SE REGION PROJECT UPDATE BUREAU OF
TRAFFIC OPERATIONSPresenter:
Dewayne Johnson, P.E.
SE Region Director/Bureau of Traffic Operations Director
SCHEDULEOVERVIEW
• 2014: Watertown Plank
Road (including US 45
interchange)
• 2014: WIS 100 bridge,
UPRR bridge and 76th Street
bridge over I-94
• Fall 2014 – Summer 2016:
Core Phase 1
• Fall 2015 – Winter 2017
Core Phase 2
• 2016 Center Street Bridge
• 2017 - 2018: North Leg
I-94 NORTH SOUTH PROJECT SCHEDULE
WIS 20 Interchange Construction of I-94 Northbound freeway and modernized entrance and exit ramps at WIS 20
WIS 142 to WIS 158:Completion of Freeway expansion and interchange improvements on I-94 southbound
WIS 50 Local RoadsCompletion of local road improvements adjoining the newly constructed interchange.
I-43 CORRIDOR STUDY PROJECT SCHEDULE
Current (this year):•Summer 2014 – Final of Environmental Impact Statement (EIS) anticipated•Fall 2014 – Functional plans of alternative development & Record of Decision Environmental Clearance anticipated•2014 – Agency coordination completion is anticipated
I-90/39 SOUTHWEST REGIONPROJECT SCHEDULE
Current 2014: WIS 73 reconstruction from I-39/90 north to US
12/18 in Dane County Reconstruct the I-39/90 southbound bridge over
Siggelkow Road, south of the US 12/18 interchange near Madison
Pavement repairs on I-39/90 northbound and southbound from Milwaukee Street in Janesville to just north of the WIS 73/US 51 interchange in Dane County
Future 2015: I-39/90 construction scheduled to start 2021 Construction expected to be completed
I-90 STILLWATER BRIDGEPROJECT SCHEDULE
March 10 through Nov. 14, 2014: Complete first phase of project
Week of June 2, 2014: •Place concrete for bridge radius walls • Remove dirt at the new interchange (County E)
Fall 2016 - Full project completion