Getting the Job Done · Getting the Job Done How to Successfully Design, Permit, and Construct a...

Preview:

Citation preview

Getting the Job Done How to Successfully Design, Permit, and Construct

a Challenging Highway Crossing

Northern California Pipe Users Group 27th Annual Sharing Technologies Seminar Concord, CA February 21, 2019

Presented by:

Colin Dudley Brown and Caldwell David Mathy DCM Consulting Additional Co-Authors:

Peter Kambel City of Modesto Chris Peters Brown and Caldwell

Agenda

City of Modesto Brown and Caldwell

2

1. Project Background and Overview

2. Crossing Design Challenges

3. Permitting Process

4. Construction Observations

Project Overview

City of Modesto Brown and Caldwell

3

Project Location

Project Overview

City of Modesto Brown and Caldwell

4

• 3,100 ft of 24-in diameter RCP

• Identified in the City’s 2007 Collection System Master Plan as a high priority project due to severe corrosion of concrete and steel

• Single barrel Highway 99 crossing dating from 1950s

Project Overview

City of Modesto Brown and Caldwell

5

Project Alternatives Rehabilitation • Existing alignment difficult to access

and within flood plain • Would require continuous bypass

pumping

Replacement • Relocate to Zeff Road

• Out of flood plain • Easier access for maintenance

• Reduce amount of bypass pumping

New highway crossing included in both alternatives

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

6

Geologic Setting

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

7

Test Borings

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

8

Test Boring B-3

Tunnel Zone

Silty Sand (SM) Loose 46% fines

Poorly Graded Sand (SP) Loose 2% fines

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

9

Tunnelmans Ground Classification

Granular materials without cohesion … run like granulated sugar or dune sand

Modesto “sugar sands”

B-3, SP loose sands = running behavior

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

10

Test Boring Profiles

B-3 B-2

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

11

Very Optimistic Interpreted Tunnel Profile

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

12

Reasonable Interpreted Tunnel Profile

Crossing Design Challenges - Geotechnical

City of Modesto Brown and Caldwell

13

Very Pessimistic Interpreted Tunnel Profile

Permitting – Tunnel Description

City of Modesto Brown and Caldwell

14

• 36-inch steel casing • 3/8-inch overcut banding (3/4-inch overcut on diameter) • 344 foot length • Minimum cover = 5 feet under northbound Hwy 99 • Maximum cover = 13 feet under highway berm • Separation from highway storm drain = 16 inches

Permitting – CalTrans Coordination

City of Modesto Brown and Caldwell

15

Encroachment Permit Manual, Section 600 • Requirements at time of Design (2013 Permit Manual)

• Caltrans initial interpretation was 15 feet min. cover per the HDD requirements (Section 623.2), not bore and jack as proposed

• CalTrans concern with shallow bore and jack stemmed from excessive settlement on a previous crossing

• Tunneling (30-inch or larger bore and jack) under access-controlled right-of-way allowed only if studies establish soil structure is sufficiently stable (Table 6.1)

• Permit Manual Revised in 2018 Met with CalTrans at the Stockton District office

• Reviewed Project design in detail including: • Geotechnical conditions • Plan and profile for the crossing • Mitigation measures to address systemic settlement of

Highway 99 and impacts on 18-inch diameter storm drain

Permitting – Proposed Mitigations

City of Modesto Brown and Caldwell

16

• Geotechnical instrumentation (SMPs, SSMPs and UMPs) • 100 feet of tunnel before going under Highway 99 travel lanes

• allowed for instrumentation to check for settlement (3 SSMPs) • allowed for Contractor to dial in methods • allowed for baselining tunnel spoils weights

Permitting – Proposed Mitigations (Cont.)

City of Modesto Brown and Caldwell

17

• Permeation grouted storm drain bedding and pipe embedment

• Limited overcut to 3/8-inch banding • Required full and continuous lubrication of overcut • Monitored tunnel spoils weights • Soil plug in lead casing (no free bore) • No grade checks under travel lanes • Monitored instrumentation • Immediate contact grouting (36-inch casing) Calculated systemic settlement with 5 feet of cover and all

mitigations = 0.35”

Permitting – Project Approval

City of Modesto Brown and Caldwell

18

With all mitigations carefully included in the project plans and specifications CalTrans approved the project with 5 feet of tunnel cover.

Construction Observations – Weight of Spoils

City of Modesto Brown and Caldwell

19

Crane scale used to weigh every bucket of spoils removed

Running average monitored for significant change

Weight of spoils impacted by: • Buildup in jacking shaft • Incomplete removal by crew • Build up in casing if augers not

removed for grade checks

Construction Observations – Spoils Observation

City of Modesto Brown and Caldwell

20

Cohesiveness and fines content of spoils used to estimate behavior of tunnel face and changes in soil composition

Construction Observations – Tunnel Face Obs.

City of Modesto Brown and Caldwell

21

Tunnel face observed when line and grade was checked by laser

Note teeth marks from cutter head in face of tunnel. Typical of tunnel face at grade checks.

Construction Observations

City of Modesto Brown and Caldwell

22

Very Optimistic Interpreted Tunnel Profile

Construction Observations

City of Modesto Brown and Caldwell

23

Settlement monitors • Surveyed every 2 hours during

boring operations • Showed little to no settlement

Contact Grouting

• Total injected was less than theoretical void space

• Indicative of tight void space and use of lubrication

Project Team and Costs

City of Modesto Brown and Caldwell

24

Owner: City of Modesto Designer: Brown and Caldwell Trenchless Consultant: DCM Consulting Geotechnical Engineer: Crawford and Associates General Contractor: Rolfe Construction Boring Contractor: Pacific Boring Total Project Cost: $5,744,000 Bore and Jack Cost (including shafts): $613,000 (~$50/in-dia/ft)

Thank you.

Questions?

Recommended