Association with Azmeel, Abu-Nayyan& Saudi Tumpane PROJECT098-C58 Excavation Weekly Inspection Checklist Contractor Supervisor/ Foreman: Name: Signature: Date: Legend Good Poor x Rev.0 SITE LOCATION: DATE: TIME: COMPETENT PERSON: SOIL TYPE: SOIL CLASSIFICATION EXCATION DEPTH: EXCAVATION WIDTH: General Inspection of Site Good Poor 1. Excavations, adjacent areas, and protective systems inspected by a competent person daily before the start of work. 2. Competent person has the authority to remove employees from the excavation immediately. 3. Employees protected from loose rock or soil that could pose a hazard by falling or rolling into excavation. 4. Proper PPEs worn by all employees 5. Material and equipment set back at least 1.5 meter from the edge of excavation. 6. Adequate barricades provided all around the edge of excavation. 7. Walkways and bridges over excavation are equipped with standard guardrail and toe boards 8. Adequate signage provided for deep excavation. 9. Underground utilities are inspected by concern department. 10. Adequate access given every 7.5 m to the long excavation. 11. Employees protected from cave-ins when entering or exit the excavation. 12. Precaution taken to protect employees forms the accumulation of water. 13 All tools and equipment are in good condition and properly inspected. 14. Proper shoring and sloping provided for deep excavation. 15.

Weekly excavation checklist

Embed Size (px)

Citation preview

Page 1: Weekly excavation checklist

Association with Azmeel, Abu-Nayyan& Saudi Tumpane

PROJECT098-C58

Excavation Weekly Inspection Checklist

Contractor Supervisor/ Foreman:

Name:

Signature:

Date: Legend

Good √

Poor x

Rev.0

SITE LOCATION:

DATE: TIME: COMPETENT PERSON:

SOIL TYPE:

SOIL CLASSIFICATION EXCATION DEPTH: EXCAVATION WIDTH:

General Inspection of Site Good Poor

1. Excavations, adjacent areas, and protective systems inspected by a competent person daily before the start of work.

2. Competent person has the authority to remove employees from the excavation immediately.

3. Employees protected from loose rock or soil that could pose a hazard by falling or rolling into excavation.

4. Proper PPEs worn by all employees

5. Material and equipment set back at least 1.5 meter from the edge of excavation.

6. Adequate barricades provided all around the edge of excavation.

7. Walkways and bridges over excavation are equipped with standard guardrail and toe boards

8. Adequate signage provided for deep excavation.

9. Underground utilities are inspected by concern department.

10. Adequate access given every 7.5 m to the long excavation.

11. Employees protected from cave-ins when entering or exit the excavation.

12. Precaution taken to protect employees forms the accumulation of water.

13 All tools and equipment are in good condition and properly inspected.

14. Proper shoring and sloping provided for deep excavation.

15.