Upload
khangminh22
View
3
Download
0
Embed Size (px)
Citation preview
ATTOCK PETROLEUM LIMITED 7th Floor Attock House, Rawalpindi, Pakistan. Ph- 051-5127250-4
ATTOCK PETROLEUM LIMITED
TENDER DOCUMENTS FOR
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY
FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING
AUTHORITY, LAHORE.
TABLE OF CONTENTS
1.0 GENERAL CONDITIONS OF CONTRACT
Conditions of Contract Part-1 –Annexure – 1
Conditions of Contract Part-2 –Annexure – 2
2.0 BILL OF QUANTITIES
BOQ –Annexure – 3
3.0 APL’S SAFETY AND SECURITY REQUIREMENTS
APL’s Safety Requirements-Annexure – 4
APL’s Security Requirements-Annexure –5
4.0 SPECIFICATIONS
Specifications for Civil Works-Annexure – 6 (A)
Specifications for Mechanical Works-Annexure – 6 (B)
5.0 DRAWINGS
Drawings-Annexure – 7
Annexure-1
Page 1 of 7
CONDITIONS OF CONTRACT PART-1
General Conditions
Article 1.0: Security
1.1 All Contractors’ Manpower has to prove their identity by submitting National Identity
cards.
1.2 All contractors’ staff working must wear yellow I.D. Cards during working.
Article 2.0: Material and Equipment
2.1 Unless specified otherwise, all the material required for the job will be supplied by the
Contractor. The Contractor shall be allowed to proceed with the job only after material has
been inspected and approved by the Owner/authorized representative of the Owner. The
inspection of both the work and material shall progress till the completion of the job.
2.2 Deleted.
2.3 Diesel generator sets, cable and all accessories including fuel to be provided by the
Contractor, as and when required.
2.4 All tools/equipment required for the execution of the said job to be provided by the
Contractor.
2.5 All equipment/material, consumable or other required for the welding operation i.e.,
welding rods, helmets/visors, goggles, grinder wheels/machines etc. to be provided by the
Contractor. All protective apparel/gear/canopies required during/before or after the
welding operation also to be provided by the Contractor.
2.6 All equipment required for the testing of the executed job to be provided by the Contractor.
Article 3.0: Site Cleaning
3.1 It is the responsibility of the Contractor to clear away all rubbish and surplus materials
from the site at his own expenses on completion of the work and shall leave the site clean
and tidy. The debris shall be removed from site.
3.2 Any usable surplus items redundant from site which are the property of the APL shall be
delivered to the General Stores by the Contractor against a Credit Delivery Order duly
authorized by a representative of the APL. However, in case of material supplied by the
Annexure-1
Page 2 of 7
Contractor, the Contractor can take the surplus material out of APL site after thorough
inspection and approval by the Representative of the Owner.
Article 4.0: Guaranties and Warranties
4.1 A high standard of workmanship shall be maintained by the Contractor as per
Specifications.
4.2 All work shall be guaranteed for a period of one year after issuance of Provisional
Completion Certificate. Should any defect develop during this period, due to bad
workmanship or faulty material supplied by the Contractor, he shall rectify the same at his
own cost to the satisfaction of the Owner’s authorized representative.
Article 5.0: Errors and Omissions
5.1 The Contractor will be responsible for corrections of all errors and omissions related to
their work including resolution of all issues related to their work to the satisfaction of APL
at no additional cost for a period of one year starting from the date of issuance of
Provisional Completion Certificate. Previous approval by the owner shall not relieve
Contractor of the responsibility of rectifying any shortcomings or discrepancies.
Article 6.0: Insurance/Medical
6.1 The contractor shall be responsible for obtaining and keeping in force at his cost an
appropriate (contractors all risk/comprehensive insurance policy from EFU), in a manner
and to an extent and only from an Insurance Company to be approved in writing, by the
owner, valid during the entire period of execution, completion and maintenance of the
works. Contractor shall be able to invoke it when required.
6.2 The Contractor ALL RISK policy shall, inter alias, cover the following risks:
1. Third party risk.
2. Accident or injury to workman.
3. All loss or damage from whatever cause arising for which the contractor is
responsible under the contract.
6.3 In case the contractor fails to submit the insurance policies mentioned in Article 6.2, then
deduction @ 3.43% or as applicable under the law will be made from contractor’s bills.
Annexure-1
Page 3 of 7
6.4 In case of any injury / accident caused to any employee / worker during the course of
employment the Contractor shall immediately refer him to any recommended Hospital of
APL for necessary medical treatment for which charges shall be borne by the Contractor.
6.5 All employees hired by the Contractor for the execution of the works shall be provided all
medical treatment from recommended Hospital of APL at against the prescribed charges of
the Hospital to be paid by the Contractor on case-to-case basis.
Article 7.0: Contractor’s employment conditions
7.1 Contractor shall be independently and directly responsible for payment of dues and wages
to his employees and to settle terms and conditions of their service. He would also be
directly responsible for compliance with all laws, Rules and Regulations that may be
applicable to the employees hired by him for the due execution of this agreement.
7.2 Contractor shall be solely and exclusively responsible for payment of dues under the
Provincial Employees Social Security Ordinance 1965 and contribution payable under
Employees Old-Age Benefits act 1976 and any other law applicable to his establishment.
Article 8.0: Taxes
8.1 Owner will make tax deductions from payments made to the Contractor under this
Contract, as required under the law.
Article 9.0: Additional Services/Change Orders
9.1 Owner during the execution of the said project may call upon Contractor to render any
extra/additional services or change orders with regard to the said project. Payment and
time schedule will be on mutually agreed basis between the Contractor and the owner.
However, in case of any dispute the authorized representative of the Owner reserves the
rights to fix the rates.
Article 10.0: Indemnity
10.1 The Contractor shall indemnify and keep indemnified the owner and all its employees and
assignees against all losses and claims for injuries or damage to any person or any property
what-so-ever which may arise out of or in consequence of the awarded work and against
all claims, demands, proceedings, damages, costs, charge and expenses what-so-ever in
respect of or in relation thereto.
Annexure-1
Page 4 of 7
Article 11.0: Confidentiality
11.1 All data, drawings, analysis etc. provided by the owner or conducted by the Contractor on
behalf of the owner will be held confidential and would not be revealed to any outside
agency/party.
Article 12.0: Law to Govern
12.1 This contract shall be interpreted in accordance with the laws of Pakistan.
Article 13.0: Force Majeure
13.1 The term "Force majeure" means any cause beyond the control of the Contractor, which the
Contractor could not foresee and/or reasonably provide against and which prevents the
Contractor from wholly or partly performing any duties under the Contract. Force Majeure
includes, but is not limited to, any of the following:
13.1.1 War, revolution, insurrection or hostilities (whether declared or not).
13.1.2 Riot, civil commotion or civil uprising
(Other than among the Contractor's Employees);
13.1.3 Earthquake, flood, tempest, hurricane, lightning or other natural disasters (not
including rains of any proportion;
13.1.4 Any fire of major proportions, or explosion;
13.1.5 Epidemic;
13.2 If any event occurs constituting Force Majeure, the Contractor shall give written notice to
the owner as soon as possible describing the Force Majeure and its effect upon the
performance of this Contract, and shall continue to undertake and perform the duties set
forth in this contract as far as is reasonably practicable.
13.3 In the event of a Force Majeure, resulting in a suspension of work, this Contract shall be
extended by a period equal to that for which the Contractor was prevented from
performing.
13.4 If the Contractor's inability to perform by reason of the Force majeure lasts for more than
45 days after notice has been given to the Owner, either party may terminate this contract
Annexure-1
Page 5 of 7
and the Contractor shall be entitled to any sums which would be payable in case of
termination of this contract.
Article 14.0: Suspension of Work
14.1 The Owner may, at any time, by written order to the Contractor (Suspension of Work),
require the Contractor to stop all, or any part, of the work required by the contract for a
period of up to 21 days from the specified effective date.
14.2 Upon receipt of such an order, the Contractor shall immediately comply with its term, and
take all reasonable steps to minimize the incurring of costs allocable to the work covered by
the order.
14.3 Within the period of the Suspension of Work Order, the Owner shall either:
14.3.1 Cancel the Suspension of Work Order; or
14.3.2 Terminate the work covered by such Order as provided in the termination clause of
the contract.
14.3.3 If the Suspension of Work Order is cancelled or the Order expires, the Contractor
shall resume work. An equitable adjustment shall be made as necessary in the time
schedule, the budget, or a combination thereof, or any other provisions of the
contract that may be affected and the contract shall be amended accordingly, if the
Contractor asserts a claim for such adjustment within 30 days after the end of the
period of work suspension.
Article 15.0: Termination by the Owner for Default
15.1 The performance of work under the contract may be terminated by the Owner in whole, or
from time to time in part, in accordance with this clause, whenever the Contractor defaults
in performance of this contract and shall fail to cure such default within a period of 10 days
(or such longer period as the Owner may allow) after receipt from the Owner of a written
notice specifying the default.
15.2 Termination shall be effected by a Notice of Termination to the Contractor specifying that
termination is for the default of the Contractor, the extent to which performance of work
under the contract is terminated, and the date upon which such termination becomes
effective.
Annexure-1
Page 6 of 7
15.3 After receipt of a Notice of Termination and except as otherwise directed by the Owner, the
Contractor shall:
15.3.1 Stop work under the contract on the date and to the extent specified in the Notice of
Termination; and place no further orders, except as may be necessary for
completion of the portion of the work under the contract.
15.3.2 Terminate all orders and to the extent that they relate to the performance of work
terminated by the Notice of termination;
15.3.3 Assign to the Owner as it may direct, all of the rights, titles, and interests of the
Contractor under the orders so terminated, in which case the Owner shall have the
right to settle or pay any claims arising out of the termination of such orders;
15.3.4 With the approval or ratification of the Owner to the extent the Owner may require,
which approval or ratification shall be final and conclusive for all purposes of this
clause, settle all outstanding liabilities and all claims arising out of such termination
of orders and subcontracts, the cost of which would be reimbursable in whole or in
part in accordance with the provisions of this contract;
15.3.5 Transfer title to the Contracting Office and deliver as directed by the Owner, the
completed or partially completed drawings, information, and other property which
would be required to be furnished to the Owner under the contract except that this
requirement shall not apply to goods for which the Contractor has not been
reimbursed.
15.3.6 Complete performance of the part of the work which has not been terminated by
the Notice of Termination; and
15.3.7 Take such action as may be necessary for the protection of the property related to
this contract which is in the possession of the Contractor and to which the Owner
has title.
15.3.8 If the contractor fails to complete the job the owner reserves the right to carry out
the remaining jobs at the risk and cost of the contractor by engaging another
contractor.
15.3.9 If the contractor fails to start the work after the lapse of mobilization period or his
performance is slow, the Owner reserves the right to terminate the contract.
Annexure-1
Page 7 of 7
15.4 If the progress of the work is slow or the Contractor fails to complete his obligations under
this Contract then the Owner may terminate the Contract and will carry out the remaining
work through other sources at the risk and cost of Contractor.
Article 16.0 Subcontracts or Assignments
16.1 The Contractor shall not subcontract all or any part of the Contract without first obtaining
Owner’s approval in writing of the sub-contracting and the sub-contractor.
16.2 The Contractor guarantees that any or all sub-contractors to the Contractor for performance
of any part of the work under the Contract will comply fully with the terms of the Contract
applicable to such part of the work under the Contract.
Article 17.0: Inspections
17.1 The Contractor agrees to permit Owner/authorized representatives of the Owner to
inspect the activities, and work pertinent to this Contract.
Article 18.0: Amendments
18.1 Modification of the terms of this contract shall be made by an amendment signed by the
parties. Any amendments, including such amendments, which increase the Contract
amount or extend the completion date of the Contract, must be approved by the Owner.
Article 19.0: Dispute and Appeals
19.1 In the event of any dispute that the parties hereto are unable to resolve, "Inter parties" the
parties hereto agree to submit such dispute to arbitration under Pakistan's Arbitration Act
(X of) 1940 in Civil Courts of Rawalpindi.
Article 20.0: Delays on the part of Owner
No delay in the contract on the owner’s side will be admissible unless the contractor has
advised the owner about it in writing within two working days after occurrence.
Annexure-2
General Condition Part -2 Page 1 of 3
CONDITIONS OF CONTRACT - PART -2
Conditions of particular application
Article 1.0: Work Schedule
1.1 Work to be carried out according to specifications and instructions of Owner/authorized
representative of the Owner following the work schedule provided by the Contractor and
approved by the Owner.
Article 2.0: Liquidated Damages
2.1 The work shall be completed to the approval of the Owner/ authorized representative of
the Owner within 150 Calendar days (excluding 7 days of mobilization) of start failing
which the Contractor will be liable to Liquidated Damages @ 0.3% of the contract value per
day up to a maximum of 10% of contract value after final measurement. The liquidated
damages will be imposed for each day of delay in achieving the milestones stipulated in
work schedule and shall be deducted from running bills. This shall however, be refunded
whenever the progress is back on schedule.
Article 3.0: Payment Schedule
3.1 All payments shall be made on monthly basis after bills submitted by Contractor have been
verified by Owner/ authorized representative of the Owner, whose decision will be final
and binding. Payment will be made to the Contractor once a month up to a maximum of
90% (after deduction of 10% retention money) of estimated value of work done as certified
by the Owner. However, other deductions (advance, taxes, insurance etc.) will be made
from the bills as applicable under the contract.
3.2 The Contract price includes all charges such as labor, plants, tools, cartage and all taxes etc.
as may be levied by the Government/Semi-Government Authorities till completion of the
job.
3.3 Payment against secured advance will be made @ 75% of estimated cost of material as per
verification of owners authorized representative. No advance against cement is allowed.
3.4 No increase or decrease resulting through any change in the fiscal policies of the
Federal/Provincial Governments affecting the existing taxes or levies on such materials as
are to be incorporated in the works or by way of any additional/enhanced benefits to the
labor or any fluctuations in the foreign exchange rates or on any other account shall affect
the Contract price.
Annexure-2
General Condition Part -2 Page 2 of 3
3.5 Contract price can be varied up to a maximum of 10% on same unit rates as given in the
Scope of Work. However if variations are exceeding 10% of contract value or additional
work (non BOQ) whose rates are not covered in the contract has been included than the
contract will be amended after mutual agreement with the contractor.
Article 4.0: Authorized Representatives
4.1 For coordination / execution and other purposes to this Contract and the Project,
_______________________________________ Mr. will
act as the Contractors authorized representative. He will co-ordinate and will inform the
Owner regarding progress of the work
4.2 For implementation and other purposes of this Contract and the Project, Mr. Yahya Jan
will be authorized to act for & on behalf of the Owner.
Article 5.0: Retention money
5.1 10% of the Contract value will be retained from the running bills as retention money.
Retention money will not be deducted from advance payments; however, deductions from
all running bills will be made proportionately so as to retain 10% of the Contract value. The
owner will release retention money one year (i.e maintenance period) after issuance of
Final Completion Certificate of works.
Article 6.0: Earnest money
6.1 2% of bid amount deposited, as earnest money along with the bid will be released after
60% of completion of work as verified by engineering department.
Article 7.0: Advance payments
7.1 10% of the contract value will be paid to the contractor as advance against mobilization if
required by contractor after the contract has been signed and the contractor has furnished a
Bank Guarantee for the full amount of advance payment. The guarantee should be from a
scheduled bank acceptable to the owner and the conditions of the guarantee shall bind the
contractor to pay the owner in full or any part of the advance payment, which remains not,
paid by the contractor to the owner. Advance payment made to the contractor will be
adjusted proportionately from all running bills till full adjustment of the advance payment.
Annexure-2
General Condition Part -2 Page 3 of 3
Article 8.0: Transportation
8.1 Transportation of material to site is the responsibility of the contractor.
Article 9.0: Supply/Storage of material
9.1 Contractor will have to make his own arrangement for storage of material and equipment at
site during contract period.
9.2 Unless specified all material required for the execution of job is to be provided by the
contractor including consumables. However, material supplied by the contractor will only be
incorporated in permanent work after Owner’s representative has verified it.
Article 10.0: Progress Report
10.1 If required, monthly progress reports shall be prepared by the contractor and submitted to
the owner in accordance with the requirement of the contract.
Article 11.0:
11.1 Any deliberations held, correspondence exchanged, minutes recorded or any views
expressed for or any issue in any manner whatsoever prior to the signing of the Agreement
shall have no legal sanctity and will be construed as non-existent. The same partly or
wholly shall not be cited for any clarification or interpretation on any of the provisions
contained in the Agreement in aid thereof. The stipulations contained in the Agreement
mutually agreed and lawfully signed shall only be enforceable in its own tone and tenor
without any consideration to any eventuality outside the scope of agreement.
11.2 Any damages to property caused due to your executions shall be repaired at your risk and
cost.
11.3 Compaction tests shall be undertaken at your cost as and when desired by the company.
11.4 Work execution must be planned to ensure that movement of vehicles is least disturbed.
11.5 Payment shall be made on actual measurements.
Annexure-4
APL’s Safety Requirements Page 1 of 4
APL’S SAFETY REQUIREMENTS
The contractor is responsible for all employees working for him and all other persons calling on
him or doing business with his firm while working inside the premises of APL Site. The
contractor is responsible for explaining all safety instructions to the concerned staff and he is
also responsible for explaining and securing compliance with APL Site’s rules and practices by
any sub-contractor engaged by him for work inside APL Site.
It is imperative to eliminate a cause of accident by engineering revision or by safe guarding or
to limit exposure time to hazardous dust, mist, vapors or excessive noise to acceptable levels by
administrative procedures, use of personnel protective equipment (PPE) is mandatory.
The following requirements must be strictly adhered to:
1) Use of safety helmets, safety shoes, cotton gloves (wherever required) and overalls
approved by the owner are must for working inside the APL Site.
2) In case of work to be carried out at a height to 10 ft. or above, safety belts to be used.
3) Cranes, winches and chain blocks must not be used to lift persons.
4) For works above 8 ft., scaffolding should be used and use of ladders should be strictly
avoided, except where platforms are available or with the permission of safety
department.
5) For following specialized jobs, the required safety measures/equipment will be must to
use as mentioned below:
5.1 Welding and grinding jobs
a) Welding helmet
b) Face shield
c) Chrome leather welder’s gloves (welder only)
d) Aural Plugs
e) Flashback Arrestors
5.2 Rockwool/Glasswool Insulation
a) Peak helmet with chin straps
b) Safety goggles
c) Filter /dust/mist masks
Annexure-4
APL’s Safety Requirements Page 2 of 4
5.3 Crane operations/rigging jobs
a) Periodic crane testing to be carried out
b) Peak helmet with chin strap
c) Safety goggles
d) Area to be cordoned off
e) Contractor to provide detailed rigging plan for critical lifts along with
load charts.
6 Transport inside APL Site
a) All heavy vehicles operating in the APL Site and camp area must have a helper to
guide the driver while reversing the vehicle.
7 Penalty for violation of safety rules
If the contractor or any of his employee or sub-contractor found not complying with the
safety requirements of APL during the execution of the jobs, the firm will be liable to a
penalty as given below:
a) For contract up to Rs. 5 million, a penalty of Rs.10,000/- will be imposed if
the contractor fails to adhere by APL’s safety rules.
b) For contract above Rs. 5 million, a penalty ranging from Rs.10,000/- upto
Rs.100,000/- will be imposed if the contractor fails to adhere by APL’s safety
rules.
For any serious violation of safety rules, the Owner reserves the right to
terminate the contract without assigning any reason. In this case, outstanding
bills of the contractor will be forfeited or otherwise adjusted against the assessed
loss to the company.
Annexure-4
APL’s Safety Requirements Page 3 of 4
APL SAFETY RULES: ELECTRICAL CABLE & CONNECTION
Safety at work is of prime importance. Temporary job sites / project areas are most vulnerable
and extra precautions must be taken for making these places safe for working. It has been
observed that due care is not taken when temporary electrical connections are made. Following
instructions must be followed for eliminating hazards due to electrical cables:-
1. A qualified person from electrical section for suitability of its rating and type must
check all temporary cables. Megger test of all cables to be carried out.
2. Temporary cables must not be laid on the ground. It must either be supported on
proper supports such that it is at least 18 inches above ground throughout its length
(Wye type supports can be used for this) or it must be buried underground / placed
in proper sleeves to avoid any damage.
3. Road crossings must be done from under the culverts, through already laid
underground sleeves or through metallic pipe laid on the road properly fastened at
both ends of the road and covered with sand to make a smooth slope.
4. Where overhead crossing is done, at least 10 feet clearance shall be given on the
walkways and eighteen feet on the roads. All underground cables must be marked
with suitable signboard.
5. All main cables must have safety cut outs at both its ends. (MCCB can be used for
this). Electrical department shall confirm suitability of the circuit breaker / cutout in
writing on the back of the permit issued for the job. All circuit breakers / cut outs
shall be placed at easily accessible well-illuminated and prominent place.
6. Cable joints must be avoided in all temporary cables. However, where unavoidable
due to the length of the circuit, each joint shall be thoroughly checked by electrical
department and yellow PVC tape bands shall be used on both ends of the joint to
make it prominent. Electrical section shall note down the number of joints on the
back of the permit issued for the job. No one is allowed to open or repair the joint in
the absence of a qualified person from electrical section.
7. All electrical switchgears shall be adequately protected from rain and adverse
weather by using proper housings and shades. Safety department shall ensure this.
Annexure-4
APL’s Safety Requirements Page 4 of 4
8. All live wires, cable ends, connections etc. shall be properly covered to avoid
accidental touching by those working in the area.
9. All metallic housings, stands for switchgear and machines shall be properly earthed.
Safety department shall ensure this. Electrical section shall identify suitable
grounding point.
10. All underground cables when removed must be completely checked before it is
again used.
11. No electrical cable to be laid inside dyke wall of a live / operational tank.
12. All the electrical fittings to be of industrial type.
FIRE AND SAFETY CHECKLIST
1. Inspection of tools and equipment (Hand & Power Tools, Sling and Lifting Gears,
Scaffolding, Ladders, Sandblasting and Grid Blasting Equipment, Gas Cylinders,
Main Riding Baskets, Pressure Testing Equipment etc.) will be implemented by all
contractors on monthly basis.
2. Compliance of personal protective equipment should be done 100%.
3. Load Lifting Certificates of Cranes and Lifting Gears should be provided by the
contractors if asked.
4. Flame arrestors should be used on the any vehicle / equipment of Contractors.
Contractor drivers should obtain safety-driving permit from fire & safety
department.
5. If any unsafe act / conditions found during execution of job, Fire & Safety
department / project coordinator is authorized to stop the job and contractor will be
responsible for the implementation of recommended corrective measures.
6. APL management reserves the right to add / amend in safety regulations as and
when required.
7. Contractor to get his equipment (welding sets, grinders, gas cutters etc.) certified
from APL Fire & Safety Department on quarterly basis.
Annexure-5
APL’s SECURITY REQUIREMENTS Page 1 of 1
APL’s SECURITY REQUIREMENTS
1. In case of emergencies, the Contractor shall clear all the roads and in no case shall block the
Main entrance.
2. Contractors and their employees will have to display their yellow ID Cards.
3. Contractors’ employees will have to stay within the Project Area. Loitering inside the APL
premises shall not be allowed under any circumstances and the Contractors’ employees
shall be confined to immediate vicinity of work site.
4. All Contractors’ vehicles are allowed, provided the vehicle is searched and cleared by the
Security. The transport is generally allowed only for shifting material from outside the APL
premises to the work site.
5. All Contractors’ employees must possess the National Identity Cards, a photo-copy of
which shall be deposited to APL.
6. Contractors’ employees will not be allowed to stay inside the APL Premises over-night.
7. In case of breach of Security or Safety requirements of APL, the Company shall impose a
fine and/or the APL premises Entry Permit of the concerned employee shall be cancelled.
8. Tractor trolley will not be allowed to enter inside the APL Premises without Co-driver.
9. Security Passes are returnable.
10. For urination proper places are utilized.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 1 of 11
SPECIFICATIONS FOR CIVIL WORKS 1. GENERAL: a. Entire work shall be carried out within the specifications given hereunder and or
those shown on drawings.
b. The method of construction employed and the Workmanship shall be in accordance
with current recognized good Engineering practice and bonafide principles.
c. The work timings shall be in accordance with APL requirements.
d. Site plan may be seen in the office of the Manager (Engineering). The contractor is
deemed to have inspected and acquainted himself with site conditions and no claim
what-so-ever at this account will be entertained.
2. EXCAVATION AND EARTH WORK:
a. The site shall be cleared without extra charges of all rubbish spoil or over burden
etc. and made level as directed by the Engineer Incharge before buildings etc. are
set out.
b. The contractor shall set out the works and shell is responsible for true and perfect
setting out of the same and for the correctness of the positions, levels, dimensions
and alignment of all parts thereof.
c. Excavation should be carried out in accordance with excavation plans on the
drawing.
d. Excavated material unsuitable for use as fill and backfill shall be disposed off by the
contractor at locations approved by the Engineer within specified free haulage
limit.
e. Excavation for pits, cable trenches equipment foundations and other structure shall
be taken out to the levels and dimensions as the Engineer may direct.
f. Before starting the excavation, the contractor shall ensure the correct alignment of
the pipelines on the ground, depth and width of excavation of the trench, all in
accordance with the drawings and instruction of the Engineer.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 2 of 11
g. The excavation done in excess of mutual requirements, and dimensions as shown
on drawing and/or subsequently ordered shall be filled with P.C.C. (1:5:10) at the
Contractor's own expenses without extra cost.
h. The excavated material shall either be used on buildings for filling under floors and
around foundations or transported and disposed off as directed by Engineer
Incharge.
3. CONCRETE WORK:
a. Coarse Aggregate: Coarse aggregate shall consist of crushed stone, gravel or
approved crushed stone (Approved stone) inert material with similar characteristic
or combination of such material having clean ,hard, durable, uncoated particles free
from injuries amount of salt for all R.C.C./P.C.C.
b. Fine Aggregate: Approved course sand of grading (Approved) shall be used for all
R.C.C. and P.C.C. work as well as for plaster work.
c. Water: Water to be used in the work for mixing and curing of concrete and for
washing of aggregates shall be potable water and shall be free from other
impurities.
d. Mixing: Concrete mixing shall be carried out by power operated concrete mixing
machine. Hand mixing shall only be allowed where the total mix per day in any
particular job does not exceed 30 cft. Hand mixing for R.C.C. work shall not be
allowed.
e. Strength of Concrete: The minimum crushing strength of concrete (1:2:4) mix at the
age of (7) days and (28) days shall be 141 and 210 kg/sq.cm respectively. In case of
concrete mix (1:3:6) the strength at the age of (7) and (28) days shall be 70.30 and
105.45 kg/sq.cm respectively. Cube size will be 15 cm x 15 cm x 15 cm.
f. All cubes will be prepared and tested on contractor's own expenses from any
Government Laboratory for any work required to be tested by APL. And if results
show that strength of concrete is less than as specified, work will be rejected and
redone by the Contractor on his own risk and cost.
g. Adequate protection is provided and approval is obtained from the Engineer,
concrete shall not be placed when it is raining, during hot period, the temperature
of concrete shall be not rise above 32 degree centigrade.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 3 of 11
h. Concrete shall be conveyed and deposited as quickly as possible after mixing and
shall proceed within 40 minutes before the initial setting time start unless and
otherwise some retarding material shall be used as directed by the Engineer.
i. All work such as excavation, farm work, and reinforcement inserts ready for
concreting shall be subjected to the Engineer approval; concrete shall not be placed
until the Engineer has indicated that he is satisfied with the work.
j. Joint filler shall be a high-grade performed compressible, resistant water proof as
approved by the Engineer.
4. REINFORCEMENT:
a. All reinforcement will be prepared, bended, binded and placed in position using 18
BG binding wire and shall be checked and approved by the Engineer Incharge
before pouring of concrete is allowed.
b. The steel chairs should be provided wherever required and spacer blocks should be
of the same class concrete as that of in the slab etc.
5. BRICK/STONE WORK
a. The sand for cement mortar shall be fine graded (Approved).
b. For mortar 1: 4 ratio, the average compressive strength of their Nos. 50 mm cubes
shall not be less then 126kg/cm2 (1800) at 28 days.
c. All bricks / Blocks, except otherwise specified, shall be of 1st class quality made
from good material, free from saline deposits and shall be free from flaws, cracks,
chips, stones and modules of lime.
d. The average compressive strength of bricks / block in any case shouldn’t less than
1450 psi / 1200 psi respectively and also rendering good ringing sound in case of
bricks.
e. All bricks to be submerged for 2 to 4 hours and when soaked for 24 hours shall
absorb 15 to 20 % of water of its weight.
f. Masonry work in foundations shall be flush pointed as the work proceeds in same
mortar without extra cost.
g. Building paper in double layer shall be provided on plastered surface finished in
(1:4) cement mortar under the bearing of lintels, beams, and roof slabs.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 4 of 11
h. External faces of super structure, where plastering is not shown in drawing shall be
pointed struck with (1:2) cement mortar.
i. All stones to be soaked in water for two hours, if so directed, before being lay in
cement mortar. All joints to be well flushed up at every course. The walls shall be
carried out regularly not leaving any apart more than 1 m lower than another
unless special circumstances render this impracticable. Any wall left at different
levels to be racked back. Courses to be properly leveled, quoins, jambs and other
angle plumbed as the work proceed.
6. CURING:
The concrete shall be kept continuously wet by the application of water for a minimum
period of seven days after the concrete has been placed. Cotton mats, carpets or sand
blankets, may be used as a curing medium to retain the moisture.
7. SCAFFOLDING/FORM WORK:
a. All formwork shall be of steel unless otherwise directed by the Engineer.
b. All form work and shuttering shall be approved by the Engineer In charge
before binding and placing the reinforcement.
c. The design of formwork and its pertinent calculation should be submitted to
the authorized Engineer of APL.
d. Contractor shall provide safe scaffolding of adequate strength for use of
workmen at all levels and heights at his own expenses; damage to masonry
form scaffolding or from any other cause shall be repaired by the contractor
at his own expenses.
8. PLASTERING:
a. Except as may be otherwise shown or specified, all plaster shall be cement
plaster. Plaster shall include partition column, plastered jambs and other
returns, reveals and back of recesses and alcones jambs and head of windows
and doors, unless otherwise specified or shown on drawings.
b. Whenever required, the Puddlo should be used according to manufacturer
prescription and as directed by the Engineer.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 5 of 11
9. FLOORING:
The surface of concrete floors shall be finished fair. The floors shall be laid in alternate
layers with granular material laid under sand be properly compacted or as directed by
Engineer.
TERRAZO FINISH:
The thickness of terrazo finish shall be 10 mm. It shall consist of 1 part of cement and
two parts of marble chips passing through 3 mm and retained on 2 mm screen. The color
of pigment where used shall be approved by the Engineer. The coloring pigments will
not, however be added to the gray cement. Surface of the terrazo shall be rubbed with
carborundum blocks, after three days of lying. The oxalic acid powder shall be used on
the surface with pieces of felt and a few drops of water and a glossy finish obtained by
applying an approved floor polish.
MOSAIC TILES:
1’ * 1’ tiles in white or colored cement or specify on drawing or as directed by the
Engineer shall be used. All joints shall be approximately 1.5 mm wide parallel to walls
and a right angles o each other.
Glazed tiles should be used on the wall while mat tiles on the floor. All the corner of the
tiles are properly chamfered. There should be proper slope as per drawing.
10. TERMITE CONTROL TREATMENT:
An emulsible concentrate insecticide shall be used for dilution with water. Specially
formula to prevent by termites. Fuel oil will not be permitted as a diluent. Provide a
working solution of one of the following chemicals and concentrations.
1) Aldrin chemical toxicant, emulsifiable to 0.5% with clean water.
2) “Dieldrin” chlorinated hydrocarbon, emulsiafiable to 0.5% with clean water.
11. WOOD WORK: a. All timber to be used shall be seasoned and preserved and first class deodar wood
only, unless otherwise specified on drawings. Hard wood where specified shall be
first class shisham wood. All timber shall be subject to approval of Engineer
Incharge and priming cost will only be applied after the manufactured items have
been checked and passed.
b. All flush doors will be prepared under the instructions of Engineer Incharge or
flush doors manufactured by the reputed firms can be provided after approval of
the Engineer Incharge.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 6 of 11
c. A sample of board of all types of fittings and fixtures of doors and windows shall
be provided by contractor free of cost for approval of Engineer Incharge.
d. Nails shall be cut brads, cut clasp. Oval, square or round wire of approved
manufacture and length as required.
12. STEEL WORK;
a. Railing and grill to be provided shall be steel profile, pattern and design shown on
drawing.
b. Samples of iron mongary for each contract shall be submitted by the contractor to
the Engineer-in-Charge for approval before ordering.
c. Galvanizing shall be a through even coat of zinc free from strains, bare spots and
defects, at the rate of 610 gm of zinc per sqm of materials measured on the sides.
13. ALUMINUM WORK:
a. Aluminum shall be Pak cable unless otherwise as directed by the Engineer.
b. Doors and windows to be provided shall be of profile, pattern and design shown on
drawings and shop drawings manufacture by reputable manufacturer approved by
the Engineer.
c. The structural shape of the aluminum members shall be of uniform quality, color
and temperature, clean, round and free from the injurious defects.
d. The manufacture shall furnish his standard written guarantee against leakage of
rain, accessing infiltration of dust and air and all defects in materials and
workmanship covering all work.
e. The accessories shall be tape or ribbon of polymerized butyl or mixture of butyl and
polyisolbytlene compand with inert fillers and pigments, Solvent based 95% solid.
14. PAINTING/GLAZING: a. The term ‘paint” as used includes Synthetic Enamel Paint, Emulsion and Distemper
will be used only from Dulux or Robbialac, as directed by Engineer Incharge.
b. 5 mm. glass sheets shall be provided to all glazing area except otherwise specified
on drawings or as instructed by the Engineer Incharge.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 7 of 11
d. All putty will be prepared in synthetic varnish. 15. INTERNAL SANITATION: All sanitary work with connected accessories required to complete the work shall be of best
quality Pak Made and shall be fitted after approval of Engineer Incharge except otherwise
mentioned in the Contract/Agreement.
Sample to be prepared and submitted to APL for approval.
16. INTERNAL ELECTRIFICATION AND WATER SUPPLY:
• All work shall be carried out as per specifications and drawings and as instructed
by the Engineer Incharge. All material shall be approved before incorporation in
works
• All electrical wires to be of genuine Pakistan Cables or Newage Cables or Poineer
• All Telephone cable (0.6mm2, 5-pair) to be of genuine Pakistan cables.
• All Telephone cable (0.6mm2, 5-pair) to be of genuine Pakistan cables.
• All switches, switch/sockets, Tel sockets, fan dimmer etc. to be of genuine
• All internal buildings PVC pipes to be either of Galco or Shavyl make.
• All under forecourt & canopy schedule 40 uPVC conduits of AGM / Pak-Arab/
Dadex make
• Clipsal / SWITCH KID /ALPINE SERIES make must be in white or ivory color.
• All switch/sockets & Tel sockets will be placed in corners.
• All masonry work including cutting of walls etc. and replastering / retouching
etc. back to its original state to be done by the contractor.
• All ceiling fans to be adjusted at a height 9 feet from ground.
• Extension pipe etc. for adjustment to be supplied by contractor.
17. ROAD AND PAVING WORKS: FILL MATERIAL;
Material for embankment shall consist of suitable material excavated from barrow, road
way excavation or structural excavation. Contractor shall use AASHTO class A-1, A-2, A-3,
A-4, or other material approved by Engineer.
CBR of the material should not be less than 5% in any case.
GRANULAR SUBBASE: Granular sub base material shall consist of natural or processed aggregates such as gravel,
sand or stone fragments and shall be clean from dirt, organic matter. The max passing size
should not be greater than 2-1/2”. The material shall have a CBR value of at least 30%.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 8 of 11
The material passing through sieve # 40, when prepared in accordance with AASHTO T
146-49 having liquid limit 25% max & plastic index 6% max.
BASE COURSE: Material for base course shall consist of hard durable gravel, rock or fragments. It shall be
free and clean from organic matters lumps of clay and deleterious substances.
The material shall be well graded such that the coefficient of uniformity D60/D10 shall be
greater than four.
The coarse aggregate shall have a percentage of wear by Loss Angeles Abrasion test
(AASHTO T-96) of not more than 40%
The material shall have a loss of less than 12% when subjected to 5 cycles of the Sodium
Soundness test according to AASHTO T_104.
The material passing the 19mm sieve shall have a CBR value of a minimum 80% tested
according to AASHTO t-193.
Laminated material shall no be allowed.
EXECUTION: The base course consist of crusher run stones which shall be well compacted until there is
no movement of the stones under the roller.
The surface of the top course shall be checked for compliance with grade and profile and
any irregularities made good by the addition of new material which shall be added in before
the layer of material is fully compacted. It is advisable that rolling the top layer, the laying of
material shall be to the right grade and level allowing for settlement due to rolling. . If the
density is less than 100 percent of maximum density as determined by AASHTO T 10, the
contractor shall perform additional rolling may be necessary to obtain that density.
WATER BOND MACADAM: AGGREGATE: Coarse aggregate and screening shall consist of crushed stone. Coarse aggregate shall have a
percentage of wear by the LOS ANGELESS TEST of not mare hen 50%. Screening shall be of
suitable binding quality. The screening shall be of following gradation.
Sieve designation Percentage passing by Wt
Passing 3/in.Sieve 100 Passing No.4 sieve 85-100 Passing No 10-30
Water bound macadam work shall not be constructed during freezing weather or on wet or
frozen sub-grade or sub base course. The base course shall be constructed in complete
layers of not less than 3” or more than 41/2 compacted thicknesses or as directed by the
Engineer. Coarse aggregate shall not be spread more than 15,000 sq.ft.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 9 of 11
After proper compaction the screening shall be spread in thin layers at a uniform and slow
rate to insure filling all voids, immediately after the voids of a layer have been filled with
screening, the macadam shall be sprinkled with water, the sprinkler being followed by the
roller. The density tests shall be performed in accordance with AASHTO TT 14 modified to
include only material passing a ¾” inches sieve. If the density is less than 100 percent of
maximum density as determined by AASHTO T 10, the contractor shall perform additional
rolling may be necessary to obtain that density.
BITUMINOUS PRIME COAT: The bituminous materials shall be of the type and grade call for in the bid schedule. The
material used for prime coats should have high penetrating qualities. The cutback MC-0
grade is best suited for priming very dense flexible base and rate of application usually
varies from 18 to 32 lbs per 100 sft. A quantity of 20lbs/100 sft is usually recommended.
The ideal rate of application of a primer is the maximum that will, under favorable weather
conditions, be completely absorbed by the base material within 24 hrs from the imo of
application.
The application is prohibited when the weather is foggy or rainy, or when the temperature
is below 15 degree centigrade and rising above 60 centigrade unless otherwise directed by
the Engineer.
Bituminous materials shall be applied by means of a distributor at the rate or rate directed
by the engineer, which will usually be from 12 to 18 lbs per 100 sft and at a temperature
within the range for the type and grade 44 of bituminous and the type of the distributors.
BITUMINOUS TACK COAT: Bituminous material shall be of type and grade called for in the bid schedule and shall
conform to the requirements. When more than grade is shown in the bid schedule the
grade shall be that directed by the Engineer, However materials commonly used for tack
coats include the rapid curing liquid asphalts, RC2, RC3, RC3, emulsified asphalt of quick
breaking type bituminous of 80/100, 20/150, or 150/200 penetration or lighter grades.
BITUMINOUS PLANT MIX COURSE; The Aggregate shall consist of coarse aggregate of crushed stone or stone, composed of
hard durable pebbles or fragments and fine aggregates of crushed gravel or stone or sand
etc. The aggregate shall be from vegetation’s, or clay or, particles within soften appreciably.
The coarse aggregate shall have the percentage of wear by Los Angeles abrasion test of not
more than 50.
The percentage of bituminous binder by weight of dry aggregate will usually be in the
range of 3-7 percent depending on the type of material. The exact percentage to be used
shall be fixed by Engineer on the basis of laboratory tests on the job mix.
Plant mix base course material can be laud in virtually all weather conditions except where
there is standing water or very heavy rain Plant mix base course shall only be constructed
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 10 of 11
when the surface is dry, when the atmospheric temperature in the shade is above 40 F and
rising or above 50 f.
The placing and compacting of bituminous materials shall progress in section not more
than 1 mile in length. The bituminous mixture shall be spread, shaped and finishing
with a mechanical paper approved by the Engineer.
Thickness and weight requirements including test measurement and corrective measures shall be in accordance with following.
1) Thickness: Not more than 3/8 of the specified thickness 2) Weight: No more than 10 percent if specified on a weight per unit area basis. All edges shall be trimmed by the contractor to neat lines in accordance with the plans.
BITUMINOUS SURFACE TREATMENTS
Surface Treatment Aggregate
Bituminous Material
Type Application Size # Qty. (Kg./Sq.M) Qty. (Liters/Sq.M) Type
Single
Single
2
12.5
1.19 (a)
1.63 (b)
Double
First
1 24.0
1.90 (a)
2.14 (b)
Second
2 12.5
1.19 (a)
1.63 (b)
Tripple
First
1
24.0
1.90 (a)
2.14 (b)
Second
2
12.5
1.19 (a)
1.63 (b)
Third
3
6.5
0.68
(c)
Seal coat with Aggregate
4
4
0.5
(c)
US standard sieve Percent passing by weight Size No. 1 Sieve No. 2 Sieve No. 3 Sieve No. 4 No. 4 (4.75 mm) 0-5 0-15 10-30 85-100 No. 8 (22.38 mm) 0 0-5 0-10 10-40 No. 16 (1.18 mm) - 0 0-5 0-10 No. 200 (0.075 mm) - - 0 0
(i) Bituminous material types are (a) asphalt cement, (b) cut-back or emulsified and (c) asphalt cement, cutback and emulsified.
Annexure-6A
SPECIFICATIONS FOR CIVIL WORKS Page 11 of 11
(ii) Quantities of bituminous material may be varied by the Engineer by + 15% depending on site conditions.
(iii) Prime coat shall be applied prior to the surface treatment for the newly constructed payment at the rate as specified by the Engineer.
MATERIAL REQUIREMENTS
Mineral Aggregate
The Aggregate shall consist of coarse aggregates, fine aggregates and filler material, if required
and shall be clean based, tough, durable and sound particles of uniform quality and from
decomposed material, vegetable matter shall clay, lumps and other delirious substances.
The filler shall consist of finely divided mineral matter such as rock dusts, hydrated lime,
hydraulic cement or other suitable mineral matter free from lumps, balls or other deleterious
material and shall confirm to the following gradation: -
US Standard Sieve Percent Passing by Weight
No. 30 (0.600 mm) 100 No. 50 (0.300 mm) 95-100
No. 200 (0.075 mm) 75-100 The coarse and fine aggregates shall meet the following requirements:-
(a) The percent of war by the Los Angles Abrasion test (AASHTO T 96) shall not be more than thirty (30).
(b) The loss when subjected to five cycles of the Sodium Sulphate Soundness test (AASHTO) 104) shall be less than twelve (12).
(c) The Sand Equivalent (AASHTO 176) determined after all processing except for addition of asphalt cement shall not be less than 45.
Annexure-6B
SPECIFICATIONS FOR MECHANICAL WORKS Page 1 of 2
SPECIFICATIONS FOR MECHANICAL WORKS
1. All material required for welding e.g. electrodes, grinders, cutting disks welding sets
and other consumables to be arranged by the Contractor.
2. Red oxide primer and enamel paint will be supplied and applied by the Contractor. It
includes one coat of red oxide primer and two coats of enamel paint (film thickness to be
in accordance with manufacturer’s recommendation) on pipe supports and pipelines.
Colors will be approved by APL and paint will be of ICI make only.
3. Pressure testing of all pipelines to be done by the Contractor at 250 psi or as otherwise
specified. Contractor will have to arrange for blind spades and hydraulic pump. Water
will be supplied by APL free of cost for pressure testing.
4. All pipelines will be flushed by water before pressure testing, by the Contractor
5. All material supplied by the Contractor will be approved by APL before installation.
6. All welding will be done at specified welding yard. Unless otherwise specified
Contractor will have to fabricate and weld pipelines and will have to transport them to
the site within a radius of 1.5 KM approx.
7. Steam tracing of pipelines to be done by the Contractor with special expansion loops
and bends as per instructions.
8. Insulation of pipes to be done by the Contractor with the help of rock wool covered with
chicken wire on both sides (80 Kg/m3 density and 0.039 Btu/hr oC thermal conductivity)
and GI sheets 24 SWG. All material required for insulation e.g rock wool, G.I Sheet,
bolts, drill machine etc. will be provided by the Contractor. Steam traced pipeline will be
wrapped with Aluminum foil first and then insulated. Thickness of rock wool to be 2”
for pipelines up to 2’’ diameter, 3” thick for pipelines diameter 3” to 6” and 4” thick for
pipelines diameters equal to and more than 8”
9. The Contractor shall carry out all the jobs according to good engineering practices.
Installation of pipelines will be done in such a way that they are aesthetically good e.g.
level and alignment of pipelines and supports to be maintained properly. Lying of
pipelines should be done in such a way that maximum utilization of supports is
ensured.
Annexure-6B
SPECIFICATIONS FOR MECHANICAL WORKS Page 2 of 2
10. APL will provide isometric drawings (not to scale) to the Contractors for the purpose of
route and location but construction drawings will not be provided by APL.
11. Optimum utilization of material provided by APL to be done by the Contractor e.g.
using pipe and cutting of gaskets, using of bolts and nuts etc. APL can impose penalty if
it feels that material provided to the Contractor is not being used properly.
12. Contractor should be energy conscious especially in case of electricity and water. These
resources should not be wasted.
13. Flame arrestor to be provided to the gas cylinders and vehicles of the Contractors.
14. All the welding shall be carried out in accordance with relevant API/ASME/AWS
codes. The Contractor will have to get the welding procedures approved by APL prior to
start of work. 10% or more of the weld joints will be subjected to radiography on APL’s
cost, however, in case of radiography failure, the cost of redoing radiography will be borne
by the Contractor through Owner’s appointed radiography (NDT) company.
15. Epoxy painting will be done in the following way. (Paint should be of ICI Make): -
a) Sand blasting of the surface as per Para 17 & 18.
b) Two coats of epoxy primer paint, thickness of each coat to be in accordance with
manufacturer’s recommendations.
c) Two coats of final epoxy paint, thickness of each coat is to be in accordance with
manufacturer’s recommendation.
16. Unless otherwise specified all pipes, fittings, valves, gaskets sheets and material for pipe
supports to be provided by APL. Contractor will have to cut gaskets at his own
arrangement.
1 OF 14
1
Demolition & Removing
Dismantling of existing structure including RCC beam, sabs, brick work wall etc.; including disposal of
dismantled of Civil structure material from site location to suitable location as per APL Engineer instruction.
Removal of Tuff Tile :
Carefully removal of tuff tile with 2'' sand cushion and removal of tuff tile and debris in area as directed by
Engineer Incharge.
Cutting and Levelling:
Cutting the earth fill in all kinds of soil / rock, dry or wet, hard or soft, including site clearing and leveling of site,
dressing, watering and compaction, also including dewatering, if required to achieve require level and disposal
of surplus material outside boundaries or as directed by Engineer Incharge. Complete in all respect as per
drawings, specifications and direction of Engineer Incharge.
Water (deep well bore) - Optional
Construction of deep well water 6”dia bore up to the depth of 300 ft including supply and installation of RCC
cover & double stage 3-phase, 2hp Submersible/centrifugal pumps (as per site requirement and as directed by
Area Engineer In charge) with power connection & 1” dia delivery pipes to the Under ground water tank etc.,
complete in all respect.
Water proof electrical cable 7/36 for submersible main supply from main DB including breaker.
Steel rope for motor holding 1/2”dia.
Pump discharge pipe 1” diameter PPRC best quality pipe up to underground water tank.
Aabshar company best quality casing 6” diameter & 300' deep with all necessary fittings.
Complete labor charges for upto 150 ft deep bore.
Earthing
Earth Pit with Rod type Electrode:
The electrode shall be of 600 mm long solid copper rod and 14 mm dia used, stranded copper bare conductor
2x16 sqmm in 38mm dia pvc pipe with a cc chamber at Hard standing level. 180 mm bore hole and minimum
30 ft depth below ground level or moisture content whichever comes earlier . Job should be completed as per
details provided in drawing # 01 & specification complete in all respect or as directed by Engineer Incharge.
1.3 Cft 30,659
Fixed
Cost1
1.5
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
Preliminary works
1.4
S.NO.
1.1 Cft. 60,000
Unit
Nos.
Components Quantity
5
Rate Per Unit Cost
Sub-Total Serial No. 1
1.2 Sft 16,138
2 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
2 Surfacing
Concrete paving - Optional
Constructing hard standing in 1:2:4 concrete. The concrete should be poured in 8’ x 8’ panel 9” RCC 1:2:4 ratio
with Steel of Dia 3/8" double mesh both ways at a distance of 8" C/C, complete in all respect as advised by
Engineer
Job should be completed as per details provided in drawing # 03 & standards and as direction of Engineer
Incharge.
Tuff Pavers (60mm):
Approved filling material brought from outside 9" thick stone soling layer will be laid in two layers stone metal
well compacted with 10 ton road roller to achieve 98% Aashto standard.
Providing and laying pre cast concrete pavers of "Concrete Concept / Tough Pavers / Banu Mukhtar make and
city type of size 200 mm x 100 mm x 60 mm thick laid in herring rectangle pattern and should have minimum
compressive strength of 42 N/mm2 (6000psi), to be laid over 2" thick sand & 3" thick P.C.C 1:4:8 layiing.
Pavers to be laid in driveway area with voids to be filled with "sand" properly.
This item will be complete as per drawing # 02 & standards and as direction of Engineer Incharge,
Fixing of Existing Tuff Pavers (60mm):
Fixing of existing tuff tile in approved pattern and filling the joints with sand inlcuding cost of 2'' sand cushion.
Complete in all respect, and as per direction of Engineer Incharge.
Providing and Laying structural Concrete of specified Mix 1:2:4 with Minimum 3000 Lbs. PSI work Cube Crushing strength at 28 days using crushed stone 3/4" and down
gauge for Reinforcement Cement Concrete in Foundation including cost of all material, form work and its removal, labor and equipment, compacting, vibrating, curing etc.
complete but excluding cost reinforcement as per drawing and specification and / or as directed by the engineer incharge.
100
Sq. Ft.
Excavation in all type of Soils from existing Ground level as per dimension given in applicable drawing for foundation , drain including cost of dressing, shoring, back filling in
approved manner where require, and disposal of excavated Soil outside Cantonment or Municipal limit as per applicable drawing and specification and direction of Engineer
Incharge.
2.1
Providing and Laying Plain Cement Concrete of specified mixed for Base to foundation , steps, walls footing and under floor etc. with Stone Ballast 2" Gauge including cost of
all material, lab our and equipment, compacting, curing, complete as per drawing and specification and/or as directed by the Engineer Incharge. 1:4:8 for base concrete 3" thick.
2.2
RCC Base slab 6" thick & R.C.C wall 6" thick with RCC precast slab for cover to drain 2" thick2.4
Sq. Ft.
18,919
Surface drain with steel grating:
Supplying, Fabricating, placing in position including tying of Mild Steel Plain round bars reinforcement at any level and elevation with Minimum yield stress 36000 Lbs. PSI
including all cost incurred for using 20 SWG binding wire, steel / precast concrete chairs and spacers to drawing specification and / or directed by the Engineer Incharge (
Sq. Ft. 200 2.3
3 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Surface Drain with Steel grating Rft 398
Canopy drain with 8" dia. uPVC Pipe
Providing of canopy Drain line includes supply and laying 8" pipe uPVC schedule 40 (Pak-Arab, Dadex, AGM,
Pak-Saudi) for including jointing of collars with the adhesive solution and & covering pcc 1:3:6 by 15"x15" all
around pipe. Providing connection to canopy island in uniform slope to Civic Agencies main sewerage
complete as per drawings and as directed by Engineer Incharge.
Pylon Foundation:
This will include excavation, construction of RCC 1:2:4 foundation, backfilling, grouting of anchor J-bolts 24
Nos of 1'' dia with double nuts & washers etc. as per drawing # 05 and instructions of Engineer Inchrge,
complete in all respects.
In/Out Foundation:
This will include excavation, construction of RCC 1:2:4 foundation, backfilling, grouting of anchor J-bolts of 1/2''
dia with double nuts & washers etc. as per drawing # 06 and instructions of Engineer, complete in all respects.
Dispenser/pump islands
a Island (12' x 3'-0") Nos. 6
Landscaping Works:
This work shall include Landscaping and External Development as per drawings and instructions of the
Engineer. This item includes all costs associated with landscaping, additional backfill, and plants, also includes
providing and laying sand, fertilizer, manure, sweat earth and planting Decca grass and green plants. The
works shall be finished in a workman like manner according to accepted horticultural practices. The kinds,
sizes and quantities of plants to be furnished and planted and the locations at which they are to be planted shall
be as called for on the Drawing or as designated by the Engineer
2.5
Providing and Laying P.C.C. of specified Mix 1:2:4 with Minimum 3000 Lbs. PSI work Cube Crushing strength at 28 days using crushed stone 3/4" and down gauge for R.C.C.
Pipe connecting surface drain channel including cost of all material, form work and its removal, labor and equipment, compacting, vibrating, curing etc. complete as per
drawing # 04 and specification and / or as directed by the Engineer Incharge.
1,200
2.6
2.7 2
1
2.9
2.8
Sq. Ft.
Nos.
Each
220
Constructing pump islands in cement concrete as per drawing in oval shape with the following details Excavation and providing stone soling and casting situ under dispenser CC
sump with 1:2:4 concrete. Laying grey tile (National Tile NT-711) topping & completed as per drawing # 07 & direction of Engineer’s incharge.
Rft.
Providing and laying 3/4" thick water proof cement plaster using pudlo at the ratio of 5lbs per beg of cement to wall floor and slab I/c curing smooth finished to the plumb kine
level etc. complete
Providing & Laying 8" dia RCC Pipe and Collar of approved make including excavation in all types Soil/to required Gradients cutting, fixing and jointing with asphalt
composition and segment motor (1:1) and testing with water to a head of 50 ft. above the top of the highest pipe, Provision of steel grating complete as per specification and
instruction of the Engineer including cost of Providing & Laying 21"x12"x 6" in bed in 1:3:6 below at the joints.
4 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Boundary wall (6'-6" height)
Construction of brick wall in accordance with the drawings and relative sections of the specifications, including
CC 1:4:8 foundation pad, 9” thick CC 1:3:6 in situ wall upto plinth level, and providing RCC footings & columns
at interval shown on the drawing # 08 etc. The job also includes plastering/painting works as per drawing # 15
& Standard & direction of Engineer Incharge.
Kerb wall (Precast)
Supply and installation of Precast Kerb stones 12''x18''x6'' (Tuff Pavers, Tuff Tiles, Bannu Mukhtar or approved
equivalent) at specified locations complete in all respect as drawing and specifications.
3
Canopy Foundation
This will include excavation of canopy foundation from NSL minimum 6 ft depth & construction of R.C.C (1 : 2 :
4) foundation, grouting of anchor J-bolts 24 Nos of 1.25'' dia with double nuts & washers etc., including the cost
of all required Re-inforcement as per APL's approved drawing # 09 and design complete in all respect.
4
Flexible UPP Pipe
Supply & Laying Of UPP (Uk/Italy) Pipe, Eco-smart underground flexible pipe for Gasoline, Single wall product
pipe 50mm. Material: High Density polyethylene (HDPE)
4.2UPVC Pipe: Providing and laying uPVC pipe 4" dia from product tank to pump island as shown on layout
drawing # 10 and As per Area Engineer instruction.Rft 550
Down fitting (including fill points, dip cap,)
Providing/ installing & testing pipeline, fittings and 4" dia MS pipe for Decanting of Product, 2" dia MS Pipe for
Air Vent System of Under Ground fuel storage tanks with all accessories (Make of IIL Medium) & 4 nos tanks
siphon with each other, submersible pump riser & fitting also. Complete in all respect as per APL approved
drawing # 11. Standards and Specification and as directed by the Engineer Incharge
4.4 Scully Coupling with dust cap: Made of best quality of Aluminum material Nos 6
4.5 Vent cap: Made of best quality of Aluminum material Nos 6
4.6
Guard Rail: Providing, painting and fixing 4” dia. MS pipe Schedule 40 (make IIL M or equivalent) as shown
on drawing # 12, complete in all respects. Complete as per layout & specifications or instruction of the Engineer
Incharge.
Rft 100
550
Set
Rft.
Rft
Canopy
Fuel system
170
2.10 416
4.1
3.1 6
64.3
Nos.
Sub-Total Serial No. 3
Sub-Total Serial No. 2
Rft.2.11
5 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
4.7 Brass Coupling: Product Pipe Brass Coupling (Local) high grade for coupling of Upp pipes 50mm dia Nos 16
4.8Trench for suction pipe line Excavating trench for fuel pipeline including backfilling, as per direction of the
Engineer Incharge.Rft 525
Backfilling the tank pit with riverbed sand around the pit and compacted sand inside the tank pit.
Providing and laying 8" thick RCC top slab over 4’’ thick CC 1:4:8 over 9" compacted stone and over
compacted sand fill complete as per drawing # 13 and specifications.
Providing & Laying grey tile (National Tile NT-711) on tank chamber 3.5 ft all around covered with tile
a Tanks - 5000 IG x 1 (As per Drawing # 13) Nos. 1
b Tanks - 5000 IG x 2 (As per Drawing # 13a) Nos. 1
c Tanks - 10,000 IG x 1 (As per Drawing # 13) Nos. 2
Manhole Cover:
Providing, making and fixing MS Sheet manhole cover with iron frame and angle of approved weight for under
ground tanks complete as per specifications, drawing and approval of the Engineer Incharge. Drawing #13
5
Excavation for foundation in normal/hard clayey/marshy soil including back filling between the trenches plinth and depression including leveling, breaking clods, watering,
compacting in layers not exceeding 6" in depth. Foundation to be brought from virgin soil.
Constructing the tank enclosure including RCC walls and base around the pit as per drawings.
4.9
Building
Dewatering of sub soil water if required.
Offices, Tuck Shop & Prayer Place Building
Construction of the Building in accordance with the drawings and specifications provided for the project. This will include:
Storage tanks
Providing 12” thick sand cushion before installing the fuel tanks.
Lowering and placing the tank in correct position by crane
4.10 Nos. 6
Construction of R.C.C Pit & Installation of U/G Tank
Sub-Total Serial No. 4
Providing 4” dia PVC perforated (Dadex or equivalent) pipe as a sniffer tube 1 in number in each tank pit complete with chamber &
steel cover
Providing filter sump for Diesel tank only made of CC1:2:4 wall & base with MS cover
Excavation in normal earth/hard/rocky/marshy clayey soil.
6 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Providing and laying 2" thick DPC (Damp proof course) under walls in CC 1:2:4 by volume mixed with water proofing compound Conplast-100 or equivalent @ 1 kg per bag of
cement including formwork leveling, making edges and curing etc. Applying 2 coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat, over one coat of
primer and one layer of 500 gauge polythene sheet (weighing 2.5 lbs/100 s.ft.) with at least 9" overlap, complete in all respects. (as required)
Providing and laying 6" thick stone/brick soling over earth filling laid on edge, hammer pressed with 1:6 Cement grout to fill voids in soling, including leveling, consolidation curing
etc. complete in all respects.
Providing and laying 4 1/2" thick cement concrete 1:3:6 bed flooring using approved aggregates complete.
Providing and laying (a) cold-worked deformed bars complying with BS 4461 or hot rolled deformed bars with min. yield stress of 60,000 psi or (b) mild steel as per B.S. 4449 with
min. yield stress of 40,000 psi, including bending, binding, wastage etc. and placing in position in RCC works on pre-cast cement concrete spacers or steel chairs and tying with
18 gauge wire etc. complete in all respects.
Providing and fixing all sanitary fittings & fixtures which shall be of Porta, Sonex Master, approved by APL. Every toilet will be equipped with approved fittings and fixtures like
commode/W.C., hand wash basin, urinals, towel rail, mirror with matching soap dish (Master made) etc. Tile (floor) SMD63-108 laid over a bed of 2" thick CC 1:2:4 floor and Wall
Tile SMD63-24SF laid over 1/2" thick broom finished base plaster for dado in toilets complete. Tiles will be laid up to 7’- 6’’ height.
Color and paint will be used of Berger/ICI as per specification. External surfaces Weather coat Internal surfaces Matt finish
5.1
Providing and laying Master Tile MCD-1-117 Light of size 24''x24'' or approved equivalent at specified areas in floors in approved shades, and 4" skirting flush to walls laid over
CS mortar 1:2 (1 cement 2 sand).
Providing and fixing : 1-1/2" thick wooden flush doors made of commercial ply 1st class quality for internal usage complete with painting (RAL 9010 white), approved door locks
and handles etc. Wood-plastic composite doors.
Providing and laying RCC (1:2:4) (i.e. 1 part cement 2 parts sand and 4 part crushed graded boulders 3/4" and down gauge) having a minimum work cube crushing strength of
3000 lbs per sq. inch after 28 days including form work and its removal having straight unbroken joints, rodding, machine mixing, vibrating and curing etc. complete.
Earth filling in plinth foundation for earth brought from outside including transportation etc.
Providing and laying cement concrete 1:4:8 (i.e. 1 cement 4 sand and 8 parts coarse aggregate – crush) under foundation and plinth beam using approved aggregates including
leveling, compacting, curing etc.
Providing and laying C.C. 1:3:6 (i.e. 1 cement 3 sand & 6 parts coarse aggregate – crush) cast in situ using approved aggregate complete as item (c) above.
Providing & laying Cement Concrete solid machine made blocks of approved quality in 1:3:6 ratio. The average compression strength of the above shall be 1000 psi. or providing
& laying first class bricks known as “Class A” bricks. Mortar for block/brick work shall be prepared in 1:4 cement / sand ratio. The joints of the block/bricks shall have ¼” deep
grooves which should be raked before plaster. Cement mortar should be prepared in the quantity to be used within 30 minutes. Refer to relevant items in specification.
Providing and applying (vapor barrier) water proofing, over RCC slab or roof, comprising two coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat,
over one coat of primer and one layer of 500 gauge polythene sheet (weighing 2.5 lbs/100 sft) with at least 9" overlap, with mud in slope (2” min.) and 1" thick 1:6 cement/sand
mortar, Brick roof tiles fixed with fresh mortar & grouted with 1:3 cement/sand slurry, as per specifications or Providing and laying CC 1:2:4 roof screed (minimum 1-1/2” thick) for
water proofing with two coats of bitumen @ 30 lbs per 100 sft and blinded with pea gravel 1/8" to 3/8" in size @ 2 to 5 cft 100 sft, complete in all respects
7 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Offices, Tuck Shop & Waiting Building Sq. ft 2,472
Plinth Protection:
Constructing of plinth protection as shown in the relevant drawings and approved by Engineer Incharge. DWG
# A-02
False ceiling
Providing & Installing false ceiling works in gypsum board 2' x 2' with imported tee 1" wide, powder coated with
proper suspension system complete in all respects. The suspension wires to be supported by anchor-bolts to
the building ceiling.
O. H. Tank ( 250 gallon fiber glass)
Providing and installing fiber glass Over Head Water Tank including 1" dia GI pipe connections to all water
points shown on the drawings or directed by the Engineer, Incharge complete in all respect. There must be
separate supply lines for bathrooms and water cooler.
Safe (under ground)
To be provided and installed as per the drawings # 14 & specifications and recommendations / approval of
APL, complete in all respect
6
5.2 sq. ft
5.3
Installation of Distribution Box as per drawing or Engineer incharge directied & installation of emergency cut off switch (push button NBI/ElectroMac make) which deactivates
whole electric system in one go. (DWG # A-01, A-02, A-03, S-0A, S-0B, S-01, S-02, S-03, S-04, S-05, S-06, S-06a, S-07) Payment shall be made at plinth level in squre feet rate.
5.4
Sub-Total Serial No. 5
5.5 2
Electrification shall be as per specifications and as per Electrical drawings. PAKISTAN CABLE/New Age 7/29, 7/44 for AC & shop, wire in 1" dia PVC Galco/Popular/ DADEX
pipe with air tight joints. Tube light, choke and other fittings will be used of Philips Pakistan made. 16, 20 Amp. Imported switches will be fitted (CLIPSAL or approved equivalent).
Dimmer for fan will also be fitted. Providing and installing 2’x2’ ceiling lights with louver or 12 watt led's ceiling light to be installed in Shop as per electrical drawings &
specification. Providing and installing spot lights at designated locations as per electrical drawings & specification, complete in all respects. Fans/Bracket fans of brand "Pak
Fans", Lahore Fan, "Millat” and “Climax” with sub distribution board for tuck shop & coffee shop & three phase approved electrical meter should be used at locations as per
drawings and identified by Project Engineer.
Front show window and door shall be made in Anodized Aluminum 4" wide & 1.8 mm thick LUCKY or approved make fitted with 08 mm thick plain glass with 100 micron scratch
resistant 3M film. Doors will be provided with LUCKY or approved locking arrangement and RYOBI hydraulic door closure.
3
sq. ft 1,087
each
294
Nos.
Provide water supply line from under ground tank to overhead tank and to different parts of building as identified. For main line 1 1/2" dia pipe of IIL (medium) make and for
internal lines 3/4" dia of IIL (medium) make should be used.
Car Parking and Offices Double Storey Building (Ground Floor + 1st Floor)
Building
Construction of the Building in accordance with the drawings and specifications provided for the project. This will include:
Excavation for foundation in normal/hard clayey/marshy soil including back filling between the trenches plinth and depression including leveling, breaking clods, watering,
8 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Providing and laying RCC (1:2:4) (i.e. 1 part cement 2 parts sand and 4 part crushed graded boulders 3/4" and down gauge) having a minimum work cube crushing strength of
3000 lbs per sq. inch after 28 days including form work and its removal having straight unbroken joints, rodding, machine mixing, vibrating and curing etc. complete.
Color and paint will be used of Berger/ICI as per specification. surfaces Weather coat Internal surfaces Matt finish
Providing and laying (a) cold-worked deformed bars complying with BS 4461 or hot rolled deformed bars with min. yield stress of 60,000 psi or (b) mild steel as per B.S. 4449
with min. yield stress of 40,000 psi, including bending, binding, wastage etc. and placing in position in RCC works on pre-cast cement concrete spacers or steel chairs and tying
Providing and laying 2" thick DPC (Damp proof course) under walls in CC 1:2:4 by volume mixed with water proofing compound Conplast-100 or equivalent @ 1 kg per bag of
cement including formwork leveling, making edges and curing etc. Applying 2 coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat, over one coat
Providing and fixing door of 3mm thick injection molded skins are joined to a specially extruded aluminum frame, fitted with special hot plate welded skin holders and
subsequently filled with rigid polyurethane for high rigidity, strength, thermal and acoustic insulation, complete with painting (RAL 9010 white), approved door locks and
handles etc.
Providing and laying 6" thick stone/brick soling over earth filling laid on edge, hammer pressed with 1:6 Cement grout to fill voids in soling, including leveling, consolidation
curing etc. complete in all respects.Providing and laying 4 1/2" thick cement concrete 1:3:6 bed flooring using approved aggregates complete.
For First Floor: Providing and laying Master Tile MCD-1-117 Light of size 24''x24'' or approved equivalent at specified areas in floors in approved shades, and 4" skirting flush to
walls laid over CS mortar 1:2 (1 cement 2 sand).
Providing and applying (vapor barrier) water proofing, over RCC slab or roof, comprising two coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each
coat, over one coat of primer and one layer of 500 gauge polythene sheet (weighing 2.5 lbs/100 sft) with at least 9" overlap, with mud in slope (2” min.) and 1" thick 1:6
cement/sand mortar, Brick roof tiles fixed with fresh mortar & grouted with 1:3 cement/sand slurry, as per specifications or Providing and laying CC 1:2:4 roof screed
(minimum 1-1/2” thick) for water proofing with two coats of bitumen @ 30 lbs per 100 sft and blinded with pea gravel 1/8" to 3/8" in size @ 2 to 5 cft 100 sft, complete in all
respects
6.1
Earth filling in plinth foundation for earth brought from outside including transportation etc.
Providing and laying cement concrete 1:4:8 (i.e. 1 cement 4 sand and 8 parts coarse aggregate – crush) under foundation and plinth beam using approved aggregates including
leveling, compacting, curing etc.
Providing and laying C.C. 1:3:6 (i.e. 1 cement 3 sand & 6 parts coarse aggregate – crush) cast in situ using approved aggregate complete as item (c) above.
Providing & laying Cement Concrete solid machine made blocks of approved quality in 1:3:6 ratio. The average compression strength of the above shall be 1000 psi. or providing
& laying first class bricks known as “Class A” bricks. Mortar for block/brick work shall be prepared in 1:4 cement / sand ratio. The joints of the block/bricks shall have ¼” deep
grooves which should be raked before plaster. Cement mortar should be prepared in the quantity to be used within 30 minutes. Refer to relevant items in specification.
For Ground Floor: Providing and laying C.C Concrete 1:2:4, 3'' Thk. in flooring in panelling using marble strips 1/2''x2'' or approved equivalent at specified areas in floors in
approved shades, and 4" skirting flush to walls laid over CS mortar 1:2 (1 cement 2 sand).
Providing and fixing all sanitary fittings & fixtures which shall be of Porta, Sonex Master, approved by APL. Every toilet will be equipped with approved fittings and fixtures
like commode/W.C., hand wash basin, urinals, towel rail, mirror with matching soap dish (Master made) etc. Tile (floor) SMD63-108 laid over a bed of 2" thick CC 1:2:4 floor
and Wall Tile SMD63-24SF laid over 1/2" thick broom finished base plaster for dado in toilets complete. Tiles will be laid up to 7’- 6’’ height.
9 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Car Parking and Offices Double Storey Building (Ground Floor + 1st Floor) Sq. ft 2,218
7
7.1
Speed Wash (Including Projections & Finishes)
This will include excavation for foundation in normal/hard clayey/marshy soil including back filling between the trenches plinth including leveling, watering, compacting in layers not
exceeding 6" in depth. Foundation to be brought from virgin soil. Earth filling in plinth foundation for earth brought from outside including transportation etc. Providing and laying
cement concrete 1:4:8 under foundation and plinth beam, floor using approved aggregates including leveling, compacting, curing etc. Providing & laying first class bricks known
as “Class A” bricks. Mortar for block/brick work shall be prepared in 1:4 cement / sand ratio. The joints of the block/bricks shall have ¼” deep grooves which should be raked
before plaster. Cement mortar should be prepared in the quantity to be used within 30 minutes. Refer to relevant items in specification. The joints of the block/bricks shall have ¼”
deep grooves which should be raked before plaster. Providing and laying 2" thick DPC (Damp proof course) under walls in CC 1:2:4 by volume mixed with water proofing
compound Conplast-100 or equivalent @ 1 kg per bag of cement including formwork leveling, making edges and curing etc. Applying 2 coats of special industrial bitumen grade
10/20 at the rate of 1.1 Kg/SM each coat, over one coat of primer and one layer of 500 gauge polythene sheet (weighing 2.5 lbs/100 s.ft.) with at least 9" overlap, complete in all
respects, Providing and laying 6" thick stone/brick soling, Providing and laying National/Master/Karam Ceramic tiles or approved equivalent at specified areas in approved shades
to walls 10' high laid over CS mortar 1:2 (1 cement 2 sand), PCC floor, pit for lift, Providing and applying (vapor barrier) water proofing, over RCC slab or roof, comprising two
coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat, over one coat of primer and one layer of 500 gauge polythene sheet (weighing 2.5 lbs/100 sft)
with at least 9" overlap, with mud in slope (2” min.) and 1" thick 1:6 cement/sand mortar, Brick roof tiles fixed with fresh mortar & grouted with 1:3 cement/sand slurry, as per
specifications or Providing and laying CC 1:2:4 roof screed (minimum 1-1/2” thick) for water proofing with two coats of bitumen PB-4 @ 30 lbs per 100 sft and blinded with pea
gravel 1/8" to 3/8" in size @ 2 to 5 cft 100 sft, complete in all respects,
Speed Wash
Installation of Distribution Box as per drawing or Engineer incharge directied & installation of emergency cut off switch (push button NBI/ElectroMac make) which deactivates
whole electric system in one go. ( DWG # C-01 to C-15 & STR-01 to STR-20 ) Payment shall be made at plinth level in square feet rate. As per drawing (DWG # A-01, A-02, A-03,
S-0A, S-0B, S-01, S-02, S-03, S-04, S-05, S-06, S-06a, S-07, S-08, S-09, S-10)
Sub-Total Serial No. 6
Electrification shall be as per specifications and as per Electrical drawings. PAKISTAN CABLE/New Age 7/29, 7/44 for AC & shop, wire in 1" dia PVC Galco/Popular/
DADEX pipe with air tight joints. Wiring for 5-A plug points on common board, Universal plug with 2X3/.029 PVC wire and 1X1.5mm2 insulated wire as ECC complete with 3
pin sockets and switches. Tube light 18 watt (LED/SMD'S) and Ceiling light out sides & insides 15 watt (LED/SMD's) fittings will be used of Philips Pakistan made. Circuit
Breaker (16, 20 Amp) as per requirement of site . Imported switches will be fitted (CLIPSAL or approved equivalent). Dimmer for fan will also be fitted. Providing and installing
2’x2’ ceiling lights (LED/SMD's) with louver to be installed in Shops. as per electrical drawings & specification. Providing and installing spot lights at designated locations as per
electrical drawings & specification, complete in all respects. Fans/Bracket fans of brand "Pak Fans", Lahore Fan, "Millat” and “Climax” should be used at locations as per
drawings and identified by Project Engineer.
Front show window and door shall be made in Anodized Aluminum 4" wide & 1.8 mm thick LUCKY or approved make fitted with 08 mm thick plain glass with 100 micron
scratch resistant 3M film. Doors will be provided with LUCKY or approved locking arrangement and RYOBI hydraulic door closure.
Provide water supply line from under ground tank to overhead tank and to different parts of building as identified. For main line 1 1/2" dia pipe of IIL (medium) make and for
internal lines 3/4" dia of IIL (medium) make should be used.
10 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Speed Wash Sft 512
Compressor Rooms
Compressor Rooms Sft 50
This will include excavation for foundation in normal/hard clayey/marshy soil including back filling between the trenches plinth including leveling, watering, compacting in layers not
exceeding 6" in depth. Foundation to be brought from virgin soil. Earth filling in plinth foundation for earth brought from outside including transportation etc. Providing and laying
cement concrete 1:4:8 under foundation and plinth beam, floor using approved aggregates including leveling, compacting, curing etc. Providing & laying first class bricks known
as “Class A” bricks. Mortar for block/brick work shall be prepared in 1:4 cement / sand ratio. The joints of the block/bricks shall have ¼” deep grooves which should be raked
before plaster. Cement mortar should be prepared in the quantity to be used within 30 minutes
7.2
Refer to relevant items in specification. The joints of the block/bricks shall have ¼” deep grooves which should be raked before plaster. Providing and laying 2" thick DPC (Damp
proof course) under walls in CC 1:2:4 by volume mixed with water proofing compound Conplast-100 or equivalent @ 1 kg per bag of cement including formwork leveling, making
edges and curing etc.
Providing and laying RCC (1:2:4) (i.e. 1 part cement 2 parts sand and 4 part crushed graded boulders 3/4" and down gauge) having a minimum work cube crushing strength of
3000 lbs per sq. inch after 28 days including form work and its removal having straight unbroken joints, rodding, machine mixing, vibrating and curing etc. complete. Providing and
laying cold-worked deformed bars complying with BS 4461 or hot rolled deformed bars with min. yield stress of 60,000 psi including bending, binding, wastage etc. and placing in
position in RCC works on pre-cast cement concrete spacers or steel chairs and tying with 18 gauge wire etc. complete in all respects. Color and paint will be used of Berger as
per specification. External surfaces Weather coat Internal surfaces Matt finish, Electrification shall be as per specifications and as per Electrical drawings. PVC PAKISTAN
CABLE 7/29 internal wiring & 7/44 for air compressor wire in 1" dia PVC Galco/Popular/ DADEX pipe with air tight joints. Tube light, choke and other fittings will be used of Philips
Pakistan made. complete in all respect as per (DWG # A-01, A-02, A-03, S-0A, S-0B, S-01, S-02, S-03, S-04, S-05, S-06, S-06a, S-07, CW-01, CW-02) and instructions of the
Engineer. (Bill measurement shall be measured at plinth level).
Providing and laying RCC (1:2:4) (i.e. 1 part cement 2 parts sand and 4 part crushed graded boulders 3/4" and down gauge) having a minimum work cube crushing strength of
3000 lbs per sq. inch after 28 days including form work and its removal having straight unbroken joints, rodding, machine mixing, vibrating and curing etc. complete. Providing and
laying cold-worked deformed bars complying with BS 4461 or hot rolled deformed bars with min. yield stress of 60,000 psi including bending, binding, wastage etc. and placing in
position in RCC works on pre-cast cement concrete spacers or steel chairs and tying with 18 gauge wire etc. complete in all respects. Color and paint will be used of Berger as
per specification. External surfaces Weather coat Internal surfaces Matt finish, Electrification shall be as per specifications and as per Electrical drawings. PVC PAKISTAN
CABLE 7/36 & 7/44 wire in 1" dia PVC Galco/Popular/ DADEX pipe with air tight joints. Louver gate as per drainage Tube light, choke and other fittings will be used of Philips
Pakistan made. Installation Sub-distribution Box as per drawing or Engineer incharge directied complete in all respect as per drawings and instructions of the Engineer. (Bill
measurement shall be measured at plinth level).
Applying 2 coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat, over one coat of primer and one layer of 500 gauge polythene sheet (weighing 2.5
lbs/100 s.ft.) with at least 9" overlap, complete in all respects, Providing and laying 6" thick stone/brick soling, PCC Flooring, Providing and applying (vapor barrier) water proofing,
over RCC slab or roof, comprising two coats of special industrial bitumen grade 10/20 at the rate of 1.1 Kg/SM each coat, over one coat of primer and one layer of 500 gauge
polythene sheet (weighing 2.5 lbs/100 sft) with at least 9" overlap, with mud in slope (2” min.) and 1" thick 1:6 cement/sand mortar, Brick roof tiles fixed with fresh mortar &
grouted with 1:3 cement/sand slurry, as per specifications or Providing and laying CC 1:2:4 roof screed (minimum 1-1/2” thick) for water proofing with two coats of bitumen @ 30
lbs per 100 sft and blinded with pea gravel 1/8" to 3/8" in size @ 2 to 5 cft 100 sft, complete in all respects,
11 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Concrete paving
Constructing hard standing in 1:2:4 concrete. The concrete should be poured in 4' x 4' panel 6". RCC 1:2:4 ratio
thick complete in all respect as per drawing & as direction of Engineer Incharge.
Grating in front of car wash
Providing of RCC drain channel with fixing MS Grating complete in all respect as per drawing & as direction of
Engineer Incharge. DWG # CW-03
8
8.1
Air Line:- Providing & fixing of GI 1/2" dia pipe line best quality make of IIL Karachi from compressor to
equipment including all required fittings like, tee, elbows, bend, socket, nozzle, & ball valve complete in all
respect as directed by the engineer incharge.
Rft 200
9
9.1
Septic tank:- Construction of Septic Tank as per attached drawing including excavation, PCC, RCC, steel
reinforcement, shuttering, baffle wall, sewer pipe connection heavy duty manhole cover as per standard &
attached drawing # 15
Each 2
8" dia Sewerage Line
Providing of sewer line includes supply and laying of sewerage line for the site. Job includes providing and
laying 8" dia pipe uPVC schedule 40 (Pak-Arab, Dadex, AGM, Pak-Saudi) for sewerage disposal, jointing
collars with the adhesive solution and constructing RCC manhole inspection chambers (18’X18”) and providing
connection to kiosk, toilet and roof, Also providing connection in uniform slope to Civic Agencies main
sewerage complete as per standard and as directed by Engineer Incharge.
10
Reciprocating Pump
The job includes provision & installation of 1 hp pump make (diamond & Golden) with pipe-fittings.
7.4
10.1
9.2
Job
Each
250
Sub-Total Serial No. 9
Drainage
7.3
1
9.3
Sub-Total Serial No. 8
56
Sub-Total Serial No. 7
Tyre Shop Building
Oil Separator:- Construction of Septic Tank as per attached drawing including excavation, PCC, RCC, steel
reinforcement, shuttering, baffle wall, bib cock, sewer pipe connection heavy duty manhole cover as per
standard & attached drawing # 16. (For design of 2600 Sft catchment area).
Sft 360
Rft
Water
Each
1
12 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
10.2
Underground Water tank:- Construction of under ground water tank as per attached drawing including
excavation, PCC, RCC bed, RCC wall, RCC roof, steel reinforcement, shuttering, heavy duty manhole cover,
stair arrangement etc.; complete as per standard & attached drawing # 18. Capacity 3,500 Glns
Each 1
10.3
Water supply to lawn 3/4" dia:
Providing 3/4” dia pipe of IIL Karachi (medium) make including ball valve, elbows, tee sockets etc.; to desired
locations as per instructions of APL engineer.
Rft 600
Water supply to water cooler
Providing 1/2” dia pipe of IIL (medium) make including ball valve, elbows, tee sockets etc.; to desired locations
as per instructions of APL engineer.
Water Cooler
Providing & fixing of water cooler 150 liters capacity make Meco, Super Asia, Cannon & or approved from APL.
Including water filter, fixing in position, complete in all respect.
Base for Water Cooler with Drain
The job includes construction of base with PCC (1:3:6) and tile work National Tiles 4” x 10” on base & side wall
with proper filling & drainage point and as per direction of Engineer Incharge
11
Electrification of Dispenser:
Providing and laying 4-core (Pakistan Cables) cables of recommended sizes (as shown on specification) in 1”
dia PVC conduits of AGM/Pak-Arab/Dadex under the forecourt, including making connections with circuits and
providing sockets, switches etc. complete in all respects. The 2 cables will run in 2 separate conduits and
quantity will be measured as a set of 2 lines and as per direction of Engineer Incharge
Electrification of Submersible pumps:
Providing and laying 4-core (Pakistan Cables) cables of recommended sizes (as shown on drawings) in 1” dia
PVC conduits of AGM/Pak-Arab/Dadex under the forecourt, including making connections with circuits and
providing sockets, switches etc. complete in all respects and as per direction of Engineer Incharge
Electrification of Spreader:
Providing and laying 3-core (Pakistan Cables/Newage/Pioneer) cables of recommended sizes (as shown on
specification) 1” dia schedule 40 uPVC conduits of AGM/Pak-Arab/Dadex, complete in all respects and as per
direction of Engineer Incharge
11.2 Rft 650
Rft
Electrification of Site
10.6
1
Each
700Rft 11.1
Rft 800
150
1
Sub-Total Serial No. 10
Each
11.3
10.4
10.5
13 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Electrification of Credit Card reader
Providing and laying coaxial wire (Pakistan Cables/Newage/Pioneer) cables of recommended sizes 1” dia
schedule 40 uPVC conduits of AGM/Pak-Arab/Dadex, complete in all respects and as per direction of Engineer
Incharge
PVC Conduit Pipe for Dispenser Unit & Submersible Pump for automatization
Providing and laying PVC conduits 1” dia by AGM/Pak-Arab/Dadex, and as per direction of Engineer Incharge.
Main Distribution Board:
Providing and fixing Main Distribution Board as per drawings of approved quality from approved manufacturers
which should have MG, NBI or equivalent main switch, circuit breakers, change over switch with mechanical
interlock, voltmeter, ammeter, phase indicator, knobs complete in all respect as per the specifications and
instruction of APL Engineer. Distribution of load should be balance as per the standard power distribution
specification. The item also covers the supply and fixing of switches for all external lighting as per specification
and drawings within the DB room. Providing and fixing of powder coated MS racks as per APL standards for
stabilizers inside the DB room and provision & installation of IN/OUT switches & sockets for dispensers cabling
to stabilizers. As per advice of Engineer Incharge
Sub Distribution Board For Tyre Shop:
Providing and fixing Sub Distribution Board as per drawings of approved quality from approved manufacturers
which should have MG, NBI, A-Z Karachi or equivalent main switch, circuit breakers, change over switch ,
voltmeter, ammeter, phase indicator, knobs complete in all respect as per the specifications and instruction of
APL Engineer. Distribution of load should be balance as per the standard power distribution specification. The
item also covers the supply and fixing of switches for all external lighting as per specification and drawings
within the DB room as per advice of Engineer Incharge
Electrification of Steel Canopy (Fascia & Ceiling Lights)
Providing & Laying of 3-core (Pakistan Cables/Newage or equivalent) cables of recommended sizes (as
shown on specification) 1” dia as per electrical specification for fascia including Electrification of Under
Canopy ceiling lights as per electrical drawings. Connection has to be taken form Distribution board to canopy
providing circuits for the under canopy lights and circuits for fascia as shown in electrical drawings approved
electrical fittings & connections. (All under ground wiring to be double PVC-as per specifications. Water proof
fittings & junction boxes to be provided. Route to be as per the approval of Engineer.
Electrification of CO sign
Providing and laying 3-core (Pakistan Cables/Newage/Pioneer) cables of recommended sizes (as shown on
specification) 1” dia schedule 40 uPVC conduits of AGM/Pak-Arab/Dadex, complete in all respects or as
directed by Area Engineer.
Job 1
11.4
700
11.5
Rft
140
1,600
Rft
1,200Rft
Rft 11.8
11.7
11.6
11.7 Job 1
14 OF 14
CONSTRUCTION OF APL RETAIL OUTLET (COMPANY FINANCED) ON DEFENCE ROAD, DEFENCE HOUSING AUTHORITY, LAHORE
ATTOCK PETROLEUM LIMITED
S.NO. UnitComponents Quantity Rate Per Unit Cost
Electrification of water cooler
Providing and laying cables of recommended sizes (as shown on specification) in 1” dia schedule 40 uPVC
conduits of AGM/Pak-Arab/Dadex, including making connections with circuits and providing 15 amps. sockets,
switches etc. complete in all respects.
35mm Four core cable from Wapda to MDB
The job also includes the supply and laying of 4 core main cable 35 mm thick (New age/Pakistan Cable or
approved from APL) as per specification. Main cable connect from WAPDA meter to the MDB in a 4” dia 40
uPVC conduits of AGM/Pak-Arab/Dadex as per advice of Engineer.
Electrification of Secondary Sign (Site name, Air, Water, Parking etc.)
Providing and laying 3-core (Pakistan Cables/Newage/Pioneer) cables of recommended sizes (as shown on
specification) in 1” dia PVC conduits of AGM/Pak-Arab/Dadex including the providing and fixing of back boxes
in boundary wall with APL standard water proof boxes.
Electrification of In/Out Sign
Providing and laying 3-core (Pakistan Cables/Newage/Pioneer) cables of recommended sizes (as shown on
specification) 1” dia PVC conduits of AGM/Pak-Arab/Dadex, complete in all respects or as directed by Area
Engineer.
HRC light poles - Single Arm
Supply and installation of light around boundary of the site. Fabrication & Installation of 30 ft high pole with
base plate to be fixed with nuts and bolts air tight joints drawing # 17. Schedule 40 pipe will be used. Rate will
include foundation & electrification from light to junction box fitted on pole. Avenue light provided by APL
HRC light poles - Double Arm
Supply and installation of light around boundary of the site. Providing and installing, 30 ft high pole with base
plate to be fixed with nuts and bolts air tight joints as per drawing # 17. Schedule 40 pipe will be used. Rate will
include foundation & electrification from light to junction box fitted on pole. Avenue light provided by APL
Electrification of HRC light pole
Providing and laying 3-core (Pakistan Cables/Newage/Pioneer) cables of recommended sizes (as shown on
specification) 1” dia PVC conduits of AGM/Pak-Arab/Dadex, complete in all respects or as directed by Area
Engineer.
Sub-Total Serial No. 11
2Each
Rft
Rft
Rft
11.15
5
Rft
1,200
11.12
15011.11
11.13
600
Grand Total Serial No. 1 to 11
350
11.14
Each
125
Rft
11.9
11.10
Public Toilet:
Master Tile MCD-1-117
Light of size 24''x24''CS plaster CS plaster
Office (Retailer &
Manager)
Commercial ply
solid core shutter
in white ICI
enamel matt finish
Doors Windows Paint
(Master made) Wall
Tile SMD63-24SF
White ICI / Berger plastic emulsion paint on internal walls.
white ICI Dulux distemper paint on ceiling.
External wall: Weathershield paint in white Code: Ral 9003 & Pantone
705
Commode/WC, Mixer, Tap,
Shower & etc
Color: Ivory Color
Brand: Sonex / IFO/ Master
CS plaster
Toilet:
Tuck Shop
Chamagne
Aluminium 13/4"
x 4"x1.8 mm with
5mm clear glass
with pasting of
scratch resistance
3M film 100
micron
Chamagne
Aluminium 13/4"
x 4"x2"mm with
12mm imported
clear glass
Steel rolling shutter
/ Louver gate in
grey enamel paint
Same as above Same as above
Ventilater:
Chamagne
Aluminium
13/4" x 4"x 1.8
mm with 5mm
clear glass with
pasting of scratch
resistance 3M film
100 micron
White ICI / Berger plastic emulsion paint on internal walls.
White ICI Dulux distemper paint on ceiling.
External wall: White Weathershield paint
(Master made) Tile (floor)
SMD63-108
Chamagne
Aluminium 13/4"
x 4"x2 mm with
12mm clear glass
with pasting of
scratch resistance
3M film 100
micron
Same as aboveMaster Tile MCD-1-117
Light of size 24''x24''CS plaster
Angle Iron Color: Silver grey RAL 7001
White ICI / Berger plastic emulsion paint on internal walls.
White ICI Dulux distemper paint on ceiling.
Code: Ral 9003 & Pantone 705
Tyre Shop
4"x10", National Tile NT-
711
Speed Wash
Same as above
Pump Island4"x10", National Tile
NT-711
Material Specifications
Space Floor Walls Ceiling
Smooth finish cement
conc. CS plaster
Louver gate in
grey enamel paint
False ceiling 24"x24"
White Flat Laminated
gypsum board with
power coated std.
Metal runner
Smooth finish cement conc CS plaster CS plaster
Same as above(Master made) Wall
Tile SMD63-24SF
(Master made) Tile (floor)
SMD63-108CC plaster
Commode/WC, Mixer, Tap
Shower & ETC.
Color: Ivory Color
Brand: Sonex / Imaster or
Commercial ply
solid core shutter
in white ICI
enamel matt finish,
& aluminum make
12" high tore
Chamagne
Aluminium
13/4" x 4"x1.8
mm with 5mm
clear glass with
pasting of scratch
Material Specifications
Fill Point Paint: Vent Pipe Paint: Kerb Stone Safe Guard Light Pole Tuff Pavers Canopy Fascia Paint
Diesel: Green Diesel: Green ICI / BERGER
Supreme: Red Supreme: Red 3M Green 3630-H-5029
H - Octane: White H - Octane: White 3M Red 3630-43
Under Canopy Lights:
Philips:
MPF-932 HPIT,
plus 400 watt
with BSN gear.
Building Light Fixtures Switches & Sockets Cables Wood / False ceilng & Steel
* Flushed Doors : White RAL 9003 & Pantone 705
* Wooden Doors: White RAL 9003 & Pantone 705
Shop Store 4 ft. Philips T. L. TMS 140 * Ceiling : White RAL 9003
Attendant Room 4 ft. Philips T. L. TMS 140 * Door locks:- Yale / Alpha
Lube Store 4 ft. Philips T. L. TMS 140
Toilets, floor
Speed Wash
Pakistan Cables /
Pioneer /
Newage
Color: White (RAL
9003 & Pantone
705)Envicrete,
Hub Crete,
Bannu Mukhtar,
Concrete Concept
Minimum 6,000
PSI Crushing
Strenght
SGX-186 Avenue
Light & Son-T 250
watt Lamp
Electrical Fixtures Details:
Color: Black &
Yellow(RAL:1028 &
Pantone:137)
Color: Black & Yellow
(RAL:1028 &
Pantone:137)
Dealer office
Tuck Shop2'x2' Philips Tube Light, TLD 36W / 83 wl GBS
300 E/240L Louvers
Brand: Sonex / Imaster or
equilent
12" high tore
protection in
bottom
pasting of scratch
resistance 3M film
100 micron
2'x2' Philips Tube Light, 300E/240L Louvers OR
TLD 36W/83 wl GBS
Canopy Column Color: White (RAL 9003 & Pantone 705)
Canopy Ceiling: 26 SWG in white color
Philips Pacific TCW-095/136 (water proof lights)
TLD 36W/83 wl GBS
* Towel rail, soap dish and coat hanger to be stainless steel.
* False ceiling 24"x24" Off White Flat Laminated gypsum board with power coated
standard with Metal runner
* MS Collapsible louver door for sheds : Silver grey RAL 7001Switchkid-Alpine -
Clipsal series Ivory /
White color
* Chamagne color Aluminium
Quantity (Nos.) Area (mm2) Designation No. of Cores
1 1 35 19/64 4
2 1 35 19/64 4
3 2 4 7/36 3
4 1 4 7/36 3
5 1 1.5 3/29 3
6 1 4 7/36 3
7 1 2.5 7/29 3
8 1 2.5 7/29 3
9 1 6 7/44 3
10 1 6 7/44 4
11 1 6 7/44 4
12 1 2.5 7/29 Single
13 1 2.5 7/29 3
14 1 2.5 7/29 3
15
a 1 1.5 3/29 Single
b 1 1.5 3/29 Single
c 1 1.5 3/29 Single
16
a 1 8
b 1 8
c 1 8
d 1 8
e 1 8
f As Required 16
17
a
b
c
d
18
Sr.No.
General Electrical Specifications
Deep Freezer
Electric Cable Specifications
Transformer to D.B
Generator to Main D.B
Water Cooler
Description
Main D.B to Dispenser
Pylon
In/Out
Pole Lights
Water Pump
Air Conditioner
Air Comp. (Tyre Shop)
Air Comp. (Speed Wash)
Water Pump (Speed Wash)
Separate Sub Distribution Boards To Be Installed For:
Copper Conductor
General Earthing
In/Out Sign
Chiller
Generator
Earthing Pit
Canopy
Underground Fuel Storage Tank
Dispenser
Main Distribution Board
Energy Savers / Bulbs / Tube Lights
Fans
General Wiring For Lights & Fans
Speed Wash
Tyre Shop
Tuck Shop
Masjid
Surge Protectors To Be Installed For Dispensers
Annexure-3
S.# Material Item Unit Rate
1 Cement Per Bag
2 Rough Sand Per Cft
3 Fine Sand Per Cft
4 Borrow Pit Sand Per Cft
5 Crush Per Cft
6 Weather Shield Paint Per Gallon
7 Emulsion Paint Per Gallon
8 Steel Reinforcement Per Kg
9 Bitumen Drum Per 200 Kg
10 Scafolding Rate Per Sft
11 Skilled Labour Rate Per Wage
12 Unskilled Labour Rate Per Wage
13 Steel Binding Labour Per Kg
14 Bricks Per 1000 Bricks
15 National Tile 10" x 5" NT 816 Per Sq-m
16 Floor Tile 16" x 16" Granite Ivory Per Sq-m
17 Glazed Tile 8" x 10" Master Ivory Per Sq-m
18 Glazed Tile 6" x 8" Master White Per Sq-m
19 Matt Floor Tile 8" x 8" Per Sq-m
20 4" Dia UPVC Pipe Per Rft
21 6" Dia UPVC Pipe Per Rft
22 2.5 sq-mm 1-Core Per 90 RM Coil
23 2.5 sq-mm 3-Core Per 90 RM Coil
24 4 sq-mm 3-Core Per 90 RM Coil
25 4 sq-mm 1-Core Per 90 RM Coil
26 6 sq-mm 1-Core Per 90 RM Coil
27 Copper Per Kg
28 Anti Shatter Safety Film Per Sft
29 4" Dia MS Pipe Per 20 Rft
30 1/2" Dia G.I Medium Pipe Per 20 Rft
31 3/4" Dia G.I Medium Pipe Per 20 Rft
32 1" Dia G.I Medium Pipe Per 20 Rft
33 1" Dia PVC Pipe (Popular) Per 13 Rft
34 2" Dia PVC Pipe (Popular) Per 13 Rft
35 3" Dia PVC Pipe (Popular) Per 13 Rft
36 4" Dia PVC Pipe (Popular) Per 13 Rft
37 OH Water Tank 250 Gallon (Super Tuff) Each
38 OH Water Tank 400 Gallon (Super Tuff) Each
39 OH Water Tank 1000 Gallon (Super Tuff) Each
40 Centrifugal Pump (1/2 HP) Each
41 Centrifugal Pump (1 HP) Each
42 Centrifugal Pump (2 HP) Each
43 Philips SGX-186 Avenue Each
44 Philips TCW-097/236 Each
Basic Rate of Civil works
3