28
Project Time Management

Session 5 4th edition PMP

  • Upload
    -

  • View
    176

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Session 5 4th edition PMP

Project Time Management

Page 2: Session 5 4th edition PMP

Knowledge Area

Process

Initiating Planning Executing Monitoring & Control Closing

Time  

Activity DefinitionActivity SequencingActivity Resource EstimatingActivity Duration EstimatingSchedule Development

  Schedule Control  

Enter phase/Start project

Exit phase/End project

InitiatingProcesses

ClosingProcesses

PlanningProcesses

ExecutingProcesses

Monitoring &Controlling Processes

Project Time Management

Page 3: Session 5 4th edition PMP

Schedule management plan

• - How will I develop schedule? And control it?

• - Create this Document is not identified as

Separate Process.

• - It is part of Project management plan

Page 4: Session 5 4th edition PMP

Work package

decompose

activities

Page 5: Session 5 4th edition PMP

Rolling wave planning• form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS

Page 6: Session 5 4th edition PMP

Define Activities• The process of identifying the specific actions to be performed

produce the project deliverables.• Work package decomposed into activities (schedule activities)

Inputs

1. Scope baseline2. Enterprise environmental factors

3. Organizational process assets

Tools & Techniques

1. Decompositions2. Rolling wave planning3. Templates4. Expert judgment

Outputs

1. Activity list2. Activity attributes3. Milestone list

Page 7: Session 5 4th edition PMP

Activity List• The activity list is a comprehensive list including all

schedule activities required on the project.

• The activity list includes the activity identifier and a

scope of work description for each activity in

sufficient detail to ensure that project team members

understand what work is required to be completed

Page 8: Session 5 4th edition PMP

ACTIVITY LISTProject Title: Date Prepared:

ID Activity Description of WorkFollow WBS or schedule

Activity name. Description of activity in enough detail so that the person(s) performing the work understands what is required to complete it.

Page 9: Session 5 4th edition PMP

العمل وصف الرق النشاطم

الـتأريض موصالت تمديد يتمالمعدنية باالجزاء وربطها

للمبنى

شبكة عمل المبنى تأريض

1001

والتفتيح التكسير يتماالسالك لمقاطع

مجاري تفتيح

المواسير

1002

العلب اماكن تحديد يتممبين هو كما وتركيبها

باللوحات

علب تركيباالنارة

1003

= جيدا بالعلب المواسير اتصال

المواسير و مقاطع مطابقة

وعدد للمخططات طبقا=

التسليك وجداول األسالك

تمديد

المواسير

1004

2012/10/15 خاص : التاريخ مستشفى بناء المشروع

Page 10: Session 5 4th edition PMP

Activity attributes

• Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.

• The components for each activity evolve over time. During the initial stages of the project they include the Activity ID, WBS ID, and Activity Name, and when completed may include activity codes, activity description

Page 11: Session 5 4th edition PMP

ACTIVITY ATTRIBUTESProject Title: Date Prepared:

ID:

From activity list

Activity:

From activity list

Description of Work:

A description of the activity in enough detail so that the person(s) performing the work understands what is required to complete it.

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

Any activities that must occur before the activity.

The nature of the relationship, such as start-to-start, finish-to-start, or finish-to-finish.

Any required delays between activities (lag) or accelerations (lead).

Any activities that must occur after the activity.

The nature of the relationship, such as start- to-start, finish-t-start, or finish-to-finish.

Any required delays between activities (lag) or accelerations (lead).

Number and Type of Resources Required:

The number and roles of people needed to complete the work.

Skill Requirements:The level of skill necessary to complete the work (expert, average, novice or applicable job level).

Other Required Resources:Any equipment, supplies, or other types of resources needed to complete the work.

Type of Effort:

Indicate if the work is a fixed duration, fixed amount of effort, level of effort, apportioned effort or other type of work.Location of Performance:

If the work is to be completed somewhere other than at the performing organizations site, indicate the location.Imposed Dates or Other Constraints:

Indicate any fixed delivery dates, milestones or other constraints.Assumptions:

List any assumptions about resource availability, skill sets, or other assumptions that impact the activity.

Page 12: Session 5 4th edition PMP

ACTIVITY ATTRIBUTESProject Title: Date Prepared:

ID:

1004Activity: المواسير تمديد

Description of Work:

= جيدا بالعلب المواسير اتصال

التسليك و وجداول األسالك وعدد للمخططات طبقا= المواسير مقاطع مطابقة

Predecessors Relationship Lead or Lag Successor Relationship Lead or Lag

مجاري تفتيح

المواسير

تتوقف بداية النشاط الحالي على بداية النشاط السابق

يوم واحد يسبق في البدء

تركيب لوحات التوزيع الفرعي.ة

اماكن تحديدوتركيبها العلب

.

اليوجد

Number and Type of Resources Required:

عدد ( لكل) 3مطلوب كهربائيالكلي العدد يكون 12دور

كهربائي

Skill Requirements:

خبرة سابق له يكونبكهرباء العمل فيوله المستشفياتبالكود بالعمل خبرة

القياسي المصري

Other Required Resources:

اتركيب على مشرف مهندس وجود

Type of Effort:

لمدة العمل العاملين 8يكون وعدد يوميا المشرف 12ساعات والمهندس Location of Performance:

المستشفى مبنى وهو المشروع مكان فيImposed Dates or Other Constraints:

I عن اليزيد فيما النشاط من االنتهاء يوم 15مطلوبAssumptions:

الموجودة العمالة في المهارة ووجود العمل النجاز المطلوبة العمالة توفير يفترض

Page 13: Session 5 4th edition PMP

• A milestone is a significant point or event in the project. A milestone list identifies all milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.

Milestone List

Page 14: Session 5 4th edition PMP

MILESTONE LISTProject Title: Date Prepared:

Milestone Milestone Description TypeMilestone name. Description of milestone in

enough detail to understand what is needed to meet the milestone.

Internal or external. Interim of final. Mandatory or optional.

Page 15: Session 5 4th edition PMP

المشروع مراحل قائمة2012/10/15لتاريخ ا

بناء : المشروع اسمخاص مستشفى

المرحلة نوع المرحلة وصف المرحلة

جزء بها ضرورية مرحلة

االعمال وهو داخلي

خارجي وجزء المساحية

البنكية الضمانات وهو

مكاتب االشرافتجهيزالتأمينات تجهيز

البنكية والضماناتوتنفيذ األرض تسوية

المساحية األعمال

التحضير

داخليا وتتم ضرورية هي الحفر آليات بإستخدام تتم ” أعمال وتشمل الكباش"

الحفرالدمك أعمال

الدمك أعمال فحص

الحفر

داخليا وتتم ضرورية هي محاور ) تثبيتالشبمونة( األعمدة

القواعد طوبارتسميح حديد وتثبيت تنفيذ

القواعدالقواعد صب

ز القواع اا طوبار دلة

القواعد

Page 16: Session 5 4th edition PMP

• Sequence Activities• Process of identifying and documenting relationship among the project activities

Inputs

1. Activity list2. Activity attributes3. Milestone list4. Project scope statement5. Organizational process assets

Tools & Techniques

1. Precedence diagramming method (PDM)

2. Dependency determination

3. Applying leads and lags4. Schedule network templates

Outputs

1. Project schedule network diagram

2. Project document updates

Page 17: Session 5 4th edition PMP

Precedence Diagramming Method (PDM)

•  Finish-to-Start (FS)

•  Finish-to-Finish (FF)

•  Start-to-Start (SS)

•  Start-to-Finish (SF)

logical relationships:

Page 18: Session 5 4th edition PMP

• Applying Leads & Lags• Use leads and lags to support realistic and achievable project schedule.

• Each activity is connected at least to one predecessor and one successor except the start and the end.

• Leads.– May be added to start an activity before the predecessor activity is complete.

• Lags– Inserted waiting time between activities

A B C

predecessor Successor

B

A

B

A

Page 19: Session 5 4th edition PMP

Dependency DeterminationTo define sequence among activity, these type of dependency are used:

1. Mandatory (hard logic)– Inherent in the nature of work being done or required by the contract– E.g. You must design before you can develop

2. Discretionary (preferred, preferential, or soft logic)– Define base on knowledge– Can be changed if needed– Important when how to shorten or re-sequence the project

3. External– Based on the need t of the party outside the project

Page 20: Session 5 4th edition PMP

.1 Project Schedule Network Diagrams

- Project schedule network diagrams are schematic

displays of the project’s schedule activities and the

logical relationships among them, also referred to as

dependencies..

- A project schedule network diagram can be

produced manually or by using project management

Page 21: Session 5 4th edition PMP

Activity-On-Node (AON)

Precedence Diagramming Method (PDM)

Page 22: Session 5 4th edition PMP
Page 23: Session 5 4th edition PMP

•1- you are a project manager on a us $5.000.000 software development Project . While Working with your project team to develop a network diagram ,your data architects suggest that quality could be improver if the data model is approved by senior management before moving on the other design elements. They support this suggestion with an article from a leading software development journal. Which of the following best describes what this type of inputs is called?

•A- mandatory dependency

•B- discretionary dependency

•C- external dependency

•D- heuristic

Page 24: Session 5 4th edition PMP

2- Which of the following is not an activity attribute:

1-Person responsible for the activity

2-Location where to perform the activity

3-Time when to perform the activity

4-Leads and Lags

Page 25: Session 5 4th edition PMP

3-Lag means:

A-the amount of time an activity can be delaying the project

finish date.

B- the amount of time an activity can be delayed without

delaying the early start date of its successor

C- waiting time

D-the product of a forward and backward Pass

Page 26: Session 5 4th edition PMP

•4-Activity Definition is typically performed by which of the following

A-Project Manager who created the WBS

B.Project Team Members responsible for the work package

C.Project Officer

D.Project Stakeholder

Page 27: Session 5 4th edition PMP

5- A schedule activity may begin 10

days before the predecessor activity

finishes This is an example of

A-ADM2-PDMC- A dependency with lag

D- A dependency with lead

Page 28: Session 5 4th edition PMP

Thank you