2007 Fall Simulation Interoperability Workshop
VV&A ForumGMV&V PDG Status Overview
Ad van Lier / Manfred Roza
1
2007 Fall Simulation Interoperability Workshop
Outline
1. A brief peek on SISO BPDSP and GMV&V
2. GMV&V current status
3. PDG organisation
4. Product development schedule and status
5. Product scope
2007 Fall Simulation Interoperability Workshop
SISO Product Types
• Balloted Products
• Standards
• Guidance
• Non-balloted Products
• Reference
• Administrative
What we want to produce
3
2007 Fall Simulation Interoperability Workshop
ProductNomination
ActivityApproved
ProductDevelopment
ProductBalloting
ProductApproval
Interpretation ,Distribution &ConfigurationManagement
PeriodicReview
Input Process Output
Sponsor
Approved Product Nomination
1. PDG Infrastructure2. Draft Product
1. Balloting Group2. Balloting Results3. Balloted Product
1. EXCOM Approval2. SISO Product3. PSG TOR
1. Interpretations2. Problem /Change DB3. Product Support
1. Product Nomination2. Product Reaffirmed3. Product Withdrawn
Product Development Group Product Support Group
BPDSP Six Step Process
Step 2:
We Are Here!
4
2007 Fall Simulation Interoperability Workshop
BPDSP Step 2: Product Development
• Launch development activity
• PDG elects Chair, Vice Chair, Secretary
• Establish Drafting Group
• Establish and maintain development schedule
• Produce the product or product component• Reference Manual (1st draft available for comment)
• Users Manual (1st draft available for comment)
• Technical Notes (DG in concept)
• Recommended Practice Guides (DG in concept)
• Monitor & control PDG activities
• Submit draft product to SAC and EXCOM for 'Approval to Ballot’
Spring 07meeting
5
Fall 07Fall 07meetingmeeting
2007 Fall Simulation Interoperability Workshop
SG - PDG present state
• SG PN submitted Fall 06
• EXCOM / SAC approved PDG status March 07
• Spring 07 SIW kick-off meeting
• Kick-off used to assign roles and responsibilities for PDG officers and DG
• Elected officers/assigned roles:
• Chair : Ad VAN LIER
• Vice Chair : Simone YOUNGBLOOD
• Secretary : Tony MASYS
• Chair DG (E) : Rene JACQUART
• SAC TAD : Bob ELLIOTT
6
2007 Fall Simulation Interoperability Workshop
Present Drafting Group member
• Newly volunteered Spring 07:
• Scott HARMON
• Mike METZ
• Marcy STUTZMAN
• Simone YOUNGBLOOD
• Previously submitted names:
• Pierre BOUC
• Colin BRAIN
• Stephane CHAIGNEAU
• Lars HORN
• Rene JACQUART
• Tony MASYS
• Jorgen MOTH
• Sten-Ake NILSSON
• Manfred ROZA
• Pernilla SVAN
• Martijn VAN EMMERIK
• Edwin VAN VELDHOVEN
• Jeroen VOOGD
7
2007 Fall Simulation Interoperability Workshop
Drafting Group Organisation
ODD
WP 1
WP 2
WP 3
WP 4
WP 5
WE 2.1
WE 2.2
GMV&V Draft Evaluation
2006 2008/9
REVVA
DG’s
Draft submitted
SISO Community
8
2007 Fall Simulation Interoperability Workshop
PDG Organization
• Complies to the SISO Operating Principles, documented in the Policies & Procedures document, section 5
• Dedicated DG’s delegated to the DGE for each baseline document (who does what?)
• Follows a staged process where:
• DG drafts will be evaluated internally before being submitted to the SISO community
• A File library will be maintained, storing progress & and products
• SISO evaluation and feedback sessions will be documented using the reflector and
• face to face meetings during PDG sessions are held at SIW’s using mechanisms like Robert’s Rules of Order and SISO regulations such as voting rules conforming to the BSDP
• After draft completion: Start of Balloting within SISO
9
2007 Fall Simulation Interoperability Workshop
Drafting group core (to be completed)
• Rene JACQUART (DG Chair/DGE)
• Manfred ROZA Pierre BOUC
• Constantinos GIANNOULIS Stephane CHAIGNEAU
• Constantinos GIANNOULIS (DGE)
• Manfred ROZA
• Rene JACQUART
• Manfred ROZA (DGE)
• Edwin VAN VELDHOVEN Constantinos GIANNOULIS
• Jeroen VOOGD Tony MASYS
• Manfred ROZA (DGE)
• Edwin VAN VELDHOVEN Constantinos GIANNOULIS
• Colin BRAIN Tony MASYS
• Jeroen VOOGD
10
2007 Fall Simulation Interoperability Workshop
Supporting activities
• Tony MASYS (MALO case study Leader)
• Martijn VAN EMMERIK
• Colin BRAIN
• AEGIS company
• Stephane CHAIGNEAU (NBC case study leader)
• Jeroen VOOGD
• Rene JACQUART
• Sten-Ake NILSSON
• Martijn VAN EMMERIK (DGE Training Kit)
• Colin BRAIN
• Tony MASYS
• Jorgen MOTH (REVVA web master)
11
2007 Fall Simulation Interoperability Workshop
Planned product development schedule
SISO
Drafting group
SIWEuroSIW
SIW SIWEuroSIW
SIW SIWEuroSIW
SIW
RefMan
C
UserMan
C
RPGC
Scope,
Timeframe,
expected Outcomes
04 07
RefMan
CUserMan
C
01
Ballotingphase
Feedbackto SISOReport
RefManD2
UserManD2
TN
07
RPGD1 C
C
Report
C
RefManD2
UserMan
F
RefMan
F
UserMan
F
RPGF
RefMan
F
RPGFC
RPGD2
RefManD3
RefManDraftD3
RPGD2
03
UserManD2
C
C
UserManD3
UserManD3
C
RefManD1
UserManD1
RPGC
RefManD1
RPGD1
09 11
2007
2007 Fall Simulation Interoperability Workshop
Current development status
• RefMan:
• 1st draft delivered prior EURO SIW 07 (on schedule)
• UserMan:
• In concept, 1st draft delivered prior Fall SIW 07
• RPG’s:
• Identified, concept versions available
• TN’s:
• Identified, concept versions available
• Case studies:
• MALO: steady progress, expected results end of year
• NBC: specification of the ToA for one application context
• Dissemination:
• Web-site up & running
• Draft training available (presented at ITEC May 07)
2007 Fall Simulation Interoperability Workshop
GMV&V Product Structure & Scope
RefMan
Why? What? For whom?
RationaleDefinitionsConceptsComponents
How? When? Who?
RolesResponsibilitiesProcessActivities
Method Basics& Architecture
Method Utilisation & Deployment
Specific Task oriented
Specific Product oriented
Method Implementation& Execution
Detailed DescriptionParticular ActivitiesParts of ProcessSpecific Roles
Product SpecificationTechniques Tools
UserMan
RPG
TN
2007 Fall Simulation Interoperability Workshop
Introduction
Overview
Methodology Rationale
Conceptual Tools
Methodology Components
Requirements for Compliance
Glossary
GMV&V Reference Manual Scope
Reference ManualPresentation
Reference Manual
2007 Fall Simulation Interoperability Workshop
Introduction
Overview
VV&A Project Issues
Organization
Activities
Tailoring
Project assessment & return on experience
GMV&V User Manual Scope
User ManualPresentation
User Manual
2007 Fall Simulation Interoperability Workshop
GMV&V Technical Notes Scope
TN’s
Introduction
Product Overview
Product Specification
DIF – Template
Report Structure
2007 Fall Simulation Interoperability Workshop
GMV&V RPG’s Scope
RPG’s
Introduction
High-Level Activity Overview
Sub-Task Specification
Transversal Sub-Tasks
Tailoring & Tools Guidance
2007 Fall Simulation Interoperability Workshop
MALO Case study interim results
• Check here on MALO presentations
2007 Fall Simulation Interoperability Workshop
Results of PDG Fall 07
• 1st Draft Refman
• Comments statistics
• Etc.
• 1st draft Usersman
• Comments statistics
• Etc.
• Number of attendees
• New volunteers DG
2007 Fall Simulation Interoperability Workshop
Near future planning & activities
• Reschedule products
• New draft versions
• Other product release dates, etc
2007 Fall Simulation Interoperability Workshop
Questions
22