BNC Panel Test Procedure
Citation preview
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Security Level:
www.huawei.com
Vodafone IP MW Project
BNC Panel Test Procedure
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
BNC Panel Test
Page 2
Connectivity is as shown in the figure.
Test to be done by doing physical loopback on each E1.
Test on the WebLCT will be as shown in the next slide.
ALL E1s should be tested , and print screen of a successful result should be taken
CSH
IFU2 EM6F
IFU2
SP3D
E1: 1 to 16
E1: 17 to 32
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
BNC Panel Test
Page 3
Tributary Should be 0Should be 100%
Should be Green (Normal)
Start Test:-Should be performed for ALL E1s
Should be 5
1 1
2
3
3
3