CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

Embed Size (px)

Citation preview

Page 1: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

GROUP MEMBERS:

1) SITI HIJRAN BINTI ZAINAL 2011832518

2) NUR SAKINAH BT ABD HAMID 2011821644

3) NURUL AIMI BT MALEK 2011240844

4) NUR SYAZWANI BT JASNI 2011845836

GROUP : EC1106 B2

LECTURER : MR. KHAIRUL AMMAR BIN MUHD ALI

Page 2: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

INTRODUCTION

In this last semester from November 2013 until April

2014, we are given a project of double storey house. We

are decided to make a rough estimation about a unit of

double storey house and 100 unit of double storey house

construction. With this, we were choosing a plan of Semi-D

residential of Timbalan Pengarah at Kolej Matrikulasi

Banting, Selangor as our project.

Page 3: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

PROJECT DETAILS

Page 4: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

TAKING OFF

SAMPLE CALCULATION

Page 5: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

BEAMCONCRETE WORK

FORMWORK

Page 6: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

REINFORCEMENT

Page 7: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 8: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

COLUMNCONCRETE WORK

FORMWORK

Page 9: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

REINFORCEMENT

Page 10: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

SLAB

Page 11: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 12: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

PILE CAP

Page 13: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 14: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 15: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

STAIRCASE

Page 16: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 17: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 18: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 19: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

BILL OF QUANTITY

Page 20: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

BILL OF QUANTITY

Page 21: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

THE GANTT CHART

Page 22: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 23: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 24: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)
Page 25: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

S-CURVE

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

0

10000

20000

30000

40000

50000

60000

70000

80000

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2014 2015 2016

Cu

mu

lati

ve C

ost

Co

st

Cash Flow Report

Cost Cumulative Cost

Page 26: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

0

20000

40000

60000

80000

100000

120000

140000

160000

180000

0

1000

2000

3000

4000

5000

6000

7000

8000

Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26Week 28Week 30Week 32Week 34Week 36Week 38Week 40Week 42Week 44Week 46Week 48Week 50Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26Week 28Week 30Week 32Week 34Week 36Week 38Week 40Week 42Week 44Week 46Week 48Week 50Week 0Week 2Week 4Week 6Week 8Week 10Week 12Week 14Week 16Week 18Week 20Week 22Week 24Week 26

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3

2014 2015 2016

Cu

mu

lati

ve C

ost

Co

stCash Flow Report

Cost Cumulative Cost

Page 27: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

DISCUSSION

The grand total of the material cost that we gained from the calculated taking off and the bill of quantities is RM 148,664.08. After including 11% from JKR References PulauPinang the actual material cost is RM RM 164,997.13.

The Gantt chart and S-curve shows the duration and construction cost of 100 unit of double storey house which is shows the time started the project until it finished.

Page 28: CIVIL ENGINEERING CONSTRUCTION PROJECT (ECM 317)

CONCLUSION

In conclusion, the knowledge that we gained from doing this project really expose us the important of knowing the real specific of work. Taking off and the bill of quantity together with the Gantt chart and s-curve also be considered in the taking off in order to get estimated value for the each project. Thus, the specific cost needed for a unit of house have been estimated.