Connect Offshore Wind 12 September 2013

ir. Han van Asten, Programma manager TenneT

Rotterdam / Arnhem, 12 September 2013

Connect Offshore Wind 'Met EMVT op Zee'

Page 2: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Met EMVT op Zee: Connect Offshore Wind

2

• Introduction TenneT

• Video Installation DolWin Alpha

• TenneT Offshore Germany

• Regulatory Framework & Licensing

• Technology & Industry

• Comparison Germany - Netherlands

Page 3: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013 3

About TenneT

• TenneT is responsible for connecting electricity producers

to the high-voltage grid

• TenneT does not distinguish between different producers and is

obligated by law to connect all parties to the grid

Additional tasks

• Maintaining the balance between electricity supply and demand (50 Hz)

• Ensuring the security of supply

• Importing and exporting electricity and maintaining the programme

responsibility system

Page 4: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013 4 4

From

• Stable, predictable (price-driven)

energy generation

• Maintenance and (limited)

replacement

• Focus on technology

• Local markets, separate price zones

• National focus and regulation

To

• Fluctuating (nature-driven) energy

generation

• Large-scale new construction

• Technology and market

• North-Western European market,

price convergence

• Grid planning and regulation at

European level

Radically changing role and tasks of TSOs

New roles and tasks of TSOs

Page 5: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013 5

Two grid operators – One company

As Europe’s first cross-border grid operator, TenneT has been safeguarding the

security of supply in the Netherlands and large parts of Germany since 2009:

• Management, maintenance and expansion of the transmission grid

• Promoting integration of the European electricity market

• Linking up offshore wind parks to the German grid

1) 220/380 kV grid

1998 2008 2009 2010

Electricity Act:

TenneT acquires

Dutch national

electricity grid

(220/380 kV)

TenneT acquires

Dutch national

electricity grid

(110/150 kV)

E.ON Netz1)

changes its name

to transpower.

TenneT acquires

transpower and

becomes first

cross-border grid

operator

transpower

becomes

TenneT TSO

2000

E.ON Netz

established

Page 6: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013 6

TenneT strategy 2002-2020

• Ensuring a continuous supply of electricity, any time

and anywhere, 24 hours a day and seven days a week

• Offering an excellent price/quality ratio

• Responding to energy-related developments in society

and contributing to the achievement of energy-related

objectives

• Actively promoting European market integration

through targeted investments

• Creating value for our shareholders

‘Strengthen

& Build’ 2002-

2010

‘Distribute & Store’

2011-2020

Page 7: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

TenneT key figures

• Total grid length 20.392 km

• Transformer substations 443

• No. of customers 36 million

• Installed capacity 67,000 MW

• No. of staff 2,293

• Customer satisfaction 7.9

• Interconnections 14

• Revenues 2012 EUR 1,8 billion

Page 8: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Installing DolWin Alpha

2,5 minute film

8

Page 9: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Developments Germany

Energiewende

Geopolitical arguments

Renewable Energy Sources

Atomausstieg

Industry Policy

Actuals:

32000 MW Solar

33000 MW Onshore Wind

400 MW Offshore Wind

9

Page 10: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

13.000 MW Offshore Wind in 2022

Offshore goals of federal government until 2022: 13.000 MW in total, 11.000

MW to be connected by TenneT.

3 Offshore wind farms in operation, 28 licensed and more than 60 in the

licensing process.

With a fixed investment volume of approx. 6 billion Euro TenneT is largest

Investor in the „Energiewende“ and provides connection capacity of 6.200

MW.

10

Page 11: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Connecting Offshore Wind

-> 2022: 11000 MW -> 2030: 25000 MW

11

Page 12: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Comparison AC and DC

Cost for transmission of energy

12

Cost [€]

Distance [km]

50-100 km for cables

600-800 km for lines

DC

AC

Page 13: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

A typical grid connection in German North Sea

13

Leistung: 800 Megawatt

Kabellänge:165 km

• an Land: 90 km

• auf See: 75 km

Page 14: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Status Offshore Grid Connections in North Sea

14

Project Capacity

(MW) 1)

Expected

PAC Contractor AC/DC

Built / in Operation

alpha ventus 60 2009 AC

BorWin1 (West) 400 Q1/2014 ABB DC

Under Construction / Awarded

BorWin2 (West) 800 Q1/2015 Siemens Prysmian DC

AC Dt. Bucht to BorWin2 xx Q4/2015 Prysmian AC

DolWin1 (West) 800 Q1/2014 ABB DC

DolWin2 (East) 900 Q1/2015 ABB DC

DolWin3 900 Q3/2017 Alstom DC

HelWin1 576 Q4/2014 Siemens/Prysmian DC

HelWin2 690 Q1/2015 Siemens/Prysmian DC

SylWin1 2) 864 Q3/2014 Siemens/Prysmian DC

Riffgat 108 Q3/2013 NKT AC

Nordergründe 111 Q3/2015 ABB AC

∑ Built / Awarded 6.209

PAC=Preliminary Acceptance Certificate (after trial operation)

1) Total grid connection capacity

2) According to the new legislation the remaining capacity of 288 MW was allocated by BNetzA to OWF Sandbank

Page 15: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

TSO has obligation to connect OWF offshore

15

Offshore Wind Farm

Grid connection (TSO)

Investment trigger criteria by OWF for grid connection: 1. Permits awarded

2. Construction schedule

3. Soil investigation

4. Major contracts awarded & obliging financing of wind turbines

Approx. 36 months Feed in

by OWF t

Page 16: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Regulatory Framework: The business context

is improving

16

Political-/Business context:

Uncapped liabilities -> capped liabilities; enabling investors (ao Mitsubishi Corporation)

Windfarm driven connections -> plan driven connections, A 10 year Offshore Netz Entwickelungs Plan) ONEP‘:

September 22: elections 6200 MW connection, 2700 MW OWP FID

Restructure Energiewende & EEG

Page 17: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Licensing is complex and takes time

OWF: License by BSH (Bundesamt für Schifffahrt & Hydrographie

TSO: BSH, PFV (Plan Feststellung Verfahren), BimSchG, private

agreements

All parties are learning

17

Page 18: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Technology & Industry, Cables and cable

installation

18

Page 19: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Single core cable

Double core

cable

Developments Cable

MI cables up to 550 kV

XLPE cables up to 320 kV (500 kV?)

Depth of Burial 3 meter

Cable production capacity

19

Page 20: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

High Voltage Direct Current Converters

20

Page 21: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Grid Connection Options for OWF

= ~

= ~

= ~

= ~

OWF

Filter,

compensation,

etc.

Filter,

compensation,

etc.

Filter,

compensation,

etc.

Filter,

compensation,

etc.

OWF OWF

Offshore Offshore

Onshore Onshore

AC-technology DC-technology

21

Page 22: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Developments HVDC

VSC systems up to 600 kV

Cables up to 500 kV

1500 MW in one connection

DC switch / Transformer

DC grids

Offshore

Super grid

22

North Sea Country Y

North Sea country X

Offshore Windfarm

1000 MW

Cable

500 MW or

1500 MW

Cable

500 MW or

1500 MW

North Sea Country Y

North Sea country X

Offshore Windfarm

1000 MW

Interconnector

1500 MW

Business cases

to be compared

Maximise OEE

Page 23: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Offshore Platforms

23

Page 24: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013 24

BorWin alpha 400 MW:

BorWin beta 800 MW:

HelWin alpha 576 MW:

HelWin beta 690 MW:

DolWin alpha 800 MW:

DolWin beta 900 MW:

DolWin gamma 900 MW:

SylWin alpha 864 MW:

Page 25: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Developments: standard platform

25

(LxBxH):

82,7 x 56 x 26 m

Page 26: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Offshore Platforms

26

Page 27: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

NL well positioned for offshore grid connections

NL based industries active in German offshore grid connections:

• Cable production (land)

• Cable installation

• Platform manufacturing

• Platform installation

• Consultancy

And many others for OWF

27

Page 28: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Comparison Offshore Wind in NL vs D

28

NL D

Ambition 2022 4450 MW 11000 MW

Ambition 2030 10000 (?) MW 25000 MW

Operational 228 MW 460 MW

Awarded (expressed in connection capacity) 958 MW 6200 MW

Connection TSO Onshore (??) Offshore

Page 29: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Grids connect production with consumption

29

Grid = offshore and onshore

D: onshore grid to be reinforced

NL: offshore wind can be close to load

Page 30: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Experiences to be taken into account:

Regulatory framework & Licenses • Balanced regulatory framework (liabilities, financing)

• Focus offshore and onshore

• Long lead times for licenses onshore

• Planned development

Technology & Industry • New technologies in HV grids

• New combinations of technologies/suppliers

• Planned development, Standardisation

• Supply chains to be built up

30

Page 31: EMVT 12 september - Han van Asten - TenneT

Connect Offshore Wind 12 September 2013

Energie akkoord promising for Offshore Wind

TenneT experience available for Dutch

Offshore wind connections

31

Page 32: EMVT 12 september - Han van Asten - TenneT

TenneT is Europe’s first cross-border grid

operator for electricity. With approximately

20,000 kilometres of (Extra) High Voltage

lines and 36 million end users in the Netherlands

and Germany we rank among the top five

grid operators in Europe. Our focus is to

develop a north-west European energy

market and to integrate renewable energy.

www.tennet.eu