Presentation by Mead & Hunt. From the November 13th Airport Master Plan Public Meeting.
Citation preview
WELCOME!
Airport Master Plan Public MeetingNovember 13, 2013
Where are We In the Process
What the Plan Will Include
Master Plan Topics
• Community Process• Facility / Policy Inventory• Aviation Demand Forecasts• Facility Requirements• Alternatives Analysis• Implementation Plan
Meeting Objectives
• Bring you up to date on plan progress.
• Obtain specific feedback / support for new annoyance mitigation initiatives.
• Capture some plan highlights.
1998 Master Plan
Current Master Plan Concept
Plan Comparison
Then: Airport-Driven(1998)
Now: Community Driven(2013)
• Maximum Growth • Annoyance Mitigation• More Runways • Multi-Use Hangar• All-Weather Access • Non-Aviation Uses• More T-Hangars • Technology Upgrades• Non-Aviation Uses • Box Hangars
Annoyance Mitigation
• New Runway– To avoid / reduce residential overflights
• Changes to the Primary Runway– To increase the height of airplane overflights
• Changes to the Secondary Runway– To better balance runway utilization
• Off-Airport Alternatives– To increase the range of options.
Alternatives Considered
Alternatives Dismissed
New Runway• $27.4M• Wetlands
~ WETLANDS ~
Alternatives Dismissed
1A: Extend Runway 11-29 East and Displace Landings
1B: Extend Runway 11-29 East / Shorten West
• $6.5M• Limited Benefit
Alternative 1B: Airspace Impacts
Jet Departure Profile
Piaggio Departure Profile
Runway 29, Jet Departure - Existing
Runway 29, Jet Departure - RW Alt 1
Runway 29, P180 Departure - Existing
Runway 29, P180 Departure - Alt 1
Runway 29, C172 Departure - Existing
Runway 29, C172 Departure - Alt 1
Runway 11, Jet Arrival - Existing
Runway 11, Jet Arrival – Alt 1
Runway 11, P108 Arrival - Existing
Runway 11, P108 Arrival - Alt 1
OPINION
• No significant change to height or noise
• Dismiss from consideration
Alternative 1: Runway 11-29
Alternatives Dismissed
• Widen Runway 2-20– $3.5M– Minimal change in
runway utilization
• Extend North– $5M to $15M– Significant Fill or– Pylon-bridge
construction
Alternatives Retained
Widen and extend Runway 2-20 South• $6.9M• Greater dispersion of runway utilization
Runway Selection Factors• Wind direction and velocity• Runway length • Pavement strength• Local communication efforts• Taxi distance• On course / arrival direction• Glider activity • Runway width
Runway 2-20 Utilization
DEPARTURES ARRIVALS
Existing Alt 2A Existing Alt 2A
29Piston 77% 58% ↓ 66% 47% ↓Turboprop 88% 76% ↓ 82% 64% ↓Turbo Jet 96% 88% ↓ 94% 83% ↓
2Piston 8% 16% ↑ 8% 16% ↑Turboprop 2% 8% ↑ 2% 8% ↑Turbo Jet 0.5% 6% ↑ 1% 4% ↑
20Piston 11% 22%↑ 22% 33% ↑Turboprop 6% 12% ↑ 12% 24% ↑Turbo Jet 0.5% 3% ↑ 2% 10% ↑
Runway 2-20 Utilization
CA-267 Eastbound View to NE
Existing
With Extension
CA-267 Eastbound View to NE
Existing
CA-267 Westbound View to NW
With Extension
CA-267 Westbound View to NW
CA-267 Elevated View to NW
Existing
With Extension
CA-267 Elevated View to NW
Widen and Extend Runway 2-20
OPINION / RECOMMENDATION• Extending and widening will disperse operations more
effectively• Dispersion can be influenced by TTAD actions/policy• Views of Martis Valley not impacted significantly• Proceed with implementation planning
Alternatives Retained
OFF-AIRPORT MITIGATION• Annual Funding Allocation• Current models under consideration:– Expansion of Open Space Preservation Policy– Voluntary Home Improvement (Sound Insulation)– Voluntary Home Acquisition– Additional Possibilities– Flight Track Optimization– Requires Additional Community Outreach
Arrivals DeparturesOff-Airport Alternative
June 2012
Off-Airport Alternative
• 160 homes in Zone B1
• 70 homes in Zone C
Runway 29, Jet Departure - Existing
Runway 29, Jet Departure - Straight
Runway 29, C172 Departure - Existing
Runway 29, C172 Departure - Straight
Off-Airport Mitigation
OPINION/RECOMMENDATION• Increases Options Available to Residents and District• Proceed with Implementation Planning
ITEMS TO BE CLARIFIED• Funding Prioritization / Geographic Boundaries• Disposition of Acquired Property• Policy/Legal Implications
THANK YOU