Detailed Longwall planning and scheduling

Embed Size (px)

DESCRIPTION

Ben Williams, Senior Mining Consultant, from Deswik delivered this presentation at 2012 Longwall conference in the Hunter Valley Australia. Building on eleven years of excellence it’s rare that such a large gathering of underground coal operators come together under the one roof, providing a great opportunity to catch up with friends, industry leaders, former colleagues and longwall mining specialists. For more information, please visit: http://www.longwallconference.com.au

Citation preview

Page 1: Detailed Longwall planning and scheduling

Detailed Longwall Planning & Scheduling

Benjamin Williams22 Oct 2012

Presented By:Date:

Longwall 2012

Page 2: Detailed Longwall planning and scheduling

Longwall 2012

• Mine planning focused consultancy and software development company

• Focused on building innovative software solutions to solve problems in the mine technical services area

• Offerings include:

– mine planning consulting

– software packages

– training and implementation

– bespoke development services

Introduction

Page 3: Detailed Longwall planning and scheduling

LondonCalgary

Johannesburg

PerthBrisbane

Wollongong

Software also used in locations such as:Sweden, Sierra Leone, New Zealand, Kazakhstan, Ghana, Colorado, Brazil,

• Offices in Brisbane, Perth, Mackay, Newcastle,

South Africa, Canada and London

• 75 People Worldwide

• Founding members consulting with and

developing mine planning software for the

past 15 years

Longwall 2012

Page 4: Detailed Longwall planning and scheduling

Integrated Software

• Deswik Suite provides a single integratedpackage that combines:

– CAD and reserves generation

– Short Term through to Long Term Scheduling

– Blending for different economic variables

– Reporting and Presentation

Longwall 2012

Page 5: Detailed Longwall planning and scheduling

Deswik.CAD

• Design

• Visualisation

• Data validation

• Graphical reporting

• Plugin environment

Deswik.IS

• Integrates CAD and Scheduler

• Process driven approach

• Rule based task generation

• Manages data

• Reconciliation

Scheduler

• Represents design as Gantt tasks

• Resource driven schedule

• Blending and low modelling module

• Plan compliance

Core Modules

Longwall 2012

Page 6: Detailed Longwall planning and scheduling

Underground Process Flow

Planning Process

Page 7: Detailed Longwall planning and scheduling

Software Goals

• Set out to design sector specific software tools to enable modern design and integrated scheduling across all levels.

• Step through several of the general and specific issues we felt needed to be addressed for UG Coal design and scheduling:

Longwall 2012

Page 8: Detailed Longwall planning and scheduling

Software for UG Coal

• Semi generic products that don’t fit UG requirements well

• PCS (Poor Cousin Syndrome)

• 2D design

• Multiple unconnected programs causing disconnects throughout the design and scheduling process.

Page 9: Detailed Longwall planning and scheduling

Longwall 2012

• Different long term – short term schedule

• UG Coal specific scheduling issues

• Repetitive Design Elements

• 2 Dimensional environment

• Complex geologic models

Common Software Issues

Page 10: Detailed Longwall planning and scheduling

LT & ST interface

• Traditionally separate models.

• Long term Schedule lacks detail required for Short term planning.

• Short term takes too long to add into Long term.

Longwall 2012

Page 11: Detailed Longwall planning and scheduling

UG Coal Scheduling Issues

• Resourcing

• Varying production rates

• Super-paneling

• Managing conveyors

• Rapid schedule changes

• Schedule analysis

Longwall 2012

Page 12: Detailed Longwall planning and scheduling

Scheduling Solutions

Longwall 2012

Page 13: Detailed Longwall planning and scheduling

Scheduling Solutions

Longwall 2012

Page 14: Detailed Longwall planning and scheduling

Scheduling Solutions

Longwall 2012

Page 15: Detailed Longwall planning and scheduling

Design

• Working within CAD environment

• Effectively polylines/strings representing drive centrelines

• Repetitive design work - not easy to modify.

Longwall 2012

Page 16: Detailed Longwall planning and scheduling

2D Design Environment

• Often restricted to a 2D environment, depending on design software package

• Important metrics like thickness, volume and dilution treated as a 2D calculation

• Visualisation of faulting and structure

Longwall 2012

Page 17: Detailed Longwall planning and scheduling

Complex Geological Models

• Grid models that treat individual plysseparately

• Aggregated models – complicated, can lose the original data

• Complex scripting calculations

Longwall 2012

Page 18: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 19: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 20: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 21: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 22: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 23: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 24: Detailed Longwall planning and scheduling

Design Solutions

Longwall 2012

Page 25: Detailed Longwall planning and scheduling

Going Forward

Longwall 2012

• Longwall Grade Smoothing

• LTCC

• Place Changing

• Manning Overlay

Page 26: Detailed Longwall planning and scheduling

Longwall 2012