Upload
zondits
View
30
Download
0
Embed Size (px)
Citation preview
ersenergy&resource
solutions
Challenges in Review Challenges in Review and Postand Post--Installation Inspections Installation Inspections of a Demand Response Programof a Demand Response Program
© 2006 Energy & Resource Solutions, Inc.
prepared and presented by
Mark D’Antonio (ERS)Co-Authors
Chris Smith (NYSERDA)John Seryak, Gary Epstein (ERS)
ACEEE 2006 Summer Study
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
2
Presentation OverviewPresentation Overview
BackgroundNYSERDA Peak Load Reduction Program OverviewProcess OverviewReview and Inspection ChallengesCase StudiesLessons Learned
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
3
BackgroundBackground
NYSERDA – New York State Energy and Research Development Authority
Operates the Peak Load Reduction ProgramSummer Peak ReductionEnabling Technologies
Supported by Systems Benefit Charge (SBC) Funding
NYISO - New York Independent Systems Operator Administers Demand Response Programs
Incentivizes Actual Curtailments and Demand Response Actions
NYSERDA Consultants – competitively solicited group of contractors that provide Quality Assurance services for NYSERDA’s program (ERS’ region – NYC)
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
4
NYSERDANYSERDA’’s Peak Load Reduction Programs Peak Load Reduction ProgramPON 955PON 955
Permanent Demand Reduction (PDR)Electric Technologies – Lighting, Chillers, Motors….
Steam Retention (Avoided Electric Load) – Absorption Chillers, Steam Turbine Driveline Chillers
Load Curtailment/Shifting (LC/S)Enabling Controls for Curtailment
Load Shifting
Distributed Generation (DG,DR)Distributed Generation
Demand Response (Generators)
Interval Meters (IM) PSC Approved - Revenue Grade
NYISO Compliant – Shadow Meter
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
5
NYSERDANYSERDA’’s Peak Load Reduction Programs Peak Load Reduction Program
PDR LC/S DG IM
Con EdisonService
Territory
Non-Con
EdisonService
Territory
Con EdisonService
Territory
Non-Con
EdisonService
Territory
Con EdisonService
Territory onlyStatewide
$500/kW Electric
$425/kW Steam Ret
$225/kW $200/kW $45/kW
$120/kW exist DR
$160/kWnew DR$400/kW DG
$1,500/meterNYISO Compliant
$2,000/meterPSC Approved
1. Contractors will be reimbursed the lesser of 65% of the Eligible Project Costs or the incentive caps set forth in Table 1. The Facility owner/operator must contribute no less than 35% of Eligible Project Costs. Facility cap of $750,000. Contractor cap of $2 Million2. Incentive of $100,000 provided to aggregators who provide greater than 10 MW of verified load curtailment in ConEd territory3.Super Efficient Chillers eligible for additional incentives
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
6
Energy Efficiency TechnologiesLighting, Motors, HVAC, VFDs, Industrial Equipment
Energy Management System Load ControlSmart Load Control Systems Metering SystemsDirect Load ControlBackup GenerationDistributed GenerationLoad Shifting Technologies (Thermal Storage)Avoided Load (Steam Drivelines/Chillers)
Enabling Technology OptionsEnabling Technology Options
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
7
Process OverviewProcess Overview
ApplicationNYSERDA Reviews for Program Requirements (in house)
Encumber Funds, Issue PO to Applicant, Assign QA Consultant
Applicant Submits Technical Assessment (TA) to QA ConsultantTA documents analytical basis and equipment details for proposed Demand Reduction
QA Consultant Reviews TATechnical Feasibility and Accuracy
Recommendation to NYSERDA ( Approval, Modified Approval, Disapprove)
NYSERDA Issues Notice to Proceed (for Approved Projects)Installation Post-Installation Inspection by QA ConsultantFinal Approval Sent to NYSERDANYSERDA Processes Incentive
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
8
QA Consultant RoleQA Consultant Role
General GuidanceRespond to Applicant Questions About the Process
Technical Review of TAPre - Installation Site Visit (Optional)
Screen TA for Completeness
Analytical Review – Technical Content, Feasibility, Accuracy, Cost
Work with Applicant for Modifications
Approval RecommendationPost-Installation Inspection
Verification of Equipment Actually Installed – qty, make/model, details, photos
Operability and Sequence of Operation – demonstrated performance
Final Approval
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
9
Example ProjectsExample Projects
PDR - LightingCommercial Retail - T12 to T8 Conversion, Incandescent to CFLs, Delamping.
1,700 kW Peak Load, 26 kW Permanent Reduction, Approved Incentive = $12,250
LC/S – EMS Load SheddingCommercial Retail - HVAC Fan & Pump Control (VFDs)
8 MW Peak Load, 575 kW Load Curtailment, Approved Incentive = $103,500
PDR – Steam RetentionCommercial Office Building – Steam Turbine Driveline Replacement
1,424 Peak Load, 649 kW Avoided, Approved Incentive = $308,275
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
10
Example Projects Example Projects -- ContinuedContinued
DG – Gas Fired Micro TurbineRefrigerated Food – Three Natural Gas Micro Turbines
1,400 kW Peak Load, 180 kW DG, Approved Incentive = $49,500
DR – Diesel GeneratorFood Manufacturing – Diesel Back Up/Demand Response Generator
1,300 kW Peak, 259 kW in DR, Approved Incentive = $32, 375
PDR – HVAC ModificationsCommercial Office High Rise – Install Premium Efficiency Motors and VFDs on SAF,RAF and CT Fans
8,500 kW Peak, 329 kW in DR, Approved Incentive = $156,275
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
11
ChallengesChallenges
GeneralMany Players – Applicant, Building Owner, Building Operator, Contractor (TA developer), CSP, NYISO, ConEd, Department of Environmental Conservation (DEC)
Often Chasing Information
Unethical Practices?
Overly Aggressive ReductionsUnscrupulous Business Practices
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
12
Challenges Challenges -- ContinuedContinued
AnalyticalNumerous Technologies – EE, Controls, DG, Generators, Meters
Proprietary Information? (Obtaining Performance Data, Custom Spreadsheets - QA Consultant viewed as a competitor that will gain competitive advantage)
Inadequate Information in TA’s
Lack of Analytical Capabilities of Project Developers
InspectionAccess Issues (Inaccessible locations, Inaccessible Equipment, Inaccessible People)
Incomplete Projects – “Well it is almost done - perhaps I could get my incentive…..”
Unwilling to Demonstrate Operation (ex: transfer Building Load to DR Generators)
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
13
Challenges Challenges –– More SpecificallyMore Specifically
Verifying Large Lighting ProjectsRestricted Access – locked rooms
Sampling
Establishing Load ProfilesModeling vs. Logs vs. Monitoring
VFDs – now for Curtailment only (PON 955)
DR GeneratorsFacility Owner wants NYSERDA $, but often doesn’t understand NYISO – Vendor just wants to sell generator – Need CSP coordination
Permitting Documentation can be delayed
NYISO Registration Confirmation
Verification of Load Transfer (Interval Data)
Distributed GenerationEstablishing Actual Operational Parameters (Run-time, Loading)
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
14
Case Study Case Study –– 1585 Broadway1585 Broadway
•Morgan Stanley
•42 Floors – 1.4 Million SF
•8,500 MW Peak Load
•VFDs on Variable Pitch SAF, RAF
•PE Motors and VFDs on CT Fans
•Property Mgt – Applicant
•Technical Contractor – develop TA
•Installation Contractor(s)
•Separate Controls Contractor
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
15
•Proprietary Analysis
•Did Not Install PE Motors
•Communications Issues – not all VFDs working (finger pointing)
•Control Algorithms Somewhat Different than Proposed
•Modified “Final” Approval
•2nd Site Inspection Requested by Applicant After Recalibration
•EMS Trending
•Modified “Final Final” Approval
Case Study Case Study –– ChallengesChallenges
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
16
Lessons LearnedLessons Learned
Communicate, Communicate, CommunicateAssume Nothing
Explain Everything
Involve All StakeholdersMake Sure all Parties are Clear on Process, Deliverables and Requirements
Document Correspondences and Keep All Parties Informed
Program Managers as MediatorsClarifying Program Decisions are Needed Occasionally from NYSERDA Program Managers
Diligent (but respectful) Scrutiny is RequiredVerification – Did the right stuff get installed?
Ethical Practice
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
17
Further InformationFurther Information
PON 955 - On Web Downloadable at:www.nyserda.org/funding
NYSERDA: 1-866-NYSERDA (697-3732)Chris Smith ext 3360
Energy & Resource Solutions (ERS)Mark D’Antonio 212-789-8182 ext 251
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
18
Questions?Questions?
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
19
Intentionally Left Blank
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
20
Direct Load ControlDirect Load Control
Traditionally Focused on Residential SectorDHW, Pool Pumps, AC
Many New Approaches for C&I SectorCentral Control of Multi-Facility Customers
Remote EMS Control of Sites with Pre-programmed curtailment strategies
Programmable, Direct Load Control ThermostatsDirect Load Control Switches: AC, Electric Heat, Etc.
21 locations (1 MW)
36 locations(4.4MW)
16 locations (0.8 MW)
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
21
Distributed Generation TechnologiesDistributed Generation Technologies
Backup Generation SystemsAssessment of Load Applicability During Curtailment is Critical
Environmental Requirements are Similarly Critical
Diesel GeneratorsSteam Turbine DGMicroTurbine SystemsRenewable Technologies
Fuel Cells
Photovoltaics
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
22
Local Scheduling ControllersTypically Address HVAC and LightingMany Energy Management Systems have Demand Control Features
Programmed Scheduling
Demand Limiting
Duty Cycling
Generally, EMS Systems Schedule (Turn Off) Predetermined Groups of EquipmentChallenges or Limitations
Demand Control Can Conflict with Control Rules
Rules Based Logic Can Limit Certain Demand Control Effectiveness
Central and Focused Energy Management Systems Central and Focused Energy Management Systems for Demand Controlfor Demand Control
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
23
Systems are Dedicated to Demand ControlDo Not Have Standard BAS or EMS Functionality
Continually Monitor Facility kWSingle or Multiple Meters
Smart Algorithm Continually Forecasts Average kW During Specified Period (e.g.: 15 or 30 minute period)Smart Duty Cycling Routine is Used to Modulate or Turn Off End Use Equipment to Avoid Reaching Threshold kW LevelsNeural Net (AI) - Smart Building Automation System that Progressively Learns Best Operation of Building Systems
Smart Demand Control with kW ForecastingSmart Demand Control with kW Forecasting
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
24
kW Impacts with Lighting Efficiency Technologies and Occupancy SensorsScheduling with Lighting Control PanelsDirect Addressable Lighting Systems (DALI, etc.)
Multi-Level and Continuous Dimming Systems
Load Shedding Ballasts
Power Reducing or Current Limiting Devices ???
Demand Control with Lighting TechnologiesDemand Control with Lighting Technologies
ers energy & resource solutions© 2006 Energy and Resource Solutions, Inc.
25
Load ShiftingThermal Storage
Off-Peak Operations for Industrial Facilities
Fuel Switching TechnologiesAbsorption Chillers
Steam Turbine Chillers
Engine-Driven Chillers
Engine-Driven Compressors
Load Shifting/Fuel Switching TechnologiesLoad Shifting/Fuel Switching Technologies