Cavity Walls
Cavity Wall Construction
Tutor Copy
What is a cavity wall?
A cavity wall is made up from:
• An outer leaf• An inner leaf• Air gap between
these leaves which usually contains insulation
Outer leaf
Cavity wall construction
Inner leaf
50mm minimum width of air gap
Section through a cavity wall
Solid Walls can let dampness into buildings.
Section through a solid wall
Why do we use cavity walling?
Cavity Walls were originally introduced to prevent Damp penetration.
Section through a cavity wall
Problems?
• Weakness: Two slender half brick / block skins are not as strong as a one brick thick solid wall.
How can this Kind of walling be strengthened?
The use of Cavity Wall Ties
Cavity Wall TiesThe walls are supported and tied into one another by means of specially designed metal ties called ‘wall ties’.
Wall Ties are made from stainless steel
Cavity Wall TiesProblems can occur when bridging the cavity, such as
water penetrating from the outer leaf to the inner leaf.
Outer leaf brickwork
Inner leaf blockwork
Wall tie
Moisture drips off wall tie
Cavity
Section through a cavity wall
Common Faults
Wall tie bent (sloping down towards Inner leaf)
Wall tie upside down
Wall tie drip touching inner leaf
Wall tie spacing’sBuilding Regs state wall ties must be positioned 450mm vertical 750mm horizontal (100mm cavity) and no more than 300mm vertically on un-bonded reveals.
5 wall ties per m2Wall ties every course up a reveal
Bridging the cavity can create problems.
Preventing Water Transfer.
The Tray DPC prevents water crossing along the top of the air-brick liner.
Section through a cavity wall
Typical components needed for bridging cavities at openings.
Tray DPC
DPC stop endVertical DPC
Weep hole
Keep the cavity clean.
Mortar droppings can gather on wall ties and at the bottom of the cavity creating a bridge for water to pass through to the inner leaf.
Section through a cavity wall
Clean Cavities
Keep the cavity clean to prevent water penetration
Section through a cavity wall
Water cannot pass the drip on the wall tie
Ensuring Cleanliness• Core Hole
Ensuring Cleanliness• Cavity Batten
Wall construction below ground level
Cavity walling below ground level:-
• Cavity wall formed with two leafs of common bricks. The external leaf will revert to facing bricks 2 course below ground level to allow the bricklayer to ensure that bond is worked out
Broken BondIf Broken Bond can not be avoided the piece should be placed in the centre of the wall, or against the reveal. No cut should be less than ½ brick
If bastard sized window and doors are used then the piece is better placed under the opening if possible.
ANY CUT SHOULD ALWAYS STAY IN THE SAME POSITION