25
Budgeting for Plant Maintenance 1) You can set the budget for a Maintenance order . 2) You have to create a dedicated cost centre for a Maintenance order . 3) So that everytime you create a maint order the cost is booked in that respective cost centre .

Budgetting for pm

Embed Size (px)

Citation preview

Page 1: Budgetting for pm

Budgeting for Plant Maintenance

1) You can set the budget for a Maintenance order .2) You have to create a dedicated cost centre for a Maintenance order .3) So that everytime you create a maint order the cost is booked in that respective cost centre .

Page 2: Budgetting for pm

You have to create aBudgetting Profile

In SPRO

Page 3: Budgetting for pm
Page 4: Budgetting for pm

Here enter the time frame like how u want to set the Budget. Don't Put any decimal place .Put start filed as

(1) For a current year .

Save .

Page 5: Budgetting for pm

Assign the created Budget profile ,And the cost centre in Which you will maintain the budget .

Page 6: Budgetting for pm

Enter your budget Month wise or Yearly

For yearly budget

Page 7: Budgetting for pm

Here you can put your Budget Anually.

Save it .

Page 8: Budgetting for pm

Create a Maint orderand we will see the cost of

Spares,Activity cost, Planned Cost /Actual cost / Budget .

Page 9: Budgetting for pm
Page 10: Budgetting for pm

Enter all you r details for the maintOrder. Also very important is youEnter the cost centre in location

Tab above

Page 11: Budgetting for pm

In operation Tab enter the activity done for the order Here also put the activity type .In which you decide the

Cost per hour of your Technician.

Page 12: Budgetting for pm

In the component Tab put the spares used for the order.

Release and save the order youWill get the planned cost .

Page 13: Budgetting for pm

Planned cost

Page 14: Budgetting for pm

Now you do goods issue forthe spares and do the activity

confirmation .So that you capture the actual cost .T-code- Migo( For G/I)T-code- IW37 For optn

confirmation

Page 15: Budgetting for pm

Post it

Page 16: Budgetting for pm

T- code IW37operation confiramation

Page 17: Budgetting for pm
Page 18: Budgetting for pm

Select the operation and pess the tab Individual confirmation

Page 19: Budgetting for pm

You can also do the collective confirmation .if incase your Activity is more .

Page 20: Budgetting for pm

Enter the Actual time taken for Completing the activity and tick final

Confirmation .

Page 21: Budgetting for pm

Now you had got the Actual cost .If you want to see the Plan/Actl press the tab above

Page 22: Budgetting for pm
Page 23: Budgetting for pm

For Budget / Actual.T- code –

S_ALR_87013648

Page 24: Budgetting for pm

Enter the controlling area and execute the budget

Page 25: Budgetting for pm

Here in cost centre 1703 work shop maint you Can see the budget /Allotted / Available