Upload
bathsheba-nelson
View
219
Download
0
Embed Size (px)
DESCRIPTION
3 BROOKHAVEN SCIENCE ASSOCIATES Modes of Access General Users (GUs) Users apply for time on facility or non-facility beamlines. Proposals can be one time (one cycle) or two year (program). Provision also for rapid access on certain beamlines (reviewed after the fact). Contributing Users (CUs) Individuals or groups who carry out research at NSLSII Facility Beamlines and also enhance beamline capabilities and/or contribute to their operation. Year FacilityBAT GU/CU 120%50%30% 220%35%45% 320%0%80%* * GU time to be no less than 50% BAT Access – Facility run beamlines Would ramp up to 80:20 division. GU time no less than 50% in steady state. BDT Access – User run beamlines At least 25% of the time to GU program. Commissioning comes out of BDT time. Possible BAT ramp up
Citation preview
1 BROOKHAVEN SCIENCE ASSOCIATESBROOKHAVEN SCIENCE ASSOCIATES
Beamline Development and Facility Usage
2 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Development
• Beamline Access Teams (BATs) Facility receives funding to design, construct, and operate beamlines.
• Beamline Development Teams (BDTs)User group receives funding to design, construct, and operate beamline.
Two principal modes :User groups would form and work with the facility to define the scientific mission and technical requirements for the beamline
3 BROOKHAVEN SCIENCE ASSOCIATES
Modes of Access• General Users (GUs)
• Users apply for time on facility or non-facility beamlines. Proposals can be one time (one cycle) or two year (program). Provision also for rapid access on certain beamlines (reviewed after the fact).
• Contributing Users (CUs)• Individuals or groups who carry out research at NSLSII Facility Beamlines and also enhance beamline capabilities and/or contribute to their operation.
Year Facility BAT GU/CU
1 20% 50% 30%2 20% 35% 45%3 20% 0%
80%** GU time to be no less than 50%
BAT Access – Facility run beamlines
• Would ramp up to 80:20 division.• GU time no less than 50% in steady state.
BDT Access – User run beamlines
• At least 25% of the time to GU program.• Commissioning comes out of BDT time.
Possible BAT ramp up
4 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Access TeamsSubmit LOI
(10 pages)
DecisionEFAC
CDR
Feedback
TDR
BRR
Construction begins
Allocation of fundsFacility review
Refined cost estimate. Long lead time procurement commences
Facility hires made
Facility review
Facility review
Commissioning begins
As built design
Project funded MIE funded
5 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Development TeamsSubmit PP
(10 pages)
DecisionEFAC
CDR
Feedback
TDR
BRR
Construction begins
Documentation of funds and conceptual design.Allocation of beamlineFacility review
Long lead time procurement
Selected
Full Proposal Submitted
Facility review
Facility reviewCommissioning complete
As built design
Approval to seek funds
Facility assigns Project Coordinator
Facility review
6 BROOKHAVEN SCIENCE ASSOCIATES
Tentative Process & Schedule
2007 2008 2009 20112010 2012 2013 2014 2015
1st beamBO Ring bldg
Construction Commiss-ioning
LOI: Select BATs
TDRProject BATs
Initial BDTs
Possible MIEs
CDR TDR
LOI: Select BDTs
Full proposal
CDR TDR Construction Commiss-ioning
Possible MIEs ?
7 BROOKHAVEN SCIENCE ASSOCIATES
BAT Timeline
Call for LOI : March 2007Evaluate and select BATs: April 2008Staff hired for BAT: December 2008Develop and approve CDR: December 2009Develop and approve TDR: November 2010 Long Lead Procurement: November 2010Begin Construction June 2011Begin commissioning: Jan 2013End commissioning: Dec 2013
2007 2008 2009 20112010 2012 2013 2014 2015
1st beamBO Ring bldg
Construction Commiss-ioning
Select BATs + hire staff TDRCDR
Select PPs
Full proposal
Fund-ing CDR TDR Construction Commiss-
ioning
8 BROOKHAVEN SCIENCE ASSOCIATES
NSLS-II Beamlines15 five m straights for user undulators
• Could potentially drive up to 30 beamlines by canting two undulators
4 eight m straights for user undulators• Could potentially drive up to 12 beamlines by canting three undulators
8 eight m straights for user damping wigglers• Could potentially drive up to 24 beamlines by canting three DWs
20 BM ports for UV and soft X-rays10 BM ports for IR
• 5 large aperture for far-IR• 5 regular aperture for mid/near-IR
At least 57 beamlinesMany more w/ maximum IDs per straight
(plus possible multiple hutches per beamline)
9 BROOKHAVEN SCIENCE ASSOCIATES
Usage of Facility
Type IDs BMs Total IDs BMs Total
A IR/UV/soft x-ray spectroscopy 1 11 12 3 7 10B X-ray spectroscopy 6 3 9 0 9 9C soft-matter/biophysics scattering 4 0 4 0 8 8D hard matter/strongly correlated 9 1 10 3 5 8E powder/single Xtal/high-P/optics 7 3 10 3 8 11F Imaging/micro-probe 4 5 9 2 7 9G Macromolecular crystallography 7 0 7 2 8 10
Totals 38 23 61 13 52 65
NSLSNSLS-II
A strawman beamline distribution was constructed for one possible scenario for a mature facility:
Note: This process took into account the expected demand, the existing community and the enhanced NSLS-II capabilities. In this scenario a few IDs and a few BMs remain open.
10 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Distribution: Insertion Devices
Beamline Type
Unavailable (machine)
IR/UV/soft spect
Soft MatterX-ray Spect.
Powder/Hi-P/opticsHard Matter
PXImaging/Microprobe
Open
11 BROOKHAVEN SCIENCE ASSOCIATES
Beamline Type
Unavailable (machine)
IR/UV/soft spect
Soft MatterX-ray Spect.
Powder/Hi-P/opticsHard Matter
PXImaging/Microprobe
Open
Beamline Distribution: Bending Magnets
BROOKHAVEN SCIENCE ASSOCIATES
12 BROOKHAVEN SCIENCE ASSOCIATES
Scientific Staff at NSLS-II
Roles and responsibilities of NSLS-II staff• User support and independent research
• What fraction of time on independent research?• Connection to outside community
• Joint Appointments• Role of Joint Photon Science Institute• NSLS-II Fellows
– Very few (1-2) select individuals allocated resources and significant fraction of a beamline (beamtime through CU mode?). Expected to produce at very high level. Rigorously reviewed and competed for.