Upload
amarillo-gold-corp
View
419
Download
4
Tags:
Embed Size (px)
DESCRIPTION
Pre-Feasibility Study updates included.
Citation preview
AMARILLO GOLD
Emerging Gold Producer in Brazil
Source: Amarillo
AGC: TSX-V72A: Frankfurt
December 2011
The Qualified Persons for Amarillo are Frank Baker, M. IOM3 and MAusIMM. and Buddy Doyle MAusIMM
AMARILLO GOLD
These presentation materials (“the Presentation Materials”) are being supplied to you for information purposes only on Amarillo Gold. (the “Company”). These Presentation Materials have been prepared by and are the sole responsibility of the Company. The Company have taken all reasonable care to ensure that the facts stated herein are true to the best of their knowledge, information and belief.
These Presentation Materials are being distributed only to and are directed at (a) persons who have professional experience in matters relating to investments being investment professionals as defined in Article 19(5) of the Financial Services and Markets Act 2000 (Financial Promotion) Order 2001 (the “FPO”), (b) high net worth companies, unincorporated associations and other bodies within the meaning of Article 49 of the FPO or (c) persons to whom it may otherwise lawfully be communicated (together “Relevant Persons”). Any person who is not a Relevant Person or who does not have professional experience in the matters relating to investments should not act or rely on this document or any of its contents.
These Presentation Materials do not constitute, or form part of, a prospectus relating to the Company, nor do they constitute or contain any invitation or offer to any person to underwrite, subscribe for, otherwise acquire, or dispose of any shares in the Company or advise persons to do so in any jurisdiction, nor shall it, or any part of it, form the basis of or be relied on in any connection with any contract. No reliance may be placed for any purpose whatsoever on the information or opinions contained in this document or on its completeness and no liability whatsoever is accepted for any loss howsoever arising from any use of this document or its contents otherwise in connection therewith. Prospective investors are encouraged to obtain separate and independent verification of information and opinions contained in the Presentation Materials as part of their own due diligence.
By accepting these Presentation Materials, the Recipient agrees that the information contained herein or sent herewith or made available is for information purposes only. Without prejudice to the foregoing, neither the Company, nor its advisers nor its representatives accept liability whatsoever for any loss howsoever arising, directly or indirectly, from use of this document or its contents or otherwise arising in connection therewith.
The distribution of these Presentation Materials in certain jurisdictions may be restricted by law and persons into whose possession these Presentation Materials come should inform themselves about, and observe, any such restrictions. Any failure to comply with these restrictions may constitute a violation of the laws of any such other jurisdictions.
Some statements contained in these Presentation Materials or in documents referred to therein are or may be forward-looking statements. Actual results may differ from those expressed in such statements, depending on a variety of factors. Past performance of the Company or its shares cannot be relied on as a guide to future performance. Any forward-looking information contained in these Presentation Materials has been prepared on the basis of a number of assumptions which may prove to be incorrect, and accordingly, actual results may vary.
Important Notice
2
AMARILLO GOLD 3
Amarillo Gold – Committed to Development
• Focused on the acquisition and development of gold resources in Brazil• Major Projects:
1. Mara Rosa – moving towards production – 2011 Pre-feasibility Study well underway completion Q3 – 1,174,900 gold ounces, Measured & Indicated categories (1.75 g/t)– 156,400 additional gold ounces, inferred category
2. Lavras do Sul – major gold prospect in southern Brazil– Continuously upgrading our resource estimate (I+I 520K Ounces)
every 6 months or so.– Numerous untested ‘garimpo’ gold targets– Drilling ongoing
• Seasoned management team with outstanding discovery & acquisition credentials.
AMARILLO GOLD 4
Proven Management Team
Buddy Doyle – President & CEO• 28 years experience; 23 years with Rio Tinto on numerous global assignments including 13 years as North American exploration
manager for diamonds. Exposure to numerous commodities with track record of economic discoveries including:
• +30M oz Lihir (Au) deposit discovery/definition team; project leader for the Diavik discovery/ pre-feasibility, >$14B in-situ diamonds
• Excellence in Diamond Exploration award in 2007
Rick Brown – Business Development, Director• Exploring South America since 1993; focused on management and property acquisitions
• Projects include: Peru- El Hilorico /El Galeno (Au-Cu), Argentina- Calcatreu (Au), Navidad (Ag), Brasil- Mara Rosa (Au)
Luis Carlos F. da Silva – General Manager Brazil• 20 years exploration experience in Brazil managing several exploration campaigns
• Responsible for drilling off several of Jaguar Mining’s Brazilian gold deposits
Frank Baker – Project Development Manager• Graduate of Sheffield University with Masters in Metallurgy, over thirty years experience, Brazil Citizen
• Taken three mines from Feasibility into production on three continents, South America, Australia and Africa
• Most recent job was commissioning a 2million tonne per year Gold mine in Western Australia
Waldemar Opalka- CFO Secretary • BA in Quantitative Economics, Tufts University and MBA, University of Massachusetts
• former Director of Strategy and Corporate Development at Netia S.A., founder and Managing Director of Polish Broadband LLC, a telecommunications company.
AMARILLO GOLD
Robert Landis, Chairman• Princeton University, Harvard Law School• Independent investor & member of Golden Sextant Advisor LLC• 10 years Merrill Lynch, 8 years corporate & securities attorney
Todd Bruce• Extensive international mining and mine development experience• Previously President and CEO of IAMGold (96-03) and Crystallex (03-07)
Mike Durose• Mineral Economist (P.Geo.), former mining analyst (BMO Nesbitt etc.)• Nearly 20 years capital market and mineral exploration experience
Patrick Power
• 20 years of Venture exchange experience, founder of numerous Venture Co. Companies. Practical regulatory experience.• Over $100m in money raised under his tutelage
5
Non-Executive Directors
Through this strong team and their contacts,AGC has been able to finance independently.
AMARILLO GOLD
• Politically mature• Economically stable (investment grade) • Mining friendly with a significant mining community• Foreign investment & personnel welcome• Excellent exploration potential (see table below)
6
Brazilian Opportunities Beckon
Canada Australia Brazil
Archean shield (km2) 2,200 1,200 2,600
Production through 1990 (tonnes) 7,600 6,800 2,400
Exploration investment (1970-1990) ($M) $4,968 $2,963 $685
Exploration investment per km ($/km2) $2.26 $2.47 $0.26
Production per $ invested in exploration $1.53 $2.29 $3.50Source: Mineral Economic Group 2005
AMARILLO GOLD 7
Project Locations - Brazil
Our projects are located in areas of excellent infrastructure.
MARA ROSA PROJECT• Federal highway, 320km from Brasilia• Hydroelectric grid power• 35km from 4M oz Chapada mine (Yamana)• 62km from the 1.5M oz Pilar Mine (Yamana)• 100km from 1M oz Serra Grande mine
(AngloGold / Kinross)
LAVRAS DO SUL PROJECT• Tarmac highway, 320km from Porto Alegre• Hydroelectric and thermal grid power• 70km from coal mining
AMARILLO GOLD 8
Mara Rosa Project - Moving Towards Production
Posse Gold Deposit
Au mineralization coloured, hotter colours higher grades. Looking NE
Source: Amarillo
Source: Google Earth
The Posse deposit is a Shear hosted gold deposit, with a gneiss hanging wall and greenstone foot wall dipping at 47 degrees to the NW.
AMARILLO GOLD
Exploration Potential
9
Posse
Chapada 5km
Geology of the Mara Rosa Area: Greens are the Mara Rosa Belt, volcanic and sediments, Neo-Proterozoic in age, pinksrepresent gneisses. Gold stars are gold occurrences and garimpos. Amarillo Land holdings shown.
K-Channel airborne gamma Soil Geochem, red coloursTop 5% of the data
Imbricate Thrust model
Posse
AMARILLO GOLD
Key Land Position in Competitive Belt
• 62,500 ha of exploration permits• 2,600 ha of mining permits• Encompasses the majority of the
main trend hosting the Posse • 12 km co-incident K-channel /Au soil
anomaly• 5 large mines within 100 km radius
• Yamana’s Chapada Cu-Au 35 km• AGC 100% title on all but 4 permits• 2% NSR on Posse trend• Local community supportive• Environmental certificate from govt.
10
Mara Rosa Project
Town of Mara Rosa
AMARILLO GOLD
History
1700’s - Portuguese mining gold
1982 - BHP discovers Posse deposit
1988 - heap leach operation commences
1989 - WMC acquires Mara Rosa project*
1992 - 600 tpd CIL plant commissioned
1995 - WMC ceased operations
1998 - WMC sells to Metallica for $1.5 M
2003 - AGC buys Metallica Brasil for $0.45 M
*1989-1995 WMC mined 86,000 oz Au oxide and sulphide.
11
Mara Rosa Project
Source: Amarillo
Source: Google Earth
AMARILLO GOLD 12
Sub-Station 4km from Posse Serra Mesa Hydro 450MW Entrance to Mara Rosa Village
Turn off to Posse Deposit Chapada mine 32km away BR-153 major N-S Highway
Mara Rosa ProjectOutstanding Infrastructure
Source: AmarilloSource: Yamana website
AMARILLO GOLD
Posse Deposit Resource Estimate
13
Mara Rosa Project
43-101 compliant based upon 283 drill holes (>33,000 metres)
Cut-off = 0.50 g/t AuTonnes (‘000)
Average Grade Ounces Au
Measured 5,463 2.04 g/t 358,300
Indicated 15,393 1.65 g/t 816,600
Total (M + I) 20,856 1.75 g/t 1,174,900
Inferred 3,630 1.34 g/t 156,400Indicated & Inferred Mineral Resource at Posse Deposit Source: AEFS Sept 2011 – 43-101 accredited, Keith Whitehouse Qualified person.
AMARILLO GOLD
Posse Deposit Reserves
14
Mara Rosa Project
Cut-off = 0.50 g/t Au Tonnes (‘000) Average Grade Ounces Au
Proven 5,361 1.87 g/t 339,600
Probable 11,739 1.60 g/t 606,600
Total (P + P)* 17,117 1.72 g/t 945,200
Inferred 3,630 1.34 g/t 156,400I Source: Coffey Mining International Nov 2011– 43-101 accredited, Norman Lock supervising Qualified person
* Run of Mine
AMARILLO GOLD
PFS: Nov 2011
Pit shell $1100 / oz Au
(post-tax) NPV 5 $178 M (post-tax) IRR 26.6% ROI 3 years Cost/oz $524 ($464) Av annual Production 124,000 oz Mine life 7 years
15
Mara Rosa Project
• CAPEX (2.5 mtpa plant) $184 M• Overall costs
$24.63/tonne• CIL recovery 92%• Selling costs 4%• Approx. US/Real 1.8 Nominal Tax Rate 34% DCF $1200/ oz
Au
Pit Dimensions1.4 km long0.6 km wide260m deep67 hectaresHW 55 degFW 40 deg
AMARILLO GOLD
Posse PFS DCF Gold Price and Discount Rate
16
Mara Rosa Project
Base Case
Gold Price $1000/oz $1100/oz $1200/oz $1300/oz $1400/oz $1500/oz
IRR (internal rate of return) 16.8% 21.8% 26.6% 31.3% 35.9% 40.3%
NPV0 $M165 219 274 328 383 437
NPV5 $M (Base Case) 93 136 178 221 264 307
NPV7 $M71 110 149 188 227 266
NPV10 $M44 78 112 146 181 215
Pay Back period 5.1 4.1 3.5 3.0 2.7 2.5
AMARILLO GOLD
Mara Rosa Project Production Circuit Primary Crusher
Secondary and Tertiary CrushersPrimary Ball Mill Secondary Ball Mill
Lime addition 2kg/tgtt
CRUSHING CIRCUIT GRINDING AND SIZING CIRCUIT
Cyclone Sizing45um P80 to Pre-OX
Knelson
PRE-OX STAGEPSA Oxygen unit
Pre-OX TanksNumber:-3
RESIDENCE:-12hr
O2 in
CIL STAGE
RESIDENCE:-24hr
CILTanksNumber:-6
GRAVITY CIRCUIT
Cyanide reactor
GOLD RECOVERYCARBON RECOVERYFINES HANDLING, DISPOSAL, DE-WATER
Thickener
Cyanide in 0.2kg/tCarbon in
LoadedCarbon
Cyanide Detox
POSSE ORE
TAILINGS
Carbon reactivation Unit Carbon recovery electro-win
Power in138KVa12.5MW
7000 t/day
290 troy ounces/day
AMARILLO GOLD
Mine Plan
18
Mara Rosa Project
AMARILLO GOLD
Time Line to Production
19
Mara Rosa ProjectSCHEDULE - Posse Mine
ITEMS DESCRIPTION2011
2012 2013=Pre Stripping (Year 0) 2014 = Year 1 (Production)
4º T1º T. 2º T. 3º T. 4º T. 1º T. 2º T. 3º T. 4º T. 1º T. 2º T. 3º T. 4º T.
1 ENVIRONMENTAL LICENSES
1.1 Preliminary License (LP)
1.2 Installation License (LI)
1.3 Operational License (LO)
1.4 Feasibility Studies, PFS and DFS
2 ENGINEERING
2.1 Basic Engineering
2.2 Detailed Engineering
3 PURCHASES
3.1 Mills
3.2 Other Equpments/Services
3.3 Construction of 138kv Power Line
4 Pre-Operation
4.1 Pre-Stripping
4.2 Mine Operations
5 CIVIL CONSTRUCTION
5.1 Earth Moving
5.2 Concrete
6 INSTALLATION/TESTS
6.1 Electromechanical Installation
6.2 Testing
7 START UP
AMARILLO GOLD
Moving Mara Rosa Forward In 2011-2012
• Final PFS report Q4 11, being led by Coffey Mining Pty.
• PFS moves to Feasibility and then Decision to Mine 2012
• Estimated Mine build will be 18 months, mining 2014.
• Complete Geotech and “shoulder” drilling
• Exploration drilling there after, 2 rigs on site.
Mara Rosa Project
20
Source: AmarilloOne of the three rigs currently working at the Posse deposit Mara Rosa Project
AMARILLO GOLD
Lavras Do Sul Project
21Source: Amarillo
Left: Cerro Rico gold processing plant, Centre: Drill rig Butia prospect Bottom: main entrance to village
AMARILLO GOLD
• Several periods of mining from 1700’s through to 1950’s
• 1st wave 1780's 2nd wave 1880's alluvials and soils
• 2nd wave 1900's hard rock 3 central stamp mills
• 3rd wave 1930 Hydraulics
• 1980’s – First exploration drilling campaign (CBC & CRM)
• 2005 – Rio Tinto drilled ~3,000 m
• 2006 – Amarillo acquires initial interest
• 2007 – Completes airborne magnetics over Lavras intrusion
• 2008 – Drills 232 m @ 1.95 g/t Au at Butiá target
22
300 Years of Mining HistoryLavras do Sul
19 garimpos throughout the mining district Source: Diary of a German mercenary in Brazil, painting from gold rush days 1880’s
AMARILLO GOLD
LAND DISPOSITION
23
Lavras do Sul
Yellow is CBC ground part of Rio Tinto deal.Magenta is Lucia ground part of the Rio Tinto deal.Grey is the IAMGOLD deal.
AMARILLO GOLD
Numerous Targets – 19 Garimpos
24
Lavras do Sul
BUTIA120 m @ 3.23 g/t
PARADAO12m @ 4.54 g/t
CANELEIRA37m @ 1.17 g/t
CERRITO135.5m @ 0.85 g/t
ADVANCED TARGETS (with highlighted Au drill results)
Old Gold Workings
Digital Elevation in grey, roads in black. Colour image: airborne magnetics showing geology and structure.
AMARILLO GOLD
Butiá prospect initial resource estimate
43-101 compliant interim resource estimate for the Butia prospect 0.3g/t cut-off
0.3g/t cut Tonnes (mt)
Grade (g/t) Ounces
Indicated 6.4 1.05 215,000
Inferred 12.9 0.74 308,000
Total 22.1 0.88 523,000
3D Model ofButia Zone
• This is the first Resource Estimate from one of the Prospects at Lavras Do Sul, the Butia Prospect, 1 of 19.
• Bulk tonnage near surface. • High grade zones cut to 10g/t need to go back and drill to determine continuity, statically expected to increase grade and ounces, but not change the tonnes.
• Drill now at Cerrito Prospect, 4 more holes.
• The plan is to put an updated resource estimate with Butia and Cerrito.
• Next drill target is on IAMgold ground.
A 50% increase in our resource base
Source: Amarillo
25
Lavras do Sul0.3g/t cut Tonnes
(mt)Grade (g/t) Ounces
Indicated 6.4 1.05 215,000
Inferred 12.9 0.74 308,000
Total 22.1 0.88 523,000
AMARILLO GOLD
Cerrito Prospect: Current Drill Project.
26
Lavras do Sul
• Bulk tonnage, low grade, near surface gold deposit • Drilling underway with over 15 holes completed; approx. 5,000 m of drilling
completed to date• Gold results incl. 71m @ 1.08 g/t, 143.4m @ 0.75 g/t, 56m @ 1.42 g/t
• + 300m strike• up to 80m wide• + 120m depth
Source: Amarillo
AMARILLO GOLD
Matilde Prospect: Current Drill Project.
27
Lavras do Sul
• Image shows new soil anomaly developed 2.5 km south of Lavras do Sul, 0.3ppm contours.
• Named the MatildeProspect.
• It is partially on the IAMgold ground and the CBC ground.
1km
AMARILLO GOLD
Why Invest in Amarillo
Key project milestones in 2011• Pre-Feasibility Study at Mara Rosa• Continuing 43-101 resource estimates at Lavras do Sul
• Vectoring towards a >2 million oz resource base• Generating new exploration 100%-owned projects• Extensive infrastructure in place• Results driven and proven management• Exemplary capital management record• Low market cap compared to Peers, which should change
once recognition occurs.
28
AMARILLO GOLD
Amarillo Gold Timeline
•MR* - Mara Rosa•LDS** - Lavras do Sul •Metallurgical work on each Lavras prospect after resource definition.•PEA to commence (Lavras) when resource stops growing or @ 2million ounces, whichever comes first.
29
Amarillo Gold Timeline
MR* Posse Infill Drilling
MR Exploration Drilling
MR Pre Feasibility Study
MR Feasibility Study
MR Decision to Mine
MR Mine Construction
MR Mine Production
LDS** Exploration Drilling
LDS Resource Drilling
Q4 Q2 Q4 Q2 Q4 Q1 Q1 Q3 Q1 Q32010 2011 2011 2012 2012 2013 2014 2014 2015 2015
AMARILLO GOLD
Corporate Information
View from the Butia prospect
Source: Amarillo
Capital StructureShares outstanding 64 million
Options ($1.35 average) 3.2 million
Warrants @$2 3.6 million
Market cap. @ $1.45 $92.8 million
Major shareholdersBoard & Management 15%
Institutions 45%
Mid-tier Producers 5%Recent Financings
Closing No. Shares Issue Price Warrants Amount
May-11 6.7M $1.50 3.35 @ $2 $10.05M
Jul-10 8.0M $0.75 None $6M
Jul-09 3.0 M $0.70 None $2.1M
Oct-08 2.1M $0.80 None $1.68M
May-07 6.0 M $1.25 None $7.5M
TOTAL $27.32M
30
AMARILLO GOLD
Canada:Buddy DoylePresident and CEOSuite 1818 701 W. Georgia St.PO BOX 10144Vancouver BC Canada V7Y 1C6Tel: 1-604-689-1799Fax: 1-604-689-8199
Further Information
31
Brazil:Rick BrownBusiness DevelopmentPraca Carlos Chagas 49 – Salas 504 a 506Bairro Santo Agostinho – Belo Horizonte - MGBrasil CEP 30170-913Tel: +55 31 3261 5974
Source: Amarillo
Lawyers:Clark Wilson LLP800 – 885 West Georgia StreetVancouver, BC V6C 3H1 Canada
Auditors:MSCM LLP (Moore Stephens)8th Floor, 701 Evans AvenueToronto, OntarioM9C 1A3 Canada
AMARILLO GOLD
Rio Tinto Agreement Lavras do Sul
32
Summary of Acquisition terms:- Amarillo must make total payments of US$ 2.07 million through various installments up to April 1(st) 2008 in order to acquire an initial 60% interest in the Property. Completed- Amarillo is required to spend US$ 750,000 on exploration prior to Feb. 1st, 2008. Completed - Upon completing the above payments Amarillo will form a Joint Venture with the underlying owners. If the other parties elect not to contribute then Amarillo will earn a 100% interest in the Property and be required to pay a 1.5% Net Smelter Royalty on production. Letter of intent signed, full formal document in progress.- Amarillo will make a US$ 1,000,000 payment to Rio Tinto within 90 days of a bankable feasibility study being delivered and,- Amarillo will make a US$ 6,500,000 payment for every one million ounces of recoverable gold reserves that is covered by the 60% equity in the Property over which Rio Tinto have an option.- Rio Tinto will have a back-in-right to acquire 70% of Amarillo interest in the project by paying Amarillo three times (3 x) their exploration expenditure in the event that Amarillo's equity interest in the Property contains in excess of 7 million ounces of recoverable gold.- Amarillo will issue 2,000,000 warrants - exercisable at 50c - to Rio Tinto within 60 days of signing the final agreement. Expired without exercise
AMARILLO GOLD
IAMGOLD Agreement Lavras do Sul
33
Amarillo can earn a 51-per-cent interest by expending $800,000 (U.S.) on exploration over 3 years which will include a minimum of 2,000 metres drilling and of which $200,000 (U.S.) must be spent within the first 12 month period. Amarillo has made the $200K milestone and is currently drilling on the IAMGOLD ground.
In the event that IAMGOLD elects not to contribute pro-rata funding after the first earn-in period then Amarillo may earn a further 29% interest (for a total of 80%) by funding any mineral resource discovered on the Property through to feasibility study.
At the completion of a feasibility study on the Property, and up to a period of 60 days from this date, IAMGOLD may either• elect to contribute its pro-rata share to future funding OR• dilute its interest to a 2.0% Net Smelter Royalty (NSR), of which 1.0% may be bought back by Amarillo for US$1,000,000 at any time up to the commencement of production OR• exercise a one-time back-in right to increase its participating interest to 60% - if Amarillo has established a total mineral reserve in excess of 2.5 million ounces of gold on the Property – and become operator by paying three times Amarillo’s exploration costs up to the date of IAMGOLD exercising its back-in right.
Border Zone: Brazil has a border defense zone (like most South Am, countries), that extends 150km from the border where more than 50% foreign ownership in any property or business is not permitted. Many foreign companies operate in this zone, including Aura (former Yamana assests) and in the recent past Rio Tinto's Iron mines as well as many Foreign owned factories, forestry and agricultural interests. Lavras lies approx. 120km from the border.There is a push to change this law, from 150k to 50km, (it has been altered in the past from 300km to 150km), and this proposal has already past the senate, and awaits hearing in the lower house. In the meantime Amarillo will pursue the same solutions that other companies have used, which include a combination loans to a Brazilian partner and contract mining.