28
SUMMAR TRANING Larsen & Toubro Ltd. Jaipur institute & engineering Technology kukas jaipur

Vikash9887106700 l&t ppt

Embed Size (px)

Citation preview

Page 1: Vikash9887106700 l&t ppt

SUMMAR TRANINGLarsen & Toubro Ltd.

Jaipur institute & engineering Technology kukas

jaipur

Page 2: Vikash9887106700 l&t ppt

A PRESENTATION

ON WDFC Project

Submitted to Submitted by Vikash kumar Yadav

12EJACE117

Page 3: Vikash9887106700 l&t ppt

DETAILS OF PROJECT

Name of project:- Western Dedicate Freight Corridor

Cost of project:-6700 crore

Page 4: Vikash9887106700 l&t ppt

CONTENTSPREPARING THE TRACKBEDLAYING THE TRACKJOINING THE TRACK SECTIONADDING BALLASTSLEEPERSRAILS

Page 5: Vikash9887106700 l&t ppt

Preparing the Track bedThe track bed is carved into the landscape, using scrapers, graders, bulldozers and other heavy machinery layer of compact gravel is spread on the track bed. This, after being compacted by rollers, provides an adequate surface for vehicles with Tyres.

Page 6: Vikash9887106700 l&t ppt

Laying the track This time, the crane rides on the two rails that were just laid alongside the temporary track. A train of flatcars, half loaded with LGV sleepers, arrives at the site. It is pushed by a special diesel locomotive, which is low enough to fit underneath the gantry cranes. The cranes remove the panels of temporary track, and stack them onto the empty half of the sleeper train. Next, they pick up sets of 30 LGV sleepers, pre-arranged with the proper spacing using a special fixture. The sleepers are laid on the gravel bed where the panel track was. The sleeper train leaves the worksite loaded with sections of panel track.

Page 7: Vikash9887106700 l&t ppt

Joining track sectionsThe sections of rail are welded together using thermite. Conventional welding (using some type of flame) does not work well on large metal pieces such as rails, since the heat is conducted away too quickly. Thermite is better suited to this job. It is a mix of aluminium powder and rust (iron oxide) powder, which reacts to produce iron, aluminum oxide, and a great deal of heat, making it ideal to weld rail.

Page 8: Vikash9887106700 l&t ppt

Adding ballastA first layer of ballast is dumped directly onto the track, and a tamping-lining-levelling machine, riding on the rails, forces the stones underneath the sleepers. Each pass of this machine can raise the level of the track by 8 cm (3 in), so several passes of ballasting and of the machine are needed to build up a layer of ballast at least 32 cm (1 ft) thick under the sleepers. The ballast is also piled on each side of the track for lateral stability. The machine performs the initial alignment of the track

Page 9: Vikash9887106700 l&t ppt

Finishing construction

Now that the first track is almost complete, work begins on the adjacent track. This time, however, it is not necessary to lay a temporary track. Trains running on the first track bring the sleepers, and then the rail, which is unloaded directly onto the sleepers by dispensing arms that swing out to the proper alignment. The Nabla fasteners are secured, and the ballast is stuffed under the track as before.

Page 10: Vikash9887106700 l&t ppt

PILES

A slender, structural member consisting steel or concrete or timber. It is installed in the ground to transfer the structural loads to soils at some significant depth below the base of the structure.

Page 11: Vikash9887106700 l&t ppt

PILES

Page 12: Vikash9887106700 l&t ppt

PILES FOUNDATION IS USED WHEN:

The soil near the surface doesn’t have sufficient bearing capacity (weak) to support the structural loads. The estimated settlement of the soil exceeds tolerable limits Differential settlement due to soil variability or non-uniform structural loads is excessive Excavations to construct a shallow foundation on a firm soil are difficult or expensive.

Page 13: Vikash9887106700 l&t ppt

BALLAST

Ballast is the granular material usually broken stone or bricks single and kanker, gravel and sand placed and packed and around the sleeper to transmit Load from sleeper to formation Layer.Size = 20mm – 65mm

Page 14: Vikash9887106700 l&t ppt
Page 15: Vikash9887106700 l&t ppt

SleepersSleepers are members generally laid transverse

to the rails, on which the rails are fixed to

transfer the loads from the rails to the ballast

and the subgrade.

Page 16: Vikash9887106700 l&t ppt

Types of Sleepers

Wooden SleepersMetal SleepersConcrete Sleepers

Page 17: Vikash9887106700 l&t ppt
Page 18: Vikash9887106700 l&t ppt

Concrete Sleepers

Page 19: Vikash9887106700 l&t ppt

Metal Sleeper

Page 20: Vikash9887106700 l&t ppt

RAILS

Page 21: Vikash9887106700 l&t ppt

Types of Rails :-

The rails used in the construction of railway track can be divided into the following three types :

(1) Double Headed Rails (D.H. Rail)

(2) Flat Footed Rails (F.F. Rail)

(3) Bull Headed Rails (B.H. Rail)

Page 22: Vikash9887106700 l&t ppt

THE RAILS HAVING THEIR HEAD AND FOOT OF

SAME DIMENSIONS ARE KNOWN AS DOUBLE

HEADED RAIL (D.H.).

1. Double Headed Rail :-

Page 23: Vikash9887106700 l&t ppt
Page 24: Vikash9887106700 l&t ppt

2. FLAT FOOTED RAILS :-

The rail section having their foot

rolled to a flat are known as

flat footed rails.

Page 25: Vikash9887106700 l&t ppt
Page 26: Vikash9887106700 l&t ppt

3. BULL HEADED RAIL :

The rails sections having their head of

more dimension then that of their foot

are known as bull headed rails (B.H.).

Page 27: Vikash9887106700 l&t ppt
Page 28: Vikash9887106700 l&t ppt

Thank You