Draft for discussion purposes.sfpuc0718i1-11140.pptx

Civic Design ReviewConcept Design

New Treasure Island Wastewater Treatment Plant 1/13/2020

Draft for discussion purposes.sfpuc0718i1-11140.pptx

• Project Objectives

• Project Context

• Project Delivery Approach

• Concept Design

Agenda

2

Draft for discussion purposes.sfpuc0718i1-11140.pptx 3

PROJECT OBJECTIVES

3

• SFPUC provides contracted services to TIDA for O&M of all utilities on TI/YBI through a yearly MOU

• Developer is obligated to construct and fund the new infrastructure for TI/YBI

Treasure Island Background• Naval Station Treasure Island (NSTI) is a former US Navy base located in the City and County

of San Francisco

• Treasure Island Development Authority (TIDA) is responsible for the reuse and development of NSTI and operation and maintenance of all utilities on Treasure Island and Yerba Buena Island (TI/YBI)

New TI Water Resource Recovery Facility

Project Objectives

• Address aging infrastructure • Ensure regulatory compliance• Meet the wastewater and recycled water needs of the future TI/YBI development

Draft for discussion purposes.sfpuc0718i1-11140.pptx 7

PROJECT CONTEXT

7

Project Team

8

• Project Manager – Tom Birmingham, SFPUC• Project Engineer – Calvin Huey, SFPUC• Wastewater Enterprise Liaison – Nohemy Revilla• Owner’s Agent – Carollo Engineers, Inc.• Lead Architect - Michele Hollenbaugh, Carollo Engineers, Inc• Landscape Architect - Chris Guillard, CMG Landscape Architecture

Treasure Island Master Plan Long Term Vision

9

Site Constraints

10

New Treasure Island Water Resource Recovery Facility

11

Geotechnical Improvements and SLR

Recycled Water System

13

Buildout recycled water demands:• Average Annual = 0.43 mgd• Peak = 0.98 mgd

Anticipated Recycled Water Uses:• Open space irrigation• Urban farm irrigation• Commercial Building Plumbing• Dry season Green Infrastructure

plant maintenance

Stormwater Management

14

Draft for discussion purposes.sfpuc0718i1-11140.pptx 15

PROJECT DELIVERY APPROACH

15

Alternative Project Delivery Methods

16

TRADITIONALDESIGN-BID-BUILD

DesignerGeneral Contractor

Trade Subcontractors

DESIGN-BUILD

Designer General Contractor

Trade Subcontractors

CONSTRUCTION MANAGER/GENERAL

CONTRACTOR

DesignerGeneral Contractor

Trade Subcontractors

DESIGN-BUILD-OPERATE

Designer General Contractor

Trade Subcontractors

Operator

Draft for discussion purposes.sfpuc0718i1-11140.pptx 17

CONCEPT DESIGN

17

Draft for discussion purposes.sfpuc0718i1-11140.pptx 18

Treasure Island Northeast Concept Plan

19

FUTURE WWTP AND/OR CORPORATION YARD

P R O P O S E D T I W R R F

Wetland Site Plan

20

P R O P O S E D T I W R R F

Excerpt from Treasure Island D4D (2011)

21

Facility Perimeter Design Goals

22

Facility Structure

23

Examples of Buildings to be Designed, Pending CDR Approval

24

Perimeter Design Elements

25

Preliminary Cross Sections and Sightlines

26

Wetland Barrier Fence

27

Berm and Tree Screening

28

Perimeter Enclosure

29

Perimeter Enclosure Design Requirements

30

• 10’ height• 10’ clear zone (low vegetation)• Non-climbable• Non-cuttable• Anti-tunneling continuous concrete foundation• Anti-graffiti• Durability in a marine environment

Perimeter Edge Design Requirements

31

Impasse Fence – SFPUC Standard Option

32

Design Goals

33

1. CONTINUITY WITHOUT MONOTONY

2. DIFFERENTIATE THE EDGE ON AVENUE M (EASTSIDE ROAD)

3. DESIGN TO MATCH THE SCALE OF THE SITE

4. MATERIAL INTEREST AND QUALITY

5. DURABLE AND PRACTICAL MATERIAL THAT SPEAKS TO THE INDUSTRIAL NATURE OF THE SITE

6. ENGAGE LIGHT PHENOMENA – REFLECITIVITY AND SHADOW

34

Security Perimeter Design Iterations

35

Security Perimeter Design Iterations

Security Perimeter Design Iterations

36

Security Perimeter Design Concept

37

Draft for discussion purposes.sfpuc0718i1-11140.pptx 38

PERIMETER ENCLOSURE Eastside Road View

Draft for discussion purposes.sfpuc0718i1-11140.pptx 39

PERIMETER ENCLOSURE Eastside Road View

Draft for discussion purposes.sfpuc0718i1-11140.pptx 40

PERIMETER ENCLOSURE Eastside Road View

Draft for discussion purposes.sfpuc0718i1-11140.pptx 41

PERIMETER ENCLOSUREWetland View

Draft for discussion purposes.sfpuc0718i1-11140.pptx 42

PERIMETER ENCLOSUREWetland View

Draft for discussion purposes.sfpuc0718i1-11140.pptx 43

PERIMETER ENCLOSUREWetland View

Potential Public Art Locations, to be Discussed with SFAC Staff

44

Recommended