Oak Street Bridge PreservationCity of Schenectady,

Schenectady County

October 24, 2018

Roger Laime, P.E.

Associate Vice President

Christopher Wallin, P.E.

City Engineer

Background

• Constructed in 1937 over existing rail tracks and Sweethill Creek

• Six (6) Total Spans

• Steel Girder and Floor beam System

• Two driving lanes flanked by sidewalks

Project Location

Schenectady County

City of Schenectady

Project Location

Fire Station

School

Bellevue

Mount Pleasant

How We Got Here

Ambiguous Ownership

Bridge Ownership

• Historically ownership split:

– City owns and maintains the deck

– Railroad owns and maintains the substructure

• Other Similar Owned Bridges in City:

– Kings Road Bridge

– Crane Street Bridge

Bridge Closure

• NYSDOT issued a letter to the Railroad regarding the bridges condition.

• Railroad makes “repairs”, April 2014

• Bridge closed to traffic April 2013 due to deterioration of steel.

Funding Strategies

• Project listed on Transportation Improvement Program (TIP) list for replacement POST 2018

• TIP Amendment submitted to the local Metropolitan Planning Organization (MPO) to bring project into current TIP.

– Scope Change to Preservation

– Estimate reduced ($4.1M to $2.05)

– Timeline changed to 2014 Design, 2015Construction

Project Timeline

• Consultant selected - April, 2014

• Temporary Permit to Enter (TPE) granted for survey - August, 2014

• TPE granted for inspection - November, 2014

• Preliminary and Final Design - 2015 through 2017

• Construction 2018 with substantial completion August 2018

Railroad Agreements and Costs

• Draft Design & Construction Phase Agreement with Railroad

– Communication begins - April, 2015

– Draft Agreement - January, 2016

– Authorized Agreement - September, 2016

• Design Review, $98,360

• Construction Personnel (flaggers), $314,860

WARNING THE FOLLOWING BRIDGE PHOTOS ARE RATED:

Bridge Conditions - 2017

Looking East

Bridge Conditions - 2017

Looking East

Cables installed by Railroad

Bridge Conditions - 2017

Looking West

Bridge Conditions - 2017

Looking West

Cables installed by Railroad

Bridge Conditions - 2017

Cables, Ties and Section Loss

Bridge Conditions - 2017

Section Loss & Corrosion

Bridge Conditions - 2017

Section Loss & Corrosion

Bridge Conditions - 2017

Section Loss & Corrosion

PDH Question #1

• What must a Consultant or Contractor secure before entering onto Railroad property?

a) A certified resolution from the local Municipality

b) A copy of the railroads insurance

c) A Temporary Permit to Enter (TPE) from the Railroad

d) A ticket from the nearest train station

Design Issues• How to maximize repairs with a fixed budget

– Identified required repairs

Design Issues• How to maximize repairs with a fixed budget

– Identified required repairs

– Prepared preliminary estimatesPier Steel Repairs $529,000Superstructure Steel Repairs $371,000Clean and Paint Bridge $1,475,000Additional Superstructure Steel Repairs $136,000Repair Expansion Joints $28,000Abutment and Pier Concrete Repairs $57,000Clean and Lubricate Bearings $50,000Repair Curb / Reseal Joint -Slab and Sidewalk $42,000

Total Estimated Construction Cost $2,688,000

Design Issues• How to maximize repairs with a fixed budget

– Identified required repairs

– Prepared preliminary estimates

– Discussed pros and cons of each

- Pier Steel Repairs- Superstructure Steel Repairs- Clean and Paint Bridge- Additional Superstructure Steel Repairs- Repair Expansion Joints- Abutment and Pier Concrete Repairs- Clean and Lubricate Bearings- Repair Curb / Reseal Joint -Slab and Sidewalk

Design Issues• Where to draw the line when making repairs

Design Issues• The cost of bridge painting

Painting Cost Estimate: $1.5 Million

Construction Issues• Difficult Site Access from below

• Maintaining Pedestrian Access

Construction Issues

• Steel Crack Repairs

• Rivet Replacements

“. . . bring the structure up to the current AASHTO code requirements for strength, service life, and fatigue resistance.”

PDH Question #2

• Riveted connections in structures are classified as what category for fatigue resistance per the AASHTO Specifications:

a) Category A

b) Category B

c) Category C

d) Category D

Construction Issues• Working with the railroad

Construction Issues

• Maintaining Construction schedule

Original Completion Schedule: July 2016Actual Completion: August 2018

Construction Issues

• Deck Repairs

PDH Question #3

• Clear cover on concrete bridge decks, based on NYSDOT guidelines, using epoxy reinforcement is:

a) 2”

b) 2.5”

c) 3”

d) 3.5”

Construction Issues

• Appearance is everything

– Cleaning, painting and maintenance above the deck (what the public sees)

Construction Issues

Before

Construction Issues

After

Construction Issues

After-After

Construction Issues

• Bridge Deck deficiencies– Concrete test results

Test sample failed due to excessive deleterious material (shale and phyllite)

Summary• Project Schedule

– Design Completed: 2015

– Construction planned: 2016 (on STIP)

– Construction actual: 2017 – 2018

– Bridge Opened to Traffic: August 7, 2018

• Project Cost

– Actual Construction Cost - $1.75 Million

QUESTIONS ?