PowerPoint Presentation by Charlie Cook PowerPoint Presentation by Charlie Cook Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. THE MANAGERIAL PROCESS Clifford F. Gray Eric W. Larson Third Edition P ro ject M a n a g em en t P ro ject M a n a g em en t Chapter 5 Chapter 5 Estimating Project Times and Estimating Project Times and Costs Costs

Estimating Project Times and Costs

  • View
    10.963

  • Download
    10

Embed Size (px)

DESCRIPTION

Project Management, Authors: Clifford F. Gray, Eric W. Larson, Third Edition, Ch 5

Citation preview

Page 1: Estimating Project Times and Costs

PowerPoint Presentation by Charlie CookPowerPoint Presentation by Charlie CookCopyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved.2006 The McGraw-Hill Companies. All rights reserved.

THE MANAGERIAL PROCESSTHE MANAGERIAL PROCESS Clifford F. GrayEric W. Larson

Third Edition

Clifford F. GrayEric W. Larson

Third Edition

Pr ojec t ManagementPr ojec t Management

Chapter 5Chapter 5

Estimating Project Times and CostsEstimating Project Times and Costs

Page 2: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––22

Page 3: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––33

Estimating Projects Estimating Projects Estimating Projects Estimating Projects

• Estimating–The process of forecasting or approximating the time

and cost of completing project deliverables.–The task of balancing the expectations of stakeholders

and the need for control while the project is implemented

• Types of Estimates–Top-down (macro) estimates: analogy, group

consensus, or mathematical relationships–Bottom-up (micro) estimates: estimates of elements of

the work breakdown structure

Page 4: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––44

Why Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are ImportantWhy Estimating Time and Cost Are Important

EXHIBIT 5.1

• Estimates are needed to support good decisions.• Estimates are needed to schedule work.• Estimates are needed to determine how long the project

should take and its cost.• Estimates are needed to determine whether the project

is worth doing.• Estimates are needed to develop cash flow needs.• Estimates are needed to determine how well the project

is progressing.• Estimates are needed to develop time-phased budgets

and establish the project baseline.

Page 5: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––55

Factors Influencing the Quality of EstimatesFactors Influencing the Quality of EstimatesFactors Influencing the Quality of EstimatesFactors Influencing the Quality of Estimates

Quality of Quality of EstimatesEstimates

Quality of Quality of EstimatesEstimates

ProjectProjectDurationDuration

ProjectProjectDurationDuration

PeoplePeoplePeoplePeople

Project Structure Project Structure and Organizationand Organization

Project Structure Project Structure and Organizationand Organization

PaddingPaddingEstimatesEstimates

PaddingPaddingEstimatesEstimates

OrganizationOrganizationCultureCulture

OrganizationOrganizationCultureCulture

Other (Nonproject)Other (Nonproject)FactorsFactors

Other (Nonproject)Other (Nonproject)FactorsFactors

Planning Planning HorizonHorizon

Planning Planning HorizonHorizon

Page 6: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––66

Estimating Guidelines for Times, Estimating Guidelines for Times, Costs, and ResourcesCosts, and Resources

Estimating Guidelines for Times, Estimating Guidelines for Times, Costs, and ResourcesCosts, and Resources

1. Have people familiar with the tasks make the estimate.

2. Use several people to make estimates.

3. Base estimates on normal conditions, efficient methods, and a normal level of resources.

4. Use consistent time units in estimating task times.

5. Treat each task as independent, don’t aggregate.

6. Don’t make allowances for contingencies.

7. Adding a risk assessment helps avoid surprises to stakeholders.

Page 7: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––77

Macro versus Micro EstimatingMacro versus Micro EstimatingMacro versus Micro EstimatingMacro versus Micro Estimating

TABLE 5.1

Conditions for Preferring Top-Down or Bottom-up Time and Cost Estimates

Condition Macro Estimates Micro Estimates

Strategic decision making X

Cost and time important X

High uncertainty X

Internal, small project X

Fixed-price contract X

Customer wants details X

Unstable scope X

Page 8: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––88

Estimating Projects: Preferred ApproachEstimating Projects: Preferred ApproachEstimating Projects: Preferred ApproachEstimating Projects: Preferred Approach

• Make rough top-down estimates.

• Develop the WBS/OBS.

• Make bottom-up estimates.

• Develop schedules and budgets.

• Reconcile differences between top-down and bottom-up estimates

Page 9: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––99

Methods for Estimating Project Methods for Estimating Project Times and CostsTimes and Costs

Methods for Estimating Project Methods for Estimating Project Times and CostsTimes and Costs

• Macro (Top-down) Approaches

–Consensus methods

–Ratio methods

–Apportion method

–Function point methods for software and system projects

–Learning curves

Project EstimateTimesCosts

Page 10: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1010

Apportion Method of Allocating Project Costs Apportion Method of Allocating Project Costs Using the Work Breakdown StructureUsing the Work Breakdown Structure

Apportion Method of Allocating Project Costs Apportion Method of Allocating Project Costs Using the Work Breakdown StructureUsing the Work Breakdown Structure

FIGURE 5.1

Page 11: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1111

Simplified Basic Function Point Count Process Simplified Basic Function Point Count Process for a Prospective Project or Deliverablefor a Prospective Project or Deliverable

Simplified Basic Function Point Count Process Simplified Basic Function Point Count Process for a Prospective Project or Deliverablefor a Prospective Project or Deliverable

TABLE 5.2

Page 12: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1212

Example: Function Point Count MethodExample: Function Point Count MethodExample: Function Point Count MethodExample: Function Point Count Method

TABLE 5.3

Page 13: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1313

Methods for Estimating Project Methods for Estimating Project Times and Costs (cont’d)Times and Costs (cont’d)

Methods for Estimating Project Methods for Estimating Project Times and Costs (cont’d)Times and Costs (cont’d)

• Micro (Bottom-up) Approaches

–Template method

–Parametric Procedures Applied to Specific Tasks

–Detailed Estimates for the WBS Work Packages

–Phase Estimating: A Hybrid

Page 14: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1414

SB45 Support Cost Estimate WorksheetSB45 Support Cost Estimate WorksheetSB45 Support Cost Estimate WorksheetSB45 Support Cost Estimate Worksheet

FIGURE 5.2

Page 15: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1515

Phase Estimating over Product Life CyclePhase Estimating over Product Life CyclePhase Estimating over Product Life CyclePhase Estimating over Product Life Cycle

FIGURE 5.3

Page 16: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1616

Level of DetailLevel of DetailLevel of DetailLevel of Detail

• Level of detail is different for different levels of management.

• Level of detail in the WBS varies with the complexity of the project.

• Excessive detail is costly.–Fosters a focus on departmental outcomes–Creates unproductive paperwork

• Insufficient detail is costly.–Lack of focus on goals–Wasted effort on nonessential activities

Page 17: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1717

Developing BudgetsDeveloping BudgetsDeveloping BudgetsDeveloping Budgets

• Time-Phased Budgets–A cost estimate is not a budget unless it is time-

phased.•Time phasing begins with the time estimate for a

project.•Time-phased budgets mirror how the project’s cash

needs (costs) will occur or when cash flows from the project can be expected.

•Budget variances occur when actual and forecast events do not coincide.

Page 18: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1818

Work Package EstimatesWork Package EstimatesWork Package EstimatesWork Package Estimates

FIGURE 5.4

Page 19: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––1919

Three Views of CostThree Views of CostThree Views of CostThree Views of Cost

FIGURE 5.5

Page 20: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2020

Types of CostsTypes of CostsTypes of CostsTypes of Costs

• Direct Costs–Costs that are clearly chargeable to a specific work

package.•Labor, materials, equipment, and other

• Direct (Project) Overhead Costs–Costs incurred that are directly tied to an identifiable

project deliverable or work package.•Salary, rents, supplies, specialized machinery

• General and Administrative Overhead Costs–Organization costs indirectly linked to a specific

package that are apportioned to the project

Page 21: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2121

Contract Bid Summary CostsContract Bid Summary CostsContract Bid Summary CostsContract Bid Summary Costs

FIGURE 5.6

Direct costs $80,000

Direct overhead $20,000

G&A overhead (20%) $20,000

Profit (20%) $24,000

Total bid $144,000

Page 22: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2222

Refining EstimatesRefining EstimatesRefining EstimatesRefining Estimates

• Reasons for Adjusting Estimates–Interaction costs are hidden in estimates.–Normal conditions do not apply.–Things go wrong on projects.–Changes in project scope and plans.

• Adjusting Estimates–Time and cost estimates of specific activities are

adjusted as the risks, resources, and situation particulars become more clearly defined.

Page 23: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2323

Refining Estimates (cont’d)Refining Estimates (cont’d)Refining Estimates (cont’d)Refining Estimates (cont’d)

• Contingency Funds and Time Buffers–Are created independently to offset uncertainty.–Reduce the likelihood of cost and completion time

overruns for a project.–Can be added to the overall project or to specific

activities or work packages.–Can be determined from previous similar projects.

• Changing Baseline Schedule and Budget–Unforeseen events may dictate a reformulation of the

budget and schedule.

Page 24: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2424

Creating a Database for EstimatingCreating a Database for EstimatingCreating a Database for EstimatingCreating a Database for Estimating

FIGURE 5.7

Estimating Database Templates

Page 25: Estimating Project Times and Costs

Copyright Copyright © © 2006 The McGraw-Hill Companies. All rights reserved. 2006 The McGraw-Hill Companies. All rights reserved. McGraw-Hill/Irwin 5McGraw-Hill/Irwin 5––2525

Key TermsKey TermsKey TermsKey Terms

Apportionment methods

Contingency funds

Delphi method

Direct costs

Function points

Interaction costs

Learning curves

Macro and micro estimating

Overhead costs

Padding estimates

Phase estimating

Ratio methods

Template method

Time and cost databases

Time-phased budgets