3G COMMISSIONING STEPS

Preview:

Citation preview

NODE-B Commissioning guidelines

JYOSTNA INFRASTRUCTURE PRIVATE LIMITED

Er Himanshu Maurya+919807888440

PLEASE ENSURE THE FOLLOWING IP AT YOUR LAPTOP FOR CONNECTING NODE-B

ENSURE THAT SOFTWARE VERSION OF VERSION OF WN6.0 IS INSTALLED IN YOUR LAPTOP

This can be cross checked by clicking About option on left side of the BTS Manager Window

CONNECT TO THE NODE-B

User Name: Nemuadmin

Password: nemuuser

The following Pop-up Window will be observed.

Click on Update SW option.

CLICK ON CONTINUE HERE FOR UPDATING FILE

BROWSE HERE FOR FILE. CLICK ON UPDATE. ONCE THE SOFTWARE IS UPDATED, THE HARDWARE WILL BE VISIBLE (in uncommissioned state)

NOW START COMMISSIONING. CLICK ON TEMPLATE IN COMMISSIONING TYPE. BROWSE THE GOLDEN COMMISSIONING FILE (specific for RNC). THEN CLICK NEXT

EDIT SITE NAME, LOCATION, DESCRIPTION, BTS ID, TRS (Transmission) IP, BTS IP, RNC IP & NTP SERVER IP. (most imp)

CLICK ON CLOSE

CLICK ON NEXT.

CLICK NEXT. (Note: 4 E1s in IMA 33 would be already selected)

CLICK NEXT (Note: IF 1 (E1) AND IF2 (E2) in TIMING SOURCE already done)

CLICK NEXT. (Note: Traffic already defined)

CLICK NEXT. (Note: TRAFFIC already mapped) (VP1,VP0 and their VCs)

CLICK NEXT (Note: DCN INTERFACE already mapped)

CLICK NEXT. (Note: RNC IP should be in DEFAULT GATEWAY IP)

CLICK ON NEXT

CLICK NEXT. (Note: Iub sync in use would be already clicked)

CLICK NEXT. (Note: CELLS already created with 20W power

CLICK NEXT

CLICK NEXT. (Note: UARFCN already inserted as per plan)

CLICK NEXT.

CLICK NEXT

CLICK NEXT

CLICK NEXT

CLICK ON SEND PARAMETERS. BY THIS THE PARAMETERS WOULD BE SENT TO NODE-B

CLICK NEXT

CLICK NEXT

CLICK FINISH. SAVE THE COMMISSIONING FILE & COMISSIONING REPORT ON YOUR LAPTOPS AND INCLUDE COMMISSIONING REPORT’s HARD COPY IN SITE FOLDER.

Recommended