Installation Instruction EPP-0317-4/08 Raychem Solderless Earth Connection for Metal Tape Shielded Plastic and Rubber Insulated Cable Terminations 7.2 kV to 36 kV Tyco Electronics Raychem GmbH Energy Division Finsinger Feld 1 85521 Ottobrunn/Germany 0049-89-6089-0 tel 0049-89-6089-345 fax http://energy.tycoelectronics.com MOHD. BIN AHMED AKBAR TRADING EST. (Electrical, Automation & Instrumentation) Al Sahaba Street | P.O Box 30073 | Jubail 31951 | Kingdom of Saudi Arabia Tel: 00966 (0) 13 3635225, 13 3618081 | Fax: 00966 (0) 13 363 3883 | [email protected] | www.akbartrading.com MOHD. BIN AHMED AKBAR TRADING EST. (Electrical, Automation & Instrumentation) Al Sahaba Street | P.O Box 30073 | Jubail 31951 | Kingdom of Saudi Arabia Tel: 00966 (0) 13 3635225, 13 3618081 | Fax: 00966 (0) 13 363 3883 | [email protected] | www.akbartrading.com

|AKBAR TRADING EST. SAUDI ARABIA|TE TYCO ELECTRONICS Epp 0317-4 08 solderless earth connection installation instruction(1) 케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易

Embed Size (px)

Citation preview

Page 1: |AKBAR TRADING EST. SAUDI ARABIA|TE TYCO ELECTRONICS Epp 0317-4 08 solderless earth connection installation instruction(1) 케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易

Installation Instruction EPP-0317-4/08

Raychem Solderless Earth Connection for Metal Tape Shielded Plastic and Rubber Insulated Cable Terminations 7.2 kV to 36 kV

Tyco Electronics Raychem GmbH Energy Division Finsinger Feld 1 85521 Ottobrunn/Germany 0049-89-6089-0 tel 0049-89-6089-345 fax http://energy.tycoelectronics.com

MOHD. BIN AHMED AKBAR TRADING EST.

(Electrical, Automation & Instrumentation)

Al Sahaba Street | P.O Box 30073 | Jubail 31951 | Kingdom of Saudi Arabia

Tel: 00966 (0) 13 3635225, 13 3618081 | Fax: 00966 (0) 13 363 3883 |

[email protected] | www.akbartrading.com

MOHD. BIN AHMED AKBAR TRADING EST.

(Electrical, Automation & Instrumentation)

Al Sahaba Street | P.O Box 30073 | Jubail 31951 | Kingdom of Saudi Arabia

Tel: 00966 (0) 13 3635225, 13 3618081 | Fax: 00966 (0) 13 363 3883 |

[email protected] | www.akbartrading.com

Page 2: |AKBAR TRADING EST. SAUDI ARABIA|TE TYCO ELECTRONICS Epp 0317-4 08 solderless earth connection installation instruction(1) 케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易

EPP-0317-4/08 page 2/3

Before Starting Check to ensure that the kit you are going to use fits the cable. Refer to the kit label and the title of the installation instruction. Components or working steps may have been improved since you last installed this product. Carefully read and follow the steps in the installation instruction. General Instructions Use a propane (preferred) or butane gas torch. Ensure the torch is always used in a well-ventilated environment. Adjust the torch to obtain a soft blue flame with a yellow tip. Pencil-like blue flames should be avoided. Keep the torch aimed in the shrink direction to preheat the material. Keep the flame moving continuously to avoid scorching the material. Clean and degrease all parts that will come into contact with adhesive. If a solvent is used follow the manufacturer's handling instructions. Tubing should be cut smoothly with a sharp knife leaving no jagged edges. Start shrinking the tubing at the position recommended in the instruction. Ensure that the tubing is shrunk smoothly all around before continuing along the cable. Tubing should be smooth and wrinkle free with inner components clearly defined.

The Information contained in these installation instructions is for use only by installers trained to make electrical power installations and is intended to describe the correct method of installation for this product. However, Tyco Electronics has no control over the field conditions which influence product installation. It is the user's responsibility to determine the suitability of the installation method in the user's field conditions. Tyco Electronics' only obligations are those in Tyco Electronics' standard Conditions of Sale for this product and in no case will Tyco Electronics be liable for any other incidental, indirect or consequential damages arising from the use or misuse of the products. Raychem, TE Logo and Tyco Electronics are trademarks.

Page 3: |AKBAR TRADING EST. SAUDI ARABIA|TE TYCO ELECTRONICS Epp 0317-4 08 solderless earth connection installation instruction(1) 케이블 종단-거-瑞侃工具包电缆终端-阿克巴交易

EPP-0317-4/08 page 3/3

Installation of Solderless Earth Connection on 3-Core Cables

Remove the oversheath of the cable according to the dimensions given in the appropriate Raychem Terminations Installation Instruction. Position the end of the earth lead on the metal tape shield of one core about 100 mm from the end of the oversheath. Starting at the opposite side of the core, wrap the roll spring twice over the earth lead, in the direction of the metal tape shield wrap. Fold the earth lead back over the roll spring. Wrap the rest of the roll spring around the earth lead. Carefully slide the roll spring and earth lead down into the crutch until it is about 10 mm from the end of the oversheath. Tighten the roll spring with a twisting action and fix it into place with two layers of adhesive tape. Install the remaining springs and earth leads on the other two cores in the same way. Continue installation in accordance with the appropriate Raychem Terminations Installation Instruction.

Remove the oversheath and metal tape shield of the cable according to the dimensions given in the appropriate Raychem Terminations Installation Instruction. Position the end of the earth lead on the metal tape shield. Starting at the opposite side of the cable, wrap the roll spring twice over the earth lead about 5 mm from the end of the oversheath. Apply the roll spring in the direction of the metal tape shield wrap. Fold the end of the earth lead back over the roll spring. Wrap the rest of the roll spring over the earth lead. Tighten the roll spring with a twisting action and fix it into place with two layers of adhesive tape. Continue installation in accordance with the appropriate Raychem Terminations Installation Instruction.

Installation of Solderless Earth Connection on Single Core Cables

metal tape shield

roll spring

earth lead

oversheath 2425/1

2424/1

earth lead

metal tape shield

insulation

roll spring

oversheath 2426/1

2427/1 Please dispose of all waste according to environmental regulations.

MOHD. BIN AHMED AKBAR TRADING EST.

(Electrical, Automation & Instrumentation)

Al Sahaba Street | P.O Box 30073 | Jubail 31951 | Kingdom of Saudi Arabia

Tel: 00966 (0) 13 3635225, 13 3618081 | Fax: 00966 (0) 13 363 3883 |

[email protected] | www.akbartrading.com