Page 1: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 1

CanSat 2013 PDR Outline Version 0.2

Your Team # Here

Your Team Name Here

Page 2: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

IMPORTANT PRESENTATION GUIDELINE FOR CANSAT 2013:Teams should focus on charts with this star icon during the presentation. Other charts should be skipped to save time; they will be reviewed by the

judges off line.

Presentations are to be 30 minutes in length.

CanSat 2013 PDR: Team ### (Team Name) 2

Presentation Outline

• Provide a simple outline of the presentation• If possible, indicate the team member(s) who will be

presenting each section• Terms:

– Container refers to the Re-entry Container component of the CanSat

– Payload refers to the Science Payload component of the CanSat

Presenter: Name goes here

Page 3: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 3

Team Organization

• Single slide listing the team members and their roles– If possible, please include year (freshman, sophomore, etc.) for reference– This only needs to be provided once for team members showing up multiple

times on the org chart• Good format is the use of an organization chart, such as below:

Presenter: Name goes here

Team Lead(s)Name(s)

SubSystem 2 Lead(s)Name(s)

SubSystem 3 Lead(s)Name(s)

SubSystem 1 LeadName(s)

Faculty Advisor

Subsystem Engineer 1 Subsystem Engineer 2

Subsystem Engineer 1

Subsystem Engineer 1

Page 4: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 4

Acronyms

• Provide a list of acronyms used throughout the presentation– During presentations, do not read through these

acronyms• These are for reference only

Presenter: Name goes here

Page 5: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 5

Systems Overview

Presenter Name(s) Go Here

The purpose of this section is to introduce the reviewer to the overall requirements and configuration of the CanSat. This provides a basis for the details presented in the subsystem sections.

Page 6: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 6

Mission Summary

• Overview of the mission objectives• Indicate which one (1) selectable objective is being

attempted– Describe selection rationale

• Include any external objectives (personal, laboratory or sponsor, class, etc.) relevant to the design

Presenter: Name goes here

Page 7: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want) System Requirement Summary

• Overview of system (mission) level requirements– Use bullets or a table to demonstrate an understanding of

the mission requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate the team

understands the system-level requirements

CanSat 2013 PDR: Team ### (Team Name) 7Presenter: Name goes here

Page 8: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 8

System Level CanSat Configuration Trade & Selection

• Present preliminary system-level concepts considered– What configurations were considered

• Present criteria for final configuration selection– Include discussion of why the final configuration was selected

• Include sketches and diagrams of various concepts considered– Diagrams of non-selected configurations can include sketches of

physical layouts (e.g. scans of hand sketches rather than CAD drawings)

• Include variations on CONOPS considered• Limit discussions to 1-2 slides per preliminary configuration

– Presentation of the material may be at a cursory level (hit the highlights)

Presenter: Name goes here

Page 9: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 9

System Concept of Operations

• 1-3 slides providing overview of CanSat operations• Include:

– Launch and descent operations– Post-launch recovery and data reduction– Focus on selected configuration CONOPS

• Focus on how the CanSat will operate, not what everyone on the team will be doing (to be discussed at CDR)

• Simple flow diagrams and cartoons are a good way to present the CONOPS

Presenter: Name goes here

Page 10: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 10

Physical Layout

• Diagram(s) showing physical layout of selected CanSat configuration

• Make sure to include:– Dimensions– Placement of major components– Relevant configurations

• Container, Payload, launch configuration, deployed, etc.

• The goal is to present the physical idea of what the CanSat will look like for reference prior to getting into details of the design

Presenter: Name goes here

Page 11: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 11

Launch Vehicle Compatibility

• Discussion of how the CanSats are integrated into the rocket payload section

• Discussion of how the rocket payload section compatibility will be verified prior to launch day

• Include a dimensioned drawing that shows clearances with the payload section– Focus on launch configuration (Container + Payload)– Include all descent control apparatus– At PDR this may be allocated dimensions (if this is the case, these

should be requirements at the system and subsystem levels)• Note:

– In past years there were a large number of CanSats that did not deploy from the payload sections of the rocket because of protrusions

Presenter: Name goes here

Page 12: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 12

Sensor Subsystem Design

Presenter Name(s) Go Here

Page 13: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 13

Sensor Subsystem Overview

• One slide providing an overview of the CanSat sensor system– Include summary of the selected sensors (type &

models)– Include brief discussion of what the sensors are used for– Focus on selected component (not all components

trades)– Include overview of both Container and Payload sensors,

as applicable

Presenter: Name goes here

Page 14: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 14

Sensor Subsystem Requirements

Presenter: Name goes here

• Overview of sensor subsystem requirements– Use bullets or a table to demonstrate an understanding of

the requirements for this subsystem• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges an understanding of the requirements that apply to the subsystem

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsysytem

Page 15: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 15

GPS Trade & Selection

• Summary of GPS sensor trade studies and selection

Presenter: Name goes here

Page 16: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 16

Non-GPS Altitude Sensor Trade & Selection

• Summary of altitude sensor trade study and selection

Presenter: Name goes here

Page 17: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 17

Air Temperature Trade & Selection

• Summary of air temperature sensor trade study and selection

Presenter: Name goes here

Page 18: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 18

Video Camera Trade & Selection

• SELECTABLE OBJECTIVE – ONLY REQUIRED IF SELECTED

Presenter: Name goes here

Page 19: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 19

Impact Force Sensor Trade & Selection

• SELECTABLE OBJECTIVE – ONLY REQUIRED IF SELECTED

Presenter: Name goes here

Page 20: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 20

Descent Control Design

Presenter Name(s) Go Here

Page 21: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 21

Descent Control Overview

• ONE slide providing an overview of the Container and Payload descent control system(s)

• Include overview of the selected configurations and components necessary

• Include diagrams outlining descent control strategy for various flight altitude ranges

Presenter: Name goes here

Page 22: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 22

Descent Control Requirements

Presenter: Name goes here

• Overview of subsystem requirements• Use bullets or a table to demonstrate an understanding

of the DCS requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the system-level requirements

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsystem

Page 23: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 23

Container Descent Control Strategy Selection and Trade

• Summary of container DCS strategy trade studies and selection

• Include:– Color selection– Shock force survival– DCS connections– Preflight review testability

Presenter: Name goes here

Page 24: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 24

Payload Descent Control Strategy Selection and Trade

• Summary of Science Payload DCS strategy trade studies and selection– Include color selection

Presenter: Name goes here

Page 25: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 25

Descent Rate Estimates

• Present estimates for the following CanSat configurations– Container + Payload post separation (prior to deployment

of the Payload)– Container following deployment of the Payload– Payload following separation from the Container

• Include discussion of – Calculations used – Assumptions

• This discussion can carry over to multiple slides if necessary

Presenter: Name goes here

Page 26: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 26

Mechanical Subsystem Design

Presenter Name(s) Go Here

Page 27: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 27

Mechanical Subsystem Overview

• One slide providing overview of the mechanical subsystem– Include overview of major structural elements, material

selection, and interface definitions– Include Container and Payload mechanical

configurations

Presenter: Name goes here

Page 28: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 28

Mechanical Sub-System Requirements

Presenter: Name goes here

• Overview of mechanical sub-system requirements– Use bullets or a table to demonstrate an understanding of

the mission requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the requirements that apply to this sub-system

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsytem

Page 29: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 29

Egg Protection Trade & Selection

• Egg protection system trade studies and selection

Presenter: Name goes here

Page 30: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 30

Mechanical Layout of Components Trade & Selection

• Key trade issues related to mechanical layout and component selection

• Structural material selection(s)

Page 31: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want) Material Selections

• Discussion of what materials will be used for the mechanical components and why

CanSat 2013 PDR: Team ### (Team Name) 31

Page 32: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 32

Container - Payload Interface

• Describe how the Payload will be connected to and released (mechanically) from the Container– Include:

• Discussion of how descent control apparatus will be accommodated

• Diagrams• Method of operation

Presenter: Name goes here

Page 33: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want) Structure Survivability Trades

• For both Container and Payload discuss:– Electronic component mounting methods– Electronic component enclosures– Acceleration and shock force requirements and testing– Securing electrical connections (glue, tape, etc.)

• Consider required judge verification during pre-flight check in

CanSat 2013 PDR: Team ### (Team Name) 33

Page 34: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 34

Mass Budget

• Table(s) providing the following:– Mass of all components– Mass of all structural elements– Sources/uncertainties – whether the masses are

estimates, from data sheets, measured values, etc.– Total mass– Margin

• Must clearly distinguish between Container and Payload masses– Include allocated mass for egg payload

Presenter: Name goes here

Page 35: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 35

Communication and Data Handling (CDH) Subsystem Design

Presenter Name(s) Go Here

Page 36: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 36

CDH Overview

• One slide providing overview of the CDH subsystem– Should include selected components (with brief mention

of what each component is for)

Presenter: Name goes here

Page 37: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 37

CDH Requirements

Presenter: Name goes here

• Overview of CDH sub-system requirements– Use bullets or a table to demonstrate an understanding of

the mission requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the requirements that apply to this sub-system

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsystem

Page 38: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 38

Processor & Memory Trade & Selection

• Include processor speed• Include data interfaces (types and numbers)• Include memory storage requirements, if applicable

Presenter: Name goes here

Page 39: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 39

Antenna Trade & Selection

• Antenna selection criteria• Antenna range and patterns

Presenter: Name goes here

Page 40: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 40

Radio Configuration

• Demonstrate an understanding of the protocol and configuration (e.g., mode and NETID) required to initialize and utilize the XBEE radio module

• Provide description of the impact those requirements have on the CanSat design

• Include transmission control– How is this managed during each mission phase?

• Note:– Communications failures have occurred often over the past several

years of the competition– You are encouraged to use your radios in all of your development

and testing to better ensure mission success• Ideally you have started working with the radio and communications

protocol

Presenter: Name goes here

Start Radio Prototyping and Testing Early!

Page 41: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 41

Telemetry Format

• What data is included?• Data rate of packet?• How is data formatted?

– Include example frames with complete descriptions

Presenter: Name goes here

Page 42: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 42

Activation of Telemetry Transmissions

• Discuss how telemetry transmissions are enabled via remote command on the launch pad

Presenter: Name goes here

Page 43: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 43

Audible Locating Device Trade & Selection

• Describe the audible locating device• How will audible locator devices be activated and

deactivated?– (e.g. how and when the locators are activated and how

they will be deactivated upon recovery)

Presenter: Name goes here

Page 44: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 44

Electrical Power Subsystem (EPS) Design

Presenter Name(s) Go Here

Page 45: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 45

EPS Overview

• One slide providing overview of EPS components (with purposes)

• Consider using a diagram

Presenter: Name goes here

Page 46: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 46

EPS Requirements

Presenter: Name goes here

• Overview of EPS subsystem requirements• Use bullets or a table to demonstrate an understanding

of the mission requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the requirements that apply to this sub-system

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsystem

Page 47: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 47

Electrical Block Diagram

• High-level schematic (not down to the resistor level) showing power connections– Include required voltages– Include all major components

• Include overview of how power will be controlled and verified externally without disassembling the CanSat– I.e., an easily accessible external switch

Presenter: Name goes here

Page 48: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 48

Power Budget

• Power budget in tabular format which includes:– Power consumption (W) of all components– Expected duty cycles for all components– Source/uncertainty for each line item

• Estimate, data sheet, measurement, etc.

– Total power consumed (mAh)– Power available/ battery capacity (mAh)– Margins

• Include potential one hour wait on the launch pad

Presenter: Name goes here

Page 49: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 49

Power Source Trade & Selection

• Discussion of power source selection• Do not consider or select lithium polymer (LiPo)

batteries, which are not allowed because of fire risk

Presenter: Name goes here

Page 50: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 50

Battery Voltage MeasurementTrade & Selection

• Discuss voltage measurements technique / circuit

Presenter: Name goes here

Page 51: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 51

Flight Software (FSW) Design

Presenter Name(s) Go Here

Page 52: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 52

FSW Overview

• Overview of the CanSat FSW design• Should discuss

– Basic FSW architecture– Programming languages– Development environments– Brief summary of what the FSW has to do

Presenter: Name goes here

Page 53: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 53

FSW Requirements

Presenter: Name goes here

• Overview of mechanical sub-system requirements• Use bullets or a table to demonstrate an understanding

of the mission requirements• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the requirements that apply to this sub-system

• Clearly indicate:– Which Competition Guide Requirements are allocated to

this subsystem– Any derived requirements for the subsytem

Page 54: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 54

CanSat FSW State Diagram

• Software state diagram (high level at PDR) defining the states and transition conditions of the flight software

• Things to include:– Sampling of sensors (including rates)– Communications (command and telemetry)– Data storage (if applicable)– Mechanism activations– Major decision points in the logic

• FSW recovery to correct state after processor reset during flight– What data is used to recover?

Presenter: Name goes here

Page 55: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 55

Software Development Plan

• A common CanSat problem is late software development

• Present a slide describing the plan for software development and plans to reduce the risk of late software development

• Include:– Prototyping and prototyping environments– Software subsystem development sequence– Development team– Test methodology

Presenter: Name goes here

Page 56: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 56

Ground Control System (GCS) Design

Presenter Name(s) Go Here

Page 57: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 57

GCS Overview

• Include a simple context diagram showing major components (computers, antenna, adaptors, etc.)

Presenter: Name goes here

Page 58: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 58

GCS Requirements

Presenter: Name goes here

Examples of requirements to include:• Antenna placement (field-of-view requirements)• Computational requirements• Analysis SW requirements• Mission operations sequence of events

• Overview of GCS requirements• Use bullets or a table to demonstrate an understanding

of the requirements for the GCS• This chart may be expanded to multiple charts as

needed• The purpose of the chart is to demonstrate to the

judges that the team understands the requirements that apply to the GCS

Page 59: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 59

GCS Antenna Trade & Selection

• Make sure to include:– Antenna placement and coverage

• Diagram is recommended

– Antenna mast height and mounting strategy• Launch day construction• Launch day verification of height

– Distance link predictions and margins

Presenter: Name goes here

Page 60: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want) GCS Software

• Telemetry display prototypes • Commercial off the shelf (COTS) software packages

used• Real-time plotting software design• Data archiving and retrieval approach• Command software and interface• Telemetry data recording and media presentation to

judges for inspection

CanSat 2013 PDR: Team ### (Team Name) 60

Page 61: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 61

CanSat Integration and Test

Presenter Name(s) Go Here

Page 62: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 62

CanSat Integration and Test Overview

• 3-5 slides• Discussion of how the CanSat subsystems will be integrated• Discussion of system-level tests to be performed on the integrated

CanSat• At PDR this should include concepts for how subsystems will be

integrated– Sequence (which subsystems are needed prior to others)– Test equipment necessary– Test environments necessary

• The goal(s) at PDR are– Get teams thinking about how to put all the pieces together– Get teams thinking about how to test the integrated assembly to

make sure it works as a unit

Presenter: Name goes here

Page 63: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 63

Mission Operations & Analysis

Presenter Name(s) Go Here

Page 64: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 64

Overview of Mission Sequence of Events

• Preliminary launch-day sequence of events– Should start w/arrival at the launch site and proceed

through recovery and data analysis• Include:

– Flow chart of events– Team member roles and responsibilities– Antenna construction and ground system setup– CanSat assembly and test

• Preliminary at PDR

Presenter: Name goes here

Page 65: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 65

Mission Operations Manual Development Plan

• Discuss development and content of the Missions Operations Manual for your CanSat

Presenter: Name goes here

Page 66: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 66

CanSat Location and Recovery

• Discuss how you will find your CanSats in the field– Discuss Container and Payload recovery– Color selection of visible components– CanSat return address labeling

Presenter: Name goes here

Page 67: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 67

Management

Presenter Name(s) Go Here

Page 68: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 68

CanSat Budget – Hardware

• Provide a table listing the costs of the CanSat flight hardware

• Table should include– Cost of major components and hardware– Indication of whether these costs are actual, estimates,

or budgeted values– Indication of hardware re-use from previous years

• The current market value for re-used components should be included

• Note: re-used flight hardware has been known to be more likely to fail

Presenter: Name goes here

Page 69: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 69

CanSat Budget – Other Costs

• Table(s) (same format as Hardware Budget) showing– Ground control station costs– Other costs

• Prototyping• Test facilities and equipment• Rentals• Computers• Travel

– Income• Sources of project income

• The goal(s) of this budget are– To provide an understanding of the overall design and development costs– Get the teams thinking about the overall costs including necessary funds for

travel– Identify shortfalls in the budget that require attention

• In the past some teams have not been able to attend the competition due to a lack of funds

• If caught early enough, there are a number of resources for funding that may available to teams

– THE COMPEITION DOES NOT PROVIDE ANY DEVELOPMENT FUNDING OR DONORS

Presenter: Name goes here

Page 70: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 70

Program Schedule

• Overview of development schedule to include– Competition milestones– Academic milestones and holidays– Major development activities– Component/hardware deliveries– Major integration and test activities and milestones

• The schedule should be “wrapped up” to 1-2 levels– Show high-level tasks only in order to make the schedule readable– It is recommended a schedule at lower levels is developed in order to provide the

team with tools for tracking progress and assessing trouble areas• The goals of this schedule are to

– Provide a tool for the team to track progress of CanSat design and development– Provide tool for judges to assess trouble areas and offer ways for the team to best

meet the objectives of the competition• A one page Gantt summary chart showing task start and stop dates and durations

shall be presented– Schedule should include linkages between tasks to provide the team with an idea of

what happens in the overall flow when milestones are not met on time• Make sure the schedule is readable in the presentation

– This may require the schedule to be broken between multiple slides• Failure to do so will result in a loss of points

Presenter: Name goes here

Page 71: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 71

Conclusions

• Presentation summary and conclusions• In general include the following:

– Major accomplishments– Major unfinished work– Why you are ready to proceed to next stage of

development

Presenter: Name goes here

Page 72: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

CanSat 2013 PDR: Team ### (Team Name) 72

Presentation Scoring & Additional Information

The following slides provide additional information regarding presentation scoring, as well as

recommendations for the presentations and slides

Do Not Include the Following Charts in the Presentations

Page 73: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 73

Presentation Scoring

• Each slide in this template is scored on a scale of 0 to 2 points– 0 = missing or no compliance to the

intent of the requirement– 1 = topic incomplete or partial

compliance to requirements– 2 = complete and demonstrates

requirement is met• Each section of the presentation

(Systems Overview, Sensor Systems, etc.) is weighted according to the table

• Each team will receive a link to a summary score sheet that will contain all their competition scores

Systems Overview 10.00%Sensor Subsystem Design 10.00%Descent Control Design 10.00%Mechanical Subsystem Design 10.00%

Communication & Data Handling Subsystem Design

10.00%

Electrical Power Subsystem Design

10.00%

Flight Software Design 10.00%Ground Contol System Design 10.00%

CanSat Integration & Test 5.00%Mission Operations & Analysis 5.00%Management 5.00%Quality 5.00%

Total: 100.00%

PDR

Page 74: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 74

PPT Template Use

• All teams shall use this presentation template• Team logos

– A team logo can be inserted into the placeholder location (and size) on the master slide

– If no logo is to be used, remove the placeholder from the master slide

• Team numbers in the footer should be updated in the footer information view– REMEMBER TO PUT YOUR TEAM NUMBER IN THE FOOTER– Team names are optional – if no team name is used, please delete

from footer text• On each slide, replace the “Name goes here” in the bottom left corner

with the name of the person(s) presenting that slide– This will allow the judges to know the person to address any

questions or comments to

Page 75: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)

CanSat 2013 PDR: Team ### (Team Name) 75

Trade Studies

• The following recommendations are made with regards to trade studies and selections– Tabular formats listing configurations/components being considered are

helpful– Need to include a discussion of the criteria being used to make the selection

• What are the components/configurations being assessed on• How are values ascribed to the criteria

– Are high values good or low values (if a ranking system is chosen)– Why are different ranking selected

• Data sources for information impacting the criteria and rankings– Make sure it is clear which final component/configuration was selected

• Teams using hardware from previous years are still expected to do a trade to ensure the components are the most appropriate for the task– Already having a component or past experience with a component can be

criteria used in the trade space– Note that in past years re-used components have a higher failure rate

• The same format (whether table are used or not) and criteria (consistent rankings, etc.) be use for all trades to make it easier to review the various trades in a timely manner

Page 76: Team Logo Here CanSat 2013 PDR: Team ### (Team Name)1 CanSat 2013 PDR Outline Version 0.2 Your Team # Here Your Team Name Here

Team LogoHere

(If You Want)Presentation Template Update Log (Do not include in presentation)

• 0.1 Initial version for 2013• 0.2 Minor updates before release to the teams