117
David H Moloney 14 th August 2016 Sea Port Construction, Project Execution Plan Details of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly. http:// www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Sea Port . This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Video Presentation is innovative and has many beneficial uses. Video https://www.youtube.com/watch?v=6_Aco_GPO8I

Sea Port Construction, Project Execution Plan

Embed Size (px)

Citation preview

Page 1: Sea Port Construction, Project Execution Plan

David H Moloney

14th August 2016

Sea Port Construction, Project Execution PlanDetails of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.

http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan

Brief Description

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Sea Port .

This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.

High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)This Video Presentation is innovative and has many beneficial uses.

Video https://www.youtube.com/watch?v=6_Aco_GPO8I

Page 2: Sea Port Construction, Project Execution Plan

Contents

ⓒ David H Moloney

Page 3: Sea Port Construction, Project Execution Plan

Introduction

Page 4: Sea Port Construction, Project Execution Plan

Quay WallQ

uay W

all

Page 5: Sea Port Construction, Project Execution Plan

Quay WallQ

uay W

all

Brief Description

The quay wall is constructed using precast reinforced concrete hollow blocks that weigh up to 160 tonnes. The blocks were cast in the on-site precast yard and loaded onto barges at the temporary loading jetty that had a 200 tonne capacity gantry crane.

A screeding frame that extended from the sea bet to above water was used to place the bedding layer to the correct level.Up to 22 blocks were placed per day using a barge with a crane.Part of the coping beam was cast in-sit-u in sections using concrete pumps positioned on the reclaimed land behind the quay wall.

Page 6: Sea Port Construction, Project Execution Plan

Sequence & Methods to Construct Quay WallQ

uay W

all

3D Animation

Page 7: Sea Port Construction, Project Execution Plan

Quay-wall

ⓒ David H Moloney

Placing Precast Quay Blocks Placing Precast Quay Blocks

Screed Frame for preparing Granular Foundation Placing Precast Quay Blocks

Page 8: Sea Port Construction, Project Execution Plan

Quay Wall Beam

Page 9: Sea Port Construction, Project Execution Plan

Screed FrameM

iscella

ne

ous

Brief Description

Duqm, Oman

Page 10: Sea Port Construction, Project Execution Plan

Mooring Bollards & Marine FendersM

iscella

ne

ous

Page 11: Sea Port Construction, Project Execution Plan

Marine Equipment ⓒ David H Moloney

Page 12: Sea Port Construction, Project Execution Plan

Drawing – Quay Wall Cross Section

Page 13: Sea Port Construction, Project Execution Plan

Breakwater & WavewallB

reakw

ate

r &

Wavew

all

Page 14: Sea Port Construction, Project Execution Plan

Breakwater & WavewallB

reakw

ate

r &

Wavew

all Brief Description

The breakwater is constructed using core rock, rock armour, precast armour units and geotextile.The core rock is placed using split hopper barges in deep water and by lorry tipping and dozers in shallow water where the risk of slippage is minimal.The precast armour units are placed using crawler cranes fitted with a real-time visual aid system that enabled 70 placements per day.The wave wall is cast in-sit-u in 6 metre long sections.

Page 15: Sea Port Construction, Project Execution Plan

Sequence & Methods to Construct Breakwater & WavewallB

reakw

ate

r &

Wavew

all

Page 16: Sea Port Construction, Project Execution Plan

Breakwatersⓒ David H Moloney

Filling Barge with Rock – Temporary Jetty Placing Rock Fill

Breakwater under Construction Placing Rock Armour

Page 17: Sea Port Construction, Project Execution Plan

Breakwaters

Placing Rock Fill

Breakwater under Construction

Page 18: Sea Port Construction, Project Execution Plan

Barges for Rock Fill

Page 19: Sea Port Construction, Project Execution Plan

Geotextile

Page 20: Sea Port Construction, Project Execution Plan

Precast Sea Armour

Placing Armour

Page 21: Sea Port Construction, Project Execution Plan

Rock Sea Armour

Placing Armour

Page 22: Sea Port Construction, Project Execution Plan

Sea Wall

Page 23: Sea Port Construction, Project Execution Plan

Drawing – Breakwater Cross Section

Quarry Run Rock Fill

Page 24: Sea Port Construction, Project Execution Plan

Drawing – Breakwater Cross Section

Quarry Run Rock Fill

Wave Wall

Geotextile

Rock Armour 0.5 - 1 ton

Precast Armour

Rock Armour 1 - 3 ton

Page 25: Sea Port Construction, Project Execution Plan

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Page 26: Sea Port Construction, Project Execution Plan

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty Brief Description

Full-scale sample castings are constructed to demonstrate and document that all the requirements of the concrete and the execution of the work are fulfilled using the actual methods and performed by personnel that will carry out the future castings. One concrete component of each type is produced for approval. The approved castings were retained in a dedicated area for quality assurance purposes.

All works were inspected in accordance with the Inspection & Test Plan on an ongoing basis, in accordance with the site Project Quality Plan. The ITP set out in matrix form the sequence of inspection steps, the governing document (specification, standards), the standard to be achieved, the persons witnessing and the supporting documents to be produced.

Page 27: Sea Port Construction, Project Execution Plan

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Page 28: Sea Port Construction, Project Execution Plan

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Page 29: Sea Port Construction, Project Execution Plan

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Page 30: Sea Port Construction, Project Execution Plan

Pre-casting Quay Blocks

Page 31: Sea Port Construction, Project Execution Plan

Precast Sea Armour

Shutters for Precast Sea Armour Shutters for Precast Sea Armour

Page 32: Sea Port Construction, Project Execution Plan

Quarry & Aggregate Production

3D image to show Sequence, Method & Plant.

ⓒ David H Moloney

Page 33: Sea Port Construction, Project Execution Plan

Quarry

Page 34: Sea Port Construction, Project Execution Plan

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Page 35: Sea Port Construction, Project Execution Plan

Concrete Batching Yard

Silos, Ice Flake Plant, Chilled water, Mixer

Storage bays for aggregates

Page 36: Sea Port Construction, Project Execution Plan

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Page 37: Sea Port Construction, Project Execution Plan

Reinforcement Cutting & Bending

ⓒ David H Moloney

Concre

te

Page 38: Sea Port Construction, Project Execution Plan

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Page 39: Sea Port Construction, Project Execution Plan

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Page 40: Sea Port Construction, Project Execution Plan

Concrete MixG

enera

l Item

s

A concrete mix contains 5 major

elements: cement, water, coarse

aggregates, fine aggregates (sand) and

air in different proportion. Additional

elements such as pozzolanic materials (fly

ash, silica fumes or slag) and chemical

admixtures can also be incorporated to

the mix to increase its properties.

Page 41: Sea Port Construction, Project Execution Plan

Vibrating Concrete

ⓒ David H Moloney

Concre

te

Page 42: Sea Port Construction, Project Execution Plan

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion

Page 43: Sea Port Construction, Project Execution Plan

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion Brief Description

Dredgers are marine vessels used to excavate and fill under water.

Types

1. Cutter Suction Dredgers are used to dredge hard soils by cutting

and breaking up the soil using a rotating head at the end of a pipe

which is lowered onto the sea bed. The fragmented material is

sucked and pumped either into a hopper barge or through a floating

pipeline. During operation the dredger is anchored by a spud that

allows the cutting head to swing in an arc.

2. Trailing Suction Hopper Dredgers are used to dredge soft and

loose soils, gravels and silts. There are two suction drag heads

which are lowered onto the sea bed. These move with the dredger

along the sea bed. The dredged material is sucked and pumped

either into the hopper or through a floating pipeline to a discharge

area.

Page 44: Sea Port Construction, Project Execution Plan

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion

Page 45: Sea Port Construction, Project Execution Plan

Dredger - Trailing Suction D

red

gin

g &

Recla

ma

tion

Boskalis Netherlands

Page 46: Sea Port Construction, Project Execution Plan

Dredger - Cutter Suction D

red

gin

g &

Recla

ma

tion

Boskalis Netherlands

Page 47: Sea Port Construction, Project Execution Plan

Dredger - Backhoe D

red

gin

g &

Recla

ma

tion

Page 48: Sea Port Construction, Project Execution Plan

Rock - Excavability

The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.

ⓒ David H Moloney

Page 49: Sea Port Construction, Project Execution Plan

Vibro Compaction - Fill behind Quay

Page 50: Sea Port Construction, Project Execution Plan

Vibro Compaction - Fill behind Quay

Ground Improvement using deep vibro-compaction.

Purpose is to provide protection against liquefaction during a seismic

event. Also to provide a specified minimum ground bearing capacity.

Vibro-compaction was use to compact the Dubai man made islands

that were constructed from dredged sand.

Equipment.

Vibroflot with extension tube, hydraulic power pack mounted on crane,

diesel engine driven water jetting pumps, compressors, crawler cranes

60 tonne capacity, water tank, de-watering pump

Page 51: Sea Port Construction, Project Execution Plan

Vibro Compaction - Fill behind Quay

3D image to show Sequence, Method & Plant.

David H Moloney

ⓒ David H Moloney

Page 52: Sea Port Construction, Project Execution Plan

Vibro CompactionV

ibro

Com

pa

ction

Page 53: Sea Port Construction, Project Execution Plan

Surv

eyin

g &

settin

g O

ut

Survey & Setting Out

Page 54: Sea Port Construction, Project Execution Plan

Surv

eyin

g &

settin

g O

ut

Brief Description

Ope

Survey & Setting Out

Survey Tower

Page 55: Sea Port Construction, Project Execution Plan

Setting out & Surveying

Page 56: Sea Port Construction, Project Execution Plan

Setting out & Surveying

Page 57: Sea Port Construction, Project Execution Plan

Port OperationP

ort

Opera

tio

n

Page 58: Sea Port Construction, Project Execution Plan

Port OperationP

ort

Opera

tio

n

Page 59: Sea Port Construction, Project Execution Plan

Port OperationP

ort

Opera

tio

n

Page 60: Sea Port Construction, Project Execution Plan

Port OperationP

ort

Opera

tio

n

Page 61: Sea Port Construction, Project Execution Plan

Site Facilities & Temporary WorksS

ite F

acili

tie

s &

tem

pora

ry W

ork

s

Page 62: Sea Port Construction, Project Execution Plan

Site Facilities & Temporary WorksS

ite F

acili

tie

s &

tem

pora

ry W

ork

s

Page 63: Sea Port Construction, Project Execution Plan

Welfare Facilities

ⓒ David H Moloney

Genera

l Item

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Page 64: Sea Port Construction, Project Execution Plan

Site Hoarding examples

ⓒ David H Moloney

Genera

l Item

s

Page 65: Sea Port Construction, Project Execution Plan

Wheel Wash Drive-through

ⓒ David H Moloney

Genera

l Item

s

Page 66: Sea Port Construction, Project Execution Plan

Wheel Wash Drive-throughG

enera

l Item

s

Page 67: Sea Port Construction, Project Execution Plan

Temporary Electricity Supply & Tower Lights

Generators

Genera

l Item

s

Page 68: Sea Port Construction, Project Execution Plan

Dewatering

ⓒ David H Moloney

Genera

l Item

s

Page 69: Sea Port Construction, Project Execution Plan

Concrete Batching Yard 3 Nr MixersG

enera

l Item

s

Page 70: Sea Port Construction, Project Execution Plan

Health, Safety & EnvironmentalH

ealth, safe

ty &

environ

menta

l

Page 71: Sea Port Construction, Project Execution Plan

Emergency Phone Numbers & Response

Page 72: Sea Port Construction, Project Execution Plan

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Page 73: Sea Port Construction, Project Execution Plan

Site Safety Posters examples

Page 74: Sea Port Construction, Project Execution Plan

Safety Precautions

Page 75: Sea Port Construction, Project Execution Plan

Personal Protective Equipment (PPE)H

ealth,

Safe

ty &

Environm

ent

Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection

Page 76: Sea Port Construction, Project Execution Plan

Safety Training on Site M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 77: Sea Port Construction, Project Execution Plan

Safety Training Matrix M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 78: Sea Port Construction, Project Execution Plan

Emergency Response Drill H

SE

Drills and exercises are used to rehearse anticipated emergency scenarios

Page 79: Sea Port Construction, Project Execution Plan

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Page 80: Sea Port Construction, Project Execution Plan

Hazardous Substances Symbols H

ealth,

Safe

ty &

Environm

ent

COSHH stands for the Control of Substances Hazardous to Health

Shown are the new hazard symbols

Page 81: Sea Port Construction, Project Execution Plan

Water Pollution PreventionG

enera

l Item

s

Page 82: Sea Port Construction, Project Execution Plan

Segregation of Waste H

ealth,

Safe

ty &

Environm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Page 83: Sea Port Construction, Project Execution Plan

Putting Waste Concrete to use

ⓒ David H Moloney

Health,

Safe

ty &

Environm

ent

Precast bases for signs and hoarding, Precast blocks for walls.

Page 84: Sea Port Construction, Project Execution Plan

AdministrationA

dm

inis

tration

Page 85: Sea Port Construction, Project Execution Plan

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 86: Sea Port Construction, Project Execution Plan

Staff Responsibility Matrix

Page 87: Sea Port Construction, Project Execution Plan

Staff Directory

Brief Description

List of staff and their

contact details

Page 88: Sea Port Construction, Project Execution Plan

Daily Work Record

Brief Description

Daily Work Records showing the

allocation of resources, materials and

work activities carried out daily.

Page 89: Sea Port Construction, Project Execution Plan

Quotations Comparison Sheet

Page 90: Sea Port Construction, Project Execution Plan

Filing System

Page 91: Sea Port Construction, Project Execution Plan

Quality AssuranceQ

ualit

y A

ssura

nce

Page 92: Sea Port Construction, Project Execution Plan

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Page 93: Sea Port Construction, Project Execution Plan

Laboratory

ⓒ David H Moloney

Asphalt P

avin

g

Page 94: Sea Port Construction, Project Execution Plan

Programme & Progress MonitoringP

rogra

mm

e &

Pro

gre

ss M

onitori

ng

Page 95: Sea Port Construction, Project Execution Plan

Progress Monitoring & Reporting - Dashboard

ⓒ David H Moloney

Dashboard is a single page, graphical representation of current progress and historical trends

Page 96: Sea Port Construction, Project Execution Plan

Histogram Charts for Resources & Outputs

Manpower per Discipline Concrete per Location

Numbers for each month of the Project Quantity for each month of the Project

ⓒ David H Moloney

Page 97: Sea Port Construction, Project Execution Plan

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 98: Sea Port Construction, Project Execution Plan

Other ProjectsO

ther

Pro

jects

Page 99: Sea Port Construction, Project Execution Plan

Brief Description

Jetty for Kuwait Causeway

Other Projects

Page 100: Sea Port Construction, Project Execution Plan

Jetty for Kuwait Causeway

Other Projects

Page 101: Sea Port Construction, Project Execution Plan

Brief Description

Concrete Batching Plant on Barge.

Kuwait Causeway

Other Projects

Page 102: Sea Port Construction, Project Execution Plan

Kuwait Causeway Offshore Piling

Other Projects

Page 103: Sea Port Construction, Project Execution Plan

Concrete Batching Plant on Barge. Kuwait Causeway

Other Projects

Page 104: Sea Port Construction, Project Execution Plan

Pile Driving

Other Projects

Page 105: Sea Port Construction, Project Execution Plan

Temporary Bridge

Other Projects

Page 106: Sea Port Construction, Project Execution Plan

Temporary Bridge Piling

Other Projects

Page 107: Sea Port Construction, Project Execution Plan

Brief Description

Marine Piles

Other Projects

Page 108: Sea Port Construction, Project Execution Plan

Brief Description

Screed Frame. Morocco

Other Projects

Page 109: Sea Port Construction, Project Execution Plan

Brief Description

Quay Wall Ruwais UAE

Other Projects

Page 110: Sea Port Construction, Project Execution Plan

Brief Description

Dubai Palm Island, Rock Armour

Other Projects

Page 111: Sea Port Construction, Project Execution Plan

Brief Description

Dubai Creek, strengthen

quay wall with sheet piles and

ground anchors

Other Projects

Page 112: Sea Port Construction, Project Execution Plan

Brief Description

Abu Dhabi Quay Wall

Other Projects

Page 113: Sea Port Construction, Project Execution Plan

Brief Description

St. Croix Bridge

Other Projects

Page 114: Sea Port Construction, Project Execution Plan

Brief Description

Cofferdams examples

Other Projects

Page 115: Sea Port Construction, Project Execution Plan

Jebel Ali DubaiOther Projects

Page 116: Sea Port Construction, Project Execution Plan

Jebel Ali Dubai

Ports

Muscat Omani

Dublin Cork

Page 117: Sea Port Construction, Project Execution Plan

Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I