Sea Port Construction, Project Execution Plan

Preview:

Citation preview

David H Moloney

14th August 2016

Sea Port Construction, Project Execution PlanDetails of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.

http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan

Brief Description

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Sea Port .

This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.

High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)This Video Presentation is innovative and has many beneficial uses.

Video https://www.youtube.com/watch?v=6_Aco_GPO8I

Contents

ⓒ David H Moloney

Introduction

Quay WallQ

uay W

all

Quay WallQ

uay W

all

Brief Description

The quay wall is constructed using precast reinforced concrete hollow blocks that weigh up to 160 tonnes. The blocks were cast in the on-site precast yard and loaded onto barges at the temporary loading jetty that had a 200 tonne capacity gantry crane.

A screeding frame that extended from the sea bet to above water was used to place the bedding layer to the correct level.Up to 22 blocks were placed per day using a barge with a crane.Part of the coping beam was cast in-sit-u in sections using concrete pumps positioned on the reclaimed land behind the quay wall.

Sequence & Methods to Construct Quay WallQ

uay W

all

3D Animation

Quay-wall

ⓒ David H Moloney

Placing Precast Quay Blocks Placing Precast Quay Blocks

Screed Frame for preparing Granular Foundation Placing Precast Quay Blocks

Quay Wall Beam

Screed FrameM

iscella

ne

ous

Brief Description

Duqm, Oman

Mooring Bollards & Marine FendersM

iscella

ne

ous

Marine Equipment ⓒ David H Moloney

Drawing – Quay Wall Cross Section

Breakwater & WavewallB

reakw

ate

r &

Wavew

all

Breakwater & WavewallB

reakw

ate

r &

Wavew

all Brief Description

The breakwater is constructed using core rock, rock armour, precast armour units and geotextile.The core rock is placed using split hopper barges in deep water and by lorry tipping and dozers in shallow water where the risk of slippage is minimal.The precast armour units are placed using crawler cranes fitted with a real-time visual aid system that enabled 70 placements per day.The wave wall is cast in-sit-u in 6 metre long sections.

Sequence & Methods to Construct Breakwater & WavewallB

reakw

ate

r &

Wavew

all

Breakwatersⓒ David H Moloney

Filling Barge with Rock – Temporary Jetty Placing Rock Fill

Breakwater under Construction Placing Rock Armour

Breakwaters

Placing Rock Fill

Breakwater under Construction

Barges for Rock Fill

Geotextile

Precast Sea Armour

Placing Armour

Rock Sea Armour

Placing Armour

Sea Wall

Drawing – Breakwater Cross Section

Quarry Run Rock Fill

Drawing – Breakwater Cross Section

Quarry Run Rock Fill

Wave Wall

Geotextile

Rock Armour 0.5 - 1 ton

Precast Armour

Rock Armour 1 - 3 ton

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty Brief Description

Full-scale sample castings are constructed to demonstrate and document that all the requirements of the concrete and the execution of the work are fulfilled using the actual methods and performed by personnel that will carry out the future castings. One concrete component of each type is produced for approval. The approved castings were retained in a dedicated area for quality assurance purposes.

All works were inspected in accordance with the Inspection & Test Plan on an ongoing basis, in accordance with the site Project Quality Plan. The ITP set out in matrix form the sequence of inspection steps, the governing document (specification, standards), the standard to be achieved, the persons witnessing and the supporting documents to be produced.

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Precast Yard & Loading JettyP

recast Y

ard

& L

oadin

g J

etty

Pre-casting Quay Blocks

Precast Sea Armour

Shutters for Precast Sea Armour Shutters for Precast Sea Armour

Quarry & Aggregate Production

3D image to show Sequence, Method & Plant.

ⓒ David H Moloney

Quarry

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Concrete Batching Yard

Silos, Ice Flake Plant, Chilled water, Mixer

Storage bays for aggregates

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Reinforcement Cutting & Bending

ⓒ David H Moloney

Concre

te

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Concre

te

Concrete MixG

enera

l Item

s

A concrete mix contains 5 major

elements: cement, water, coarse

aggregates, fine aggregates (sand) and

air in different proportion. Additional

elements such as pozzolanic materials (fly

ash, silica fumes or slag) and chemical

admixtures can also be incorporated to

the mix to increase its properties.

Vibrating Concrete

ⓒ David H Moloney

Concre

te

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion Brief Description

Dredgers are marine vessels used to excavate and fill under water.

Types

1. Cutter Suction Dredgers are used to dredge hard soils by cutting

and breaking up the soil using a rotating head at the end of a pipe

which is lowered onto the sea bed. The fragmented material is

sucked and pumped either into a hopper barge or through a floating

pipeline. During operation the dredger is anchored by a spud that

allows the cutting head to swing in an arc.

2. Trailing Suction Hopper Dredgers are used to dredge soft and

loose soils, gravels and silts. There are two suction drag heads

which are lowered onto the sea bed. These move with the dredger

along the sea bed. The dredged material is sucked and pumped

either into the hopper or through a floating pipeline to a discharge

area.

Dredging & ReclamationD

red

gin

g &

Recla

ma

tion

Dredger - Trailing Suction D

red

gin

g &

Recla

ma

tion

Boskalis Netherlands

Dredger - Cutter Suction D

red

gin

g &

Recla

ma

tion

Boskalis Netherlands

Dredger - Backhoe D

red

gin

g &

Recla

ma

tion

Rock - Excavability

The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.

ⓒ David H Moloney

Vibro Compaction - Fill behind Quay

Vibro Compaction - Fill behind Quay

Ground Improvement using deep vibro-compaction.

Purpose is to provide protection against liquefaction during a seismic

event. Also to provide a specified minimum ground bearing capacity.

Vibro-compaction was use to compact the Dubai man made islands

that were constructed from dredged sand.

Equipment.

Vibroflot with extension tube, hydraulic power pack mounted on crane,

diesel engine driven water jetting pumps, compressors, crawler cranes

60 tonne capacity, water tank, de-watering pump

Vibro Compaction - Fill behind Quay

3D image to show Sequence, Method & Plant.

David H Moloney

ⓒ David H Moloney

Vibro CompactionV

ibro

Com

pa

ction

Surv

eyin

g &

settin

g O

ut

Survey & Setting Out

Surv

eyin

g &

settin

g O

ut

Brief Description

Ope

Survey & Setting Out

Survey Tower

Setting out & Surveying

Setting out & Surveying

Port OperationP

ort

Opera

tio

n

Port OperationP

ort

Opera

tio

n

Port OperationP

ort

Opera

tio

n

Port OperationP

ort

Opera

tio

n

Site Facilities & Temporary WorksS

ite F

acili

tie

s &

tem

pora

ry W

ork

s

Site Facilities & Temporary WorksS

ite F

acili

tie

s &

tem

pora

ry W

ork

s

Welfare Facilities

ⓒ David H Moloney

Genera

l Item

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Site Hoarding examples

ⓒ David H Moloney

Genera

l Item

s

Wheel Wash Drive-through

ⓒ David H Moloney

Genera

l Item

s

Wheel Wash Drive-throughG

enera

l Item

s

Temporary Electricity Supply & Tower Lights

Generators

Genera

l Item

s

Dewatering

ⓒ David H Moloney

Genera

l Item

s

Concrete Batching Yard 3 Nr MixersG

enera

l Item

s

Health, Safety & EnvironmentalH

ealth, safe

ty &

environ

menta

l

Emergency Phone Numbers & Response

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Site Safety Posters examples

Safety Precautions

Personal Protective Equipment (PPE)H

ealth,

Safe

ty &

Environm

ent

Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection

Safety Training on Site M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Safety Training Matrix M

iscella

ne

ous

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Emergency Response Drill H

SE

Drills and exercises are used to rehearse anticipated emergency scenarios

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Hazardous Substances Symbols H

ealth,

Safe

ty &

Environm

ent

COSHH stands for the Control of Substances Hazardous to Health

Shown are the new hazard symbols

Water Pollution PreventionG

enera

l Item

s

Segregation of Waste H

ealth,

Safe

ty &

Environm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Putting Waste Concrete to use

ⓒ David H Moloney

Health,

Safe

ty &

Environm

ent

Precast bases for signs and hoarding, Precast blocks for walls.

AdministrationA

dm

inis

tration

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Staff Responsibility Matrix

Staff Directory

Brief Description

List of staff and their

contact details

Daily Work Record

Brief Description

Daily Work Records showing the

allocation of resources, materials and

work activities carried out daily.

Quotations Comparison Sheet

Filing System

Quality AssuranceQ

ualit

y A

ssura

nce

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Laboratory

ⓒ David H Moloney

Asphalt P

avin

g

Programme & Progress MonitoringP

rogra

mm

e &

Pro

gre

ss M

onitori

ng

Progress Monitoring & Reporting - Dashboard

ⓒ David H Moloney

Dashboard is a single page, graphical representation of current progress and historical trends

Histogram Charts for Resources & Outputs

Manpower per Discipline Concrete per Location

Numbers for each month of the Project Quantity for each month of the Project

ⓒ David H Moloney

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Other ProjectsO

ther

Pro

jects

Brief Description

Jetty for Kuwait Causeway

Other Projects

Jetty for Kuwait Causeway

Other Projects

Brief Description

Concrete Batching Plant on Barge.

Kuwait Causeway

Other Projects

Kuwait Causeway Offshore Piling

Other Projects

Concrete Batching Plant on Barge. Kuwait Causeway

Other Projects

Pile Driving

Other Projects

Temporary Bridge

Other Projects

Temporary Bridge Piling

Other Projects

Brief Description

Marine Piles

Other Projects

Brief Description

Screed Frame. Morocco

Other Projects

Brief Description

Quay Wall Ruwais UAE

Other Projects

Brief Description

Dubai Palm Island, Rock Armour

Other Projects

Brief Description

Dubai Creek, strengthen

quay wall with sheet piles and

ground anchors

Other Projects

Brief Description

Abu Dhabi Quay Wall

Other Projects

Brief Description

St. Croix Bridge

Other Projects

Brief Description

Cofferdams examples

Other Projects

Jebel Ali DubaiOther Projects

Jebel Ali Dubai

Ports

Muscat Omani

Dublin Cork

Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I

Recommended