Upload
geoffrey-jackson
View
42
Download
1
Embed Size (px)
Citation preview
An Innovative Australian Design Paving The Way For
Reduced Road Fatalities and Sustainable Road Management
Mark Pilgrim - Stabilcorp
OF FATAL CRASHES IN AUSTRALIA
OCCUR ON RURAL ROADS
PEOPLE KILLED ANNUALLY IN
RURAL AREAS
In the year 2000, the per capita risk of dying or being hospitalised in a rural environment compared with an urban crash was 4 times.
TIMES HIGHER
The most frequent casualty crash
type on rural roads is run off
road crashes, equating to 60%.
Characteristics of Rural Casualty Crashes
There are many factors associated with rural road crashes
They are;
lower quality road conditions (e.g. less shoulder width, unsealed surface)
the interaction of this environment with the driver and negotiating curves
inappropriate speed for the conditions.
Shoulder Width
Adding an additional 1-2m wide
gravelled surface is associated with up
to a 50% reduction in run off road
casualty crashes.
This percentage reduction converts
into the potential for approximately
5000 less run off road cashes per year.
Road Shoulder Widening
Black Spot Funding
Narrow shoulders or no road shoulders are a common feature of the Australian
rural road environment.
The Australian Government Black Spot programme targets those road
locations where crashes are occurring.
The criteria to be considered for Black Spot funding requires that two
casualty crashes occur over five years or 0.13 casualty crashes per km over 5
yrs.
In the 2015/2016 year $16 million was allocated to include shoulder widening
and realignment as part of the project.
The Black Spot programme has found that fatal and casualty crashes are
reduced at treated sites by 30%, equalling 1 life saved per 84 project.
The ShoulderMaster
A universal skid steer attachment
designed for rehabilitating and widening
the shoulders of roads up.
The ShoulderMaster concept was
developed by Stabilcorp Pty Ltd who are
a road maintenance contracting company
on the Mid North Coast of NSW.
Stabilcorp’s core business is repairing
and maintaining Local Government rural
and regional roads in NSW.
The ShoulderMaster has been developed
to address damaged and dangerous road
shoulders, and repair them efficiently
and cost effectively.
2014
Stabilcorp staff commenced the design
process of the ShoulderMaster
January 2015
Manufacturing of prototype commenced
at Wauchope, NSW
Early May 2015
Prototype complete after 2000 hours of
design and fabrication
Mid May 2015
Prototype exhibited at IPWEA’s Civinex,
Eastern Creek NSW
June 2015
Trialed successfully at various Council sites
July/August 2015
Commenced commercial production
November 2015
First commercial unit available for sale
ShoulderMaster Operations
The ShoulderMaster can widen road
shoulders from 0.5m to 1.5M and can
incorporate grades of up to 5%.
A large hopper delivers the granular or
asphaltic material via a conveyor to the
shoulder area.
The ShoulderMaster's main operations are
remote controlled.
On a 1m wide shoulder widening at
150mm deep ShoulderMaster can
deliver 400m per hour of road
shoulder material.
Cost Savings Analysis
An independent report was undertaken in 2015 in regards to the savings the ShoulderMaster can deliver versus traditional methods of shoulder repair.
In traditional operations that adopt the use of a grader to remove shoulder material and spread new material, the new gravel material is tipped onto the roadway and graded into the excavated area. This method can result in damaged road pavement and does not give a consistent pavement depth to be then compacted.
Initially the most notable benefit of the ShoulderMaster process is the limited time that the road is required to be restricted to traffic and the overall safety of the process. According to the author, the minimum time taken by Council to undertake any shoulder work on a 300m section of road is three (3) days whereas the ShoulderMaster process takes only one (1) day for the same section.
Furthermore, the skid steer mounted ShoulderMaster system is operated by remote control with one man controlling the cross fall of material placement, layer thickness, shoulder width and delivery speed of the material.
Even if some of the material can be re-used for subbase pavement (say 50% is deemed suitable), this still requires work on additional road width that was not required. The ShoulderMaster process can undertake shoulder strengthening works from a minimum width of 0.5m to 1.5m thus saving valuable pavement material and limiting the occupation of the travel lane of the road.
The excavation of the shoulder using the ShoulderMaster system is undertaken through profiling of a trench which is a rapid process that limits the contamination of common material into the gravel shoulder and leaves the subbase of the trench relatively undisturbed. This means that profiling spoil can be re-used in other minor road re-sheeting works, for select fill and if of a high enough standard can be used for subbase.
Further, the subgrade needs only to be proof rolled to ensure that no soft spots are present. The normal Council operation of rip and remove is slower and leaves a trench, which is not of constant width, is not accurately controlled for depth and leaves a loose and uneven subgrade. This results in an uneven bitumen edge which must be trimmed and a loose and uneven subgrade which must be trimmed and compacted.
Table 1 shows a selection of different shoulder widening options using either a grader or a skid steer loader for various shoulder reconstruction widths and compares the cost of the traditional method with the ShoulderMaster process. It is evident from Table 1 below that the ShoulderMaster process demonstrates that significant savings can be achieved over the current Council processes and in all cases results in over a 50% reduction in cost. All options shown in the table below would require only one (1) day for completion prior to holding for sealing if the ShoulderMaster process is used.
In April 2016 the ShoulderMaster was utilised to lay 1400m of shoulder at Forbes in 2 days, which traditionally would have taken up to 5 days to undertake the same works.
Cost Savings Analysis
Option No Description of work
Traditional
method
($A/m2)
ShoulderMaster
method ($A/m2)
Saving
($A/m2)
% Cost
saving
1a Grader widening of shoulder 1.0m wide no pavement re-use $241.46 $78 $163.46 67.7
1b Grader widening of shoulder 1.0m wide with pavement re-use $200.90 $72 $128.9 64.2
2a Grader widening of shoulder 1.5m wide no pavement re-use $160.97 $62 $98.97 61.5
2b Grader widening of shoulder 1.5m wide with pavement re-use $133.93 $53 $80.93 60.4
3a Excavator widening of shoulder 0.5m wide no pavement re-use $344.10 $150 $194.24 56.4
3b Excavator widening of shoulder 0.5m wide with pavement re-use $330.75 $138 $192.89 58.3
4a Excavator widening of shoulder 1.0m wide no pavement re-use $205.35 $78 $127.35 62.0
4b Excavator widening of shoulder 1.0m wide with pavement re-use $191.09 $72 $119.09 62.3
5a Excavator widening of shoulder 1.5m wide no pavement re-use $145.94 $62 $83.94 57.5
5b Excavator widening of shoulder 1.5m wide with pavement re-use $131.68 $53 $78.68 59.8
Energy Savings Analysis
Increased efficiency and cost savings result in an energy saving of over 70%.
This can be quantified by comparing the plant used in both the traditional
processes and ShoulderMaster processes.
For a comparable unit rate for the work option 5a was used for comparison.
5a = Excavator widening of shoulder 1.5m wide no pavement re-use
The traditional method uses 2024ltrs of fuel versus 540ltrs of fuel by the
ShoulderMaster to undertake the same works.
This results the ShoulderMaster method using approximately 26% of the fuel
that the traditional method uses.
Energy Savings Analysis
Plant Item Fuel use (litres/hr)Council process
Machine days
ShoulderMaster
Machine days
Council fuel
consumption (litres)
ShoulderMaster fuel
consumption
(litres)
Excavator 25 3.5 - 700 0
Tandem tip trucks 9 3.5 2 252 144
Skid steer loader 20 4 1 640 160
Roller 10 3 1 240 80
Wirtgen profiler 25 - 0.5 0 100
Water truck 8 3 1 192 64
Total fuel consumption 2024 548
Energy saving = 1 – ShoulderMaster fuel consumption = (1 – (548/2024)) x 100 = 72.9% energy saving
Council process fuel consumption
Case Study 1: Nelson Bay Road
Client : RMS and Port Stephens Council
The Problem
• The client required widening of 1400m
of the eastbound carriageway of
Nelson Bay Road by 2m.
• This road regularly experiences heavy
volumes of traffic and needed to
remain open for the duration of the
works.
• Traditional methods of widening would
have taken at least 5–6 days.
Case Study 1: Nelson Bay Road
Client : RMS and Port Stephens Council
The Solution
• The trench was excavated out at 2m
wide by 300mm deep and was filled
with asphalt profiling’s using the
ShoulderMaster.
Case Study 1: Nelson Bay Road
Client : RMS and Port Stephens Council
The Result
• The works were completed in 3 days
laying a total of 1400m at 2m wide and
a depth of 300mm.
• Traditional Method = $25/m2
• ShoulderMaster Method = $15/m2
Case Study 2: Pacific Highway Upgrade
Client: McConnell Dowell/OHL JV
The Problem
• The client needed to place verge
material along the Kempsey to
Kundabung section of the Pacific
Highway Upgrade.
• The works consisted of placing verge
material in 2 layers at 225mm deep by
2.5m wide.
Case Study 2: Pacific Highway Upgrade
Client: McConnell Dowell/OHL JV
The Solution
• The ShoulderMaster’s screed extended
out 1.5m and was followed by a second
skid steer with a grader blade
attachment to spread the material a
further 1m in width.
• This process was repeated twice to
achieve the correct depth.
Case Study 2: Pacific Highway Upgrade
Client: McConnell Dowell/OHL JV
The Result
• The ShoulderMaster was laying on
average 12 tonne of 40mm granular
material in 4.5 minutes.
• On average the ShoulderMaster was
placing in excess of 800 tonnes of
verge material every day.
Stabilcorp’s ShoulderMaster method of shoulder widening and repair, has demonstrated
over the past 12 months working with Local Government, State Road Authorities and
Tier One Contractors that the use of the ShoulderMaster method of shoulder repair is
up to 50-60% more cost effective than traditional methods of shoulder widening and
repair.
If road authorities had $100,000 budgeted for shoulder widening, at 1m wide and
250mm-300mm deep, approximately 1400 lineal metres of road can be repaired and
widened using the ShoulderMaster compared with approximately 500 lineal metres if
the repair was undertaken with the traditional method.
Some options of traditional shoulder repair can take up to 3 days to complete versus
just the 1 day using the ShoulderMaster method of shoulder repair.
Conclusion
The reduced use of construction plant, labour and equipment and reduced time to
undertake works has resulted in increased efficiency and cost savings due to the
reduction in the consumption of fossil fuel, with an energy saving of over 70%
Provision of unsealed shoulders defined as a 1-2m wide gravelled surface, was
associated with up to a 50% reduction in run off road casualty crashes. This percentage
reduction converts into the potential for approximately 5,000 less run off road casualty
crashes per year.
Local Government has an opportunity to apply for funding for shoulder widening
projects under the Federal Governments Black Spot program. The program has reduced
fatal and casualty crashes by 30% in some instances, which equals one life per year for
every 84 projects.
Widening narrow shoulders with the ShoulderMaster method is indeed a proven way of
reducing the probability of run off crashes and reducing the ever increasing road toll.
References
1. Austroads, 2015, “Road Geometry Study for improved Rural Safety”, AP-T295-15, Austroads, Sydney, NSW.
2. Stephen P McElroy, 2015, “Independent Review of ShoulderMaster SM1500 Process and Conventional Council Shoulder Widening and Sealing Process”
3. Austroads, 2005, “Road Safety in Rural and Remote Areas of Australia”, AP-R273-05, Austroads, Sydney, NSW.
4. Austroads, 2014a, “Improving roadside safety: summary report”, AP-R437-14, Austroads, Sydney, NSW.
5. Austroads, 2010, “Infrastructure/speed limit relationship in relation to road safety outcomes”, AP-T141-10, Austroads, Sydney, NSW.
6. Austroads, 2014b, Model national guidelines for setting speed limits at high-risk locations”, AP-R455-14, Austroads, Sydney, NSW.
7. Hon. John Cobb MP, 2015, “$53.5 Million to fix local Black Spots in NSW”, Minister for Infrastructure and Regional Development, Media Release, http://www.minister.infrastructure.gov.au/jb/release/2015/April/jb030_2015.aspx