8.31

6 Jinan BusCompany

JN-BRT6 Expert Evaluation and Examination 48 —— —— —— —— Jinan Bus Company

Total 1000

NAEstablishment of a Municipal BusResearch Center

Local Funds NA NA NA NA

PMO, UrbanInfrastructureConstruction InvestmentGroup Co., Ltd.

Xi'an

XA-PTP1 Design of 13 Bus Priority Corridors 480 Pre-review QCBS 2010.6 21

PMO, Planning Bureau,and MunicipalAdministration Bureau,and Urban InfrastructureConstruction InvestmentGroup Co., Ltd.

XA-PTP2

Strategic Bus Planning Study: (i)evaluation and monitoring of busoperations; (ii) bus networkplanning (optimization of urbantransport, integration withneighborhood counties, integrationbetween bus lines, metro lines,airports, and theNorth RailwayStation); (iii) based on thebusnetwork optimization, planningstudy for bus terminals, transit hubs,and transit transfers; (iv) bus fleetdemand forecast, investmentestimate, and implementationschedule; (v) PTP policy research ;(vi) public participation/consultationprocess/campaign; (vii) training.

480 Pre-review QCBS 2009.12 33

PMO, Planning Bureau,and MunicipalAdministration Bureau,and Urban InfrastructureConstruction InvestmentGroup Co., Ltd.

XA-PTP3

Improvement of BusOperations: (i)research on bus operation design;(ii) establishment of monitoringdatabaseand application of relevanttransport softwares; (iii)comparativestudy on good-practicebus operations and investment -comparison between China and afew selected countries in Asia,Europe, and North America; (iv)training; (v) study tour; (vi) busoperationsseminar to exchangetechnologiesand sharegoodinternational practice.

300 Pre-review QCBS 2010.5 15

PMO, and UrbanInfrastructureConstruction InvestmentGroup Co., Ltd.

XA-TDM1

TDM Study: (i) strategic parkingstudy on buspriority corridors; (ii)congestion charging, trafficcalming/safety, and parkingmanagement study within MWC(Ming Walled City); (iii) trafficregulation study related to buspriority; (iv) public participation/consultation process.

410 Pre-review QCBS 2010.4 19

PMO, UrbanInfrastructureConstruction InvestmentGroup Co., Ltd. andPublic Security TrafficAdministration

XA-TDM2

Seminars: (i) congestion charging(within MWC); (ii) effectiveutilization of roadway; (iii) trafficcalming/safety in urban areas.

60 Post-review SOE 2010.12 1

PMO, UrbanInfrastructureConstruction InvestmentGroup Co., Ltd.

XA-TOD

TOD Study: (i) land control plan ofbus facilities; (ii) TOD study on HanChang’an City and new developmentzones; (iii) TOD research on buslinesand bus vehicleallocation; (iv)transport and land usestudy toachieve Transit-OrientedDevelopment; (v) study tour.

270 Pre-review QCBS 2010.4 30

PMO, Planning Bureauand Urban InfrastructureConstruction InvestmentGroup Co., Ltd.

Total 2000

XY-PT1Xianyang Public Transport Planningof SustainableUrban TransportSystem

475 Pre-review QCBS 2009.8 12Public UtilityCorporation of Xianyang,

Xianyang

XY-PT2Xianyang Pilot Project Monitoringand Evaluation

25 Post-review IC 2009.8 16Public UtilityCorporation of Xianyang

Total 500

JZ-TOD1Strategic Research of UrbanComprehensiveTransportation Plan

570 Pre-review QCBS2009.8-2010.8

12Jiaozuo UrbanConstruction InvestmentCorporation

Jiaozuo

—— Expert Review Cost 30 Post-review —— —— ——Jiaozuo UrbanConstruction InvestmentCorporation

Total 600

LY-BRT1Research of BRT and IntelligentTraffic System

570 Pre-review QCBS 2009.12 30

Luoyang PublicTransport Group,Luoyang Traffic PoliceDetachment

Luoyang

LY-BRT2 Evaluation and Review 30 Post-review SOE —— 12

Luoyang PublicTransport Group,Luoyang Traffic PoliceDetachment

Total 600

LF-UTP1Linfen Integrated Urban andTransport Planning Project

350 Pre-review QCBS 2009.7 11 Planning Bureau

LF-UTP2Linfen Strategic PolicymakingStudy

180 Pre-review CQS 2009.7 18 Construction Bureau

LF-UTP3Linfen Public TransportDevelopment Strategy FeasibilityStudy

185 Pre-review CQS 2009.8 7 Construction Bureau

Linfen

LF-M&E1Linfen Pilot Project Monitoringand Evaluation

35 Post-review IC 2009.7 18 FinanceBureau

Total 750

Changzhi CZ-TOD1Feasibility study on Changzhi urbantransport sustainabledevelopmentstrategy plan

750 Pre-review QCBS2009.12-2010.1

6Management Center ofChangzhi UrbanTransport

Total 750

Dongguan DG-TOD1

Theoptimization study on transportsystem in theareasalong DongguanR2 rail line � the traffic improvement study on theplanningof important hubs

750 Pre-review QCBS 2010.11 10 Dongguan Project Office

Total 750

GZ-TDM1Guangzhou City CentreTrafficDemand Management

700 Pre-review QCBS 2009.8 12 Guangzhou PMOGuangzhou

GZ-TDM2 Supervision on TDM Contract 0 NA Local procedure 2009.9 13 Guangzhou PMO

GZ-TDM3 Monitoring and Evaluation 50 NA Local procedure 2009.1 12 Guangzhou PMO

Total 750

WL-BRT1Study on Urban BusRapidTransit�BRT�Network Planning and BusOnly Lane(BOL) Planning

840 Pre-review QCBS 2010.1 12Urumqi UrbanTransportation ReserchCenter

Urumqi

WL-BRT2Urumqi Transport PlanningCapacity Building through Training

160 Pre-review QCBS 2010.9 12Urumqi UrbanTransportation ReserchCenter

Total 1000

Chongqing CQ-LRT1

Research on Rational Choiceof RailTransit Wheel-track System(including communication modeofdowntown, expanded areasand theurban economic ring)

124.45 Pre-review CQS 2009.7 6Chongqing FinanceBureau

CQ-LRT2

Rational Choiceof Rail TransitNetwork Operation andManagement Modeand theControlCenter (rail transit, city railway, rail,surface traffic)

95.17 Post-review CQS 2009.7 6Chongqing FinanceBureau

CQ-LRT3

Planning on Network Operation ofRail Transit Facilities (includingoperation planning, networkoperation planning of car depot,maintenancecenter and powersupply system)

212.3 Pre-review QCBS 2010.2 11Chongqing FinanceBureau

CQ-LRT4

Research on Rail Transit Stationsand Passenger Flow of TransferTerminal (including city railway andpublic surface traffic), passengerflow modeand facilities

139.09 Pre-review CQS 2010.2 11Chongqing FinanceBureau

CQ-LRT5

Research on theSimultaneousConstruction Modeof Rail SystemConstruction with theCross-riverBridgeof Urban Road and on theLaying Modeof Wheel-trackSystem of Rail Transit System

87.85 Post-review CQS 2010.2 11Chongqing FinanceBureau

CQ-BRT1Chongqing BusRapid TransitNetwork Planning (2009-2011)

145 Pre-review CQS 2009.11 14Chongqing FinanceBureau

CQ-BRT2Feasibility Study on ChongqingBRT Line1 Project (2009-2011)

145 Pre-review CQS 2009.11 14Chongqing FinanceBureau

CQ-BRT3Research on Transfer betweenChongqing BRT and Other PublicTraffic Systems (2010-2011)

51.14 Post-review CQS 2010.4 8Chongqing FinanceBureau

Total 1000

NC-WP1The ‘White Paper of NanchangTraffic Development’

368 Pre-review QCBS 2010.1 12PMO of NanchangDevelopment and ReformCommission

Nanchang

NC-TOD1The Construction of the Green-public-traffic-network

632 Pre-review QCBS 2009.1 12PMO of NanchangDevelopment and ReformCommission

Total 1000

Liaoningprovincialprojectmanagementinstitution

LN-IDT1 .Development and Training forLiaoning Provincial ProjectManagement Institution

110 Pre-review CQS 2009.11 5Liaoning UrbanConstruction andRenewal Project Office

LN-TPP1Consulting Service for Third RoundPublic Participation in Six Cities ofLMCIP

55 Pre-review CQS 2009.8 3Liaoning UrbanConstruction andRenewal Project Office

Total 165

Lj-PTDP1Consulting Service for PublicTraffic Development Planning inJinzhou

100 Pre-review CQS 2009.9 6 Jinzhou PMO

Jinzhou City

Lj- IDT1Development and Training forJinzhou Traffic Project ManagementInstitution

40 Post-review CQS 2009.10 1 Jinzhou PMO

Total 140

Lp-TSMP1Consulting Service for TrafficSafety Management and TrafficSafety Planning in Panjin

80 Pre-review CQS 2009.11 6 Panjin PMO

Panjin City

Lp- IDT1Development and Training forPanjin Traffic Project ManagementInstitution

40 Post-review CQS 2009.10 1 Panjin PMO

Total 120

Ll- PTDP1Consulting Service for PublicTraffic Development Planning inLiaoyang

100 Pre-review CQS 2009.9 6 Liaoyang PMO

Liaoyang City

Ll- IDT1Development and Training forLiaoyang Traffic ProjectManagement Institution

40 Post-review CQS 2009.10 1 Liaoyang PMO

Total 140

Lb-TSMP1Consulting Service for TrafficSafety Management and TrafficSafety Planning in Benxi

80 Pre-review CQS 2009.11 6 Benxi PMO

Benxi City

Lb- IDT1Development and Training forBenxi Traffic Project ManagementInstitution

40 Post-review CQS 2009.10 1 Benxi PMO

Tatol 120

DentaCity Ld- IDT1Development and Training forDengtaTraffic Project ManagementInstitution

25 Post-review CQS 2009.10 1 DengtaPMO

Total 25

Fushun City Ls- IDT1Development and Training forFushun Traffic Project ManagementInstitution

40 Post-review CQS 2009.10 1 Fushun PMO

Total 40

Total 750

*Zhengzhou

* Note: The original project of BRT submitted of Zhengzhou has been completed already, Zhengzhou is planning to carry out other projects with GEF Grants.