Draft for discussion purposes.sfpuc0718i1-11140.pptx
Civic Design ReviewConcept Design
New Treasure Island Wastewater Treatment Plant 1/13/2020
Draft for discussion purposes.sfpuc0718i1-11140.pptx
• Project Objectives
• Project Context
• Project Delivery Approach
• Concept Design
Agenda
2
Draft for discussion purposes.sfpuc0718i1-11140.pptx 3
PROJECT OBJECTIVES
3
• SFPUC provides contracted services to TIDA for O&M of all utilities on TI/YBI through a yearly MOU
• Developer is obligated to construct and fund the new infrastructure for TI/YBI
Treasure Island Background• Naval Station Treasure Island (NSTI) is a former US Navy base located in the City and County
of San Francisco
• Treasure Island Development Authority (TIDA) is responsible for the reuse and development of NSTI and operation and maintenance of all utilities on Treasure Island and Yerba Buena Island (TI/YBI)
New TI Water Resource Recovery Facility
Project Objectives
• Address aging infrastructure • Ensure regulatory compliance• Meet the wastewater and recycled water needs of the future TI/YBI development
Draft for discussion purposes.sfpuc0718i1-11140.pptx 7
PROJECT CONTEXT
7
Project Team
8
• Project Manager – Tom Birmingham, SFPUC• Project Engineer – Calvin Huey, SFPUC• Wastewater Enterprise Liaison – Nohemy Revilla• Owner’s Agent – Carollo Engineers, Inc.• Lead Architect - Michele Hollenbaugh, Carollo Engineers, Inc• Landscape Architect - Chris Guillard, CMG Landscape Architecture
Treasure Island Master Plan Long Term Vision
9
Site Constraints
10
New Treasure Island Water Resource Recovery Facility
11
Geotechnical Improvements and SLR
Recycled Water System
13
Buildout recycled water demands:• Average Annual = 0.43 mgd• Peak = 0.98 mgd
Anticipated Recycled Water Uses:• Open space irrigation• Urban farm irrigation• Commercial Building Plumbing• Dry season Green Infrastructure
plant maintenance
Stormwater Management
14
Draft for discussion purposes.sfpuc0718i1-11140.pptx 15
PROJECT DELIVERY APPROACH
15
Alternative Project Delivery Methods
16
TRADITIONALDESIGN-BID-BUILD
DesignerGeneral Contractor
Trade Subcontractors
DESIGN-BUILD
Designer General Contractor
Trade Subcontractors
CONSTRUCTION MANAGER/GENERAL
CONTRACTOR
DesignerGeneral Contractor
Trade Subcontractors
DESIGN-BUILD-OPERATE
Designer General Contractor
Trade Subcontractors
Operator
Draft for discussion purposes.sfpuc0718i1-11140.pptx 17
CONCEPT DESIGN
17
Draft for discussion purposes.sfpuc0718i1-11140.pptx 18
Treasure Island Northeast Concept Plan
19
FUTURE WWTP AND/OR CORPORATION YARD
P R O P O S E D T I W R R F
Wetland Site Plan
20
P R O P O S E D T I W R R F
Excerpt from Treasure Island D4D (2011)
21
Facility Perimeter Design Goals
22
Facility Structure
23
Examples of Buildings to be Designed, Pending CDR Approval
24
Perimeter Design Elements
25
Preliminary Cross Sections and Sightlines
26
Wetland Barrier Fence
27
Berm and Tree Screening
28
Perimeter Enclosure
29
Perimeter Enclosure Design Requirements
30
• 10’ height• 10’ clear zone (low vegetation)• Non-climbable• Non-cuttable• Anti-tunneling continuous concrete foundation• Anti-graffiti• Durability in a marine environment
Perimeter Edge Design Requirements
31
Impasse Fence – SFPUC Standard Option
32
Design Goals
33
1. CONTINUITY WITHOUT MONOTONY
2. DIFFERENTIATE THE EDGE ON AVENUE M (EASTSIDE ROAD)
3. DESIGN TO MATCH THE SCALE OF THE SITE
4. MATERIAL INTEREST AND QUALITY
5. DURABLE AND PRACTICAL MATERIAL THAT SPEAKS TO THE INDUSTRIAL NATURE OF THE SITE
6. ENGAGE LIGHT PHENOMENA – REFLECITIVITY AND SHADOW
34
Security Perimeter Design Iterations
35
Security Perimeter Design Iterations
Security Perimeter Design Iterations
36
Security Perimeter Design Concept
37
Draft for discussion purposes.sfpuc0718i1-11140.pptx 38
PERIMETER ENCLOSURE Eastside Road View
Draft for discussion purposes.sfpuc0718i1-11140.pptx 39
PERIMETER ENCLOSURE Eastside Road View
Draft for discussion purposes.sfpuc0718i1-11140.pptx 40
PERIMETER ENCLOSURE Eastside Road View
Draft for discussion purposes.sfpuc0718i1-11140.pptx 41
PERIMETER ENCLOSUREWetland View
Draft for discussion purposes.sfpuc0718i1-11140.pptx 42
PERIMETER ENCLOSUREWetland View
Draft for discussion purposes.sfpuc0718i1-11140.pptx 43
PERIMETER ENCLOSUREWetland View
Potential Public Art Locations, to be Discussed with SFAC Staff