Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
What is the cost of the Spare Parts for 2 years operation for the following commodity:
0% of PO Price
10% of PO Price
20% of PO price?
Pressure Vessels
Pumps
Control, ON/OFF valves, PSVs
Unit Control Panel
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
What is the cost of the Spare Parts for 2 years operation for the following commodity:
0% of PO Price
10% of PO Price
20% of PO price?
Pressure Vessels – 0%
Pumps – 10%
Control, ON/OFF valves, PSVs – 20%
Unit Control Panel – 10%
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
What is missing from the table of contents of the Engineering Design Data shown below?
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
What is missing from the table of contents of the Engineering Design Data shown below?
Project Engineer knowledge test
Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 12
HERVE BARON
© 2015 – Hervé Baron
Which system is used to calculate the engineering progress by document weight and progress steps (revision status)
1) the Project scheduling software, such as Primavera,
2) the document control system and master document register
3) another system
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
Which system is used to calculate the engineering progress by document weight and progress steps (revision status)
1) the Project scheduling software, such as Primavera,
2) the document control system and master document register
3) another system, as the progress measurement is done by group of documents, e.g., Unit 12 P&IDs, not by individual document which is the level system 2 goes to. The grouping is finer than that of the scheduling software.
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings?
1) 1:50
2) 1:200
3) 1:500
HERVE BARON
© 2015 – Hervé Baron
What is the graphic scale of the Civil Works Installation (also called Civil Area) drawings?
1) 1:50
2) 1:200
3) 1:500
Project Engineer knowledge test
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
When does Engineering progress picks-up to reach cruising speed on an EPC?
1) after all disciplines have been mobilized
2) after the P&IDs have been finalized
3) after the Plot Plan has been finalized
4) after the purchase orders for equipment have been placed
5) after the completion of the 3D model
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
When does Engineering progress picks-up to reach cruising speed on an EPC?
1) after all disciplines have been mobilized
2) after the P&IDs have been finalized
3) after the Plot Plan has been finalized
4) after the purchase orders for equipment have been placed. Cruise speed is reached 2 months after 50% of equipment purchase orders have ben placed.
5) after the completion of the 3D model
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers?
1) a particular specification
2) a general specification
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What type of specification is issued (by Equipment/Mechanical discipline) for air-coolers?
1) a particular specification
2) a general specification
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The lengths of pipes used for the first purchase order of piping materials are obtained from?
1) The Piping General Arrangement drawings,
2) The Plot plan,
3) Piping layout drawings,
4) The 3D model,
5) The isometric drawings,
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The lengths of pipes used for the first purchase order of piping materials are obtained from?
1) The Piping General Arrangement drawings,
2) The Plot plan,
3) Piping layout drawings,
4) The 3D model,
5) The isometric drawings,
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which of the following documents are produced at BASIC engineering stage (prior to FEED stage)
1) Equipment Process data sheets
2) Equipment Mechanical data sheets
3) Material Take-Off's
4) Piping routing drawings
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which of the following documents are produced at BASIC engineering stage (prior to FEED stage)
1) Equipment Process data sheets
2) Equipment Mechanical data sheets
3) Material Take-Off's
4) Piping routing drawings
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What is a Material Take-Off?
1) an estimate of quantities to be supplied/erected,
2) the cumulated quantities of what is shown on a set of drawings
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What is a Material Take-Off?
1) an estimate of quantities to be supplied/erected,
2) the cumulated quantities of what is shown on a set of drawings
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What does IP level of electrical and instrumentation equipment mean and stand for?
Level of mechanical protection
Level of explosion protection
IP means: ………….
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What does IP level of electrical and instrumentation equipment mean and stand for?
Level of mechanical protection
Level of explosion protection
IP means: Ingress Protection. It means mechanical protection and protection again ingress of water, dust etc. Reference code is IEC 60529 "Degree of Protection provided by enclosures". Typically a certain IP level is specified for outdoor equipment and another one for indoor equipment.
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
What do you call the Instrument & Control drawing showing all details of wiring, with termination and inter-connections from primary element to final, including tags of
• Primary element, • Individual cables, • Junction boxes, • Multipair cables, • Cable cores • Terminals, • I/O cards, • Panels, • Locations (field, technical rooms)
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Source: ”The Oil & Gas Engineering Guide”, Hervé Baron, Editions Technip, page 173
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which of the following Equipment Vendor documents are critical for Engineering progress?
1) Cross section drawings and bills of materials
2) List of inputs/outputs to DCS
3) Foundation layout and loading plan
4) Filled-in data sheet
5) Operating Manual
6) General arrangement drawing
7) Strength calculation note
8) Utility consumption list
9) Performance curve
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which of the following Equipment Vendor documents are critical for Engineering progress?
1) Cross section drawings and bills of materials
2) List of inputs/outputs to DCS
3) Foundation layout and loading plan
4) Filled-in data sheet
5) Operating Manual
6) General arrangement drawing
7) Strength calculation note
8) Utility consumption list
9) Performance curve
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which sentences are correct:
1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing,
2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification.
3) The piping isometric drawing is used for piping pre-fabrciation,
4) The Piping General Arrangement drawing is used for piping erection,
5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which sentences are correct:
1) The Piping General Arrangement Drawing contains all the information required to produce the piping isometric drawing,
2) The piping isometric drawing indicates the piping material class. The exact material designation is found in the piping material class specification.
3) The piping isometric drawing is used for piping pre-fabrciation,
4) The Piping General Arrangement drawing is used for piping erection,
5)The 3D model is often used nowdays in lieu of the Piping General Arrangement,
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The Process Data Sheet of a heat exchanger indicates which of the following information?
1) the duty
2) the heat exchange area
3) the fouling factor
4) the type of each exchanger (U-tube etc.)
5) the allowable pressure drop
6) dimensions
7) overdesign
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The Process Data Sheet of a heat exchanger indicates which of the following information?
1) the duty
2) the heat exchange area
3) the fouling factor
4) the type of each exchanger (U-tube etc.)
5) the allowable pressure drop
6) dimensions
7) overdesgin
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities?
1) ASME VIII
2) NACE MR103
3) API RP 581
4) none of the above
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which codes gives the corrosion rate (in mm/year) for the usual corrosion phenomena found in Oil & Gas facilities?
1) ASME VIII
2) NACE MR103
3) API RP 581
4) none of the above
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
FEED studies primarily focus on
1) Plant Layout
2) Piping routing
3) Process design
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
FEED studies primarily focus on
1) Plant Layout
2) Piping routing
3) Process design
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
"free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
"free draining" and "no pocket" indication on P&IDs mean the same thing. Right or Wrong?
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines".
1) the Piping and Instrumentation Diagram
2) the Unit Plot Plan
3) the line diagram
4) the Piping layout drawing
5) the Piping General Arrangement drawing
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which drawing corresponds to the following definition: "initial graphic piping plan. It is not a finished document, nor is it a deliverable to a Client. It shows all equipment in a given area to scale and includes major process and utility piping systems, significant valving and instruments. It indicates the exact equipment locations and elevations, nozzles, platform and ladder requirements and any pipe support that affects the design of equipment or structure other disciplines".
1) the Piping and Instrumentation Diagram
2) the Unit Plot Plan
3) the line diagram
4) the Piping layout drawing
5) the Piping General Arrangement drawing
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which pumps are inter-changeable, i.e., have standard dimensions
1) the ones designed to API code
2) the ones designed to ANSI code
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
Which pumps are inter-changeable, i.e., have standard dimensions
1) the ones designed to API code
2) the ones designed to ANSI code
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong?
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
The process engineer enters the heat exchange area and transfer coefficient in the process simulator as input data. Right or Wrong. The Process engineer enters the outlet temperature only.
HERVE BARON
© 2015 – Hervé Baron
Project Engineer knowledge test
That’s all for now folks, but I won’t be long with new tests…
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
A unique synthesis for the busy Project professional 270 pages 300 illustrations
Interested and wanting to know more on Engineering?
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Discipline presentation: activities and deliverables
Table of Contents
The overall process
Methods & tools
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Discipline presentation: activities and deliverables
HERVE BARON
© 2015 – Hervé Baron
The work of each Engineering
discipline is described
HERVE BARON
© 2015 – Hervé Baron
Design activities are explained, e.g., Plant
Equipment layout
HERVE BARON
© 2015 – Hervé Baron
Complex activities, such as
QRA, are explained through a practical example.
HERVE BARON
© 2015 – Hervé Baron
How are materials of
construction selected ?
HERVE BARON
© 2015 – Hervé Baron
How and when are Piping
Materials ordered?
HERVE BARON
© 2015 – Hervé Baron
A sample of all common Engineering documents is
included
HERVE BARON
© 2015 – Hervé Baron
A sample of all common Engineering documents is
included
Use this to specify what you
want to your Engineering supplier !
HERVE BARON
© 2015 – Hervé Baron
Verify the contents of
engineering documents with check lists.
HERVE BARON
© 2015 – Hervé Baron
Difference between
Engineering and Shop drawings
HERVE BARON
© 2015 – Hervé Baron
Understand the main
technical aspects, e.g., DCS vs ESD
HERVE BARON
© 2015 – Hervé Baron
The common 2 types of
package control
HERVE BARON
© 2015 – Hervé Baron
The different Plant drainage
systems
HERVE BARON
© 2015 – Hervé Baron
The dynamic forces to
which an Off-Shore Plant is subject
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
The overall process
HERVE BARON
© 2015 – Hervé Baron
Use this as standard, question deviations.
HERVE BARON
© 2015 – Hervé Baron
Understand the new 3D-model centered engineering process
HERVE BARON
© 2015 – Hervé Baron
Know the interfaces
between disciplines... and with Vendors
HERVE BARON
© 2015 – Hervé Baron
Understand what drives
the Project schedule
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
Table of Contents
Methods & tools
HERVE BARON
© 2015 – Hervé Baron
Use these methods as
standard, question deviations.
HERVE BARON
© 2015 – Hervé Baron
Implement powerful
procedures
HERVE BARON
© 2015 – Hervé Baron
Request meaningful progress
reports
HERVE BARON
© 2015 – Hervé Baron
Implement effective Project
Control
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide - 2nd edition
This book is destined to both:
Oil & Gas companies Project execution personnel
Oil & Gas contractors Project execution personnel
Date of publication: March, 2015.
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide 2nd edition
If your are on the Client side, i.e., contracting Engineering services, this book will help you to:
Specify to an Engineering supplier what you want: what deliverables and with what contents,
Set a standard in Engineering execution that you and your supplier can adhere to: design stages/gates, methods to be used, etc.
Specify the progress report you want, with the meaningful indicators,
Ask the right questions to assess the true progress,
HERVE BARON
© 2015 – Hervé Baron
The Oil & Gas Engineering Guide 2nd edition
If your are on the Contractor side, i.e., performing Engineering activities, this book will help you to:
Understand the work of each discipline and the overall picture,
Challenge what one discipline tells you,
Understand the critical areas,
Put in place the right methods to be successful,
HERVE BARON
© 2015 – Hervé Baron