Weducate Initiative 2015
1
PROGRESS REPORT ON THE IMPLEMENTATION OF MCMD PROJECT
BACKGROUND
On July 25th 2015, weducate initiative was awarded a project grant of GHC 2000 by Patriots Ghana
to put up a one unit classroom and provide furniture for children in Kpemale, a village under Mion
district of the Northern Region.
Presentation of the award to weducate initiative
Weducate Initiative 2015
2
WORK DONE SO FAR
Work started on August 25th, 2015. John Mbiyieba, together with a carpenter from the community
purchased the necessary materials for the furniture and the carpenter started work on the furniture
on August 28th, 2015. By September 9, 2015, the carpenter completed work on 35 dual desks. The
desks were designed to accommodate three children per seat and therefore, the 35 can adequately
cater for the 80 children in the school.
1 Sample dual desks
Weducate Initiative 2015
3
2 Sample dual desks
John also bought part of the building materials needed for putting up of a classroom. However, the
community members suggested that the building be put on hold until the heavy rains subsided, to
prevent possible collapse during building which will lead to wastage of resource. The building is
therefore, expected to take place in late October when there will be less rainfall in the area.
Weducate Initiative 2015
4
3 Cement bought for the building
4 Roofing sheet bought for the building
We are also glad to let you know that we have successfully launched our reading project dubbed
Read For Life, after several stakeholder discussions.
Weducate Initiative 2015
5
5 Meeting with Yankazia RC JHS headmaster
Weducate Initiative 2015
6
6 Mbiyieba John explaining the reading project to pupils
Weducate Initiative 2015
7
EXPENDITURE MADE SOO FAR (GHC)
EXPENDITURE ON FURNITURE
WOOD 812
NAILS
1 INCH 5
2 INCHS 10
3 INCHES 55
4 INCHES 40
TRANSPORTATION 75
CARPENTER'S
WORKMANSHIP
40
TOTAL 1037
EXPENDITURE ON BUILDING PROJECT
ROOFING SHEET 660
CEMENT 165
NAILS
3 INCHES 70
4 INCHES 40
CUPS 40
TRANSPORTATION 62
TOTAL 1037
GROSS TOTAL SO
FAR
2074
Weducate Initiative 2015
8
ITEMS YET TO BE BOUGHT FOR THE BUILDING
ITEM QUANTITY UNIT COST TOTAL
ROOFING
WOOD
1 2/3 inches 18 10.00 180.00
2 2/4 inches 12 12.00 144.00
Wood for doors and windows
3 Boards 3 20.00 60.00
4 2/4 inches 2 12.00 24.00
5 transport 30.00
6 emulsion paint 2 Liters 25.00 50.00
7 oil paint 50.00
8 thinner 10.00
TOTAL 548.00
7 Current state of the school
Weducate Initiative 2015
9
PLANS FOR COMPLETING THE REST OF THE PROJECT
The community members are very happy that the project is being implemented and are willing to
work at their best when it is time for building the classroom.
The school is currently running under the old shed as we wait for the classroom.
As soon as the classroom is put up, they will move in.
We continuously motivate the community members to commit to keeping their children in
school.
CHALLENGES
Heavy rain. We had to extend the date for building until the rain subsides
Funds. The community members are willing to contribute in terms of labour but not funds
People are willing to volunteer to teach the children but we are currently unable to take
volunteers from outside the locality due to lack of funds. We therefore depend on only one
volunteer teacher.