Upload
tranduong
View
215
Download
0
Embed Size (px)
Citation preview
1 Exam Prep – Study Guide for Commercial Carpentry 1
1 Exam Prep
Prov Study Guide for Commercial Carpentry
Tabs and Highlights
These 1 Exam Prep Tabs are based on Study Guide for Commercial Carpentry, 2nd Edition.
Each Tabs sheet has five rows of tabs. Start with the first tab at the first row at the top of the page; proceed
down that row placing the tabs at the locations listed below. Place each tab in your book setting it down one
notch until you get to the bottom of a page. Then start back at the top again. After each Tab, under
"Reason/Highlight" is a brief explanation of the purpose of the tab, and/or items to highlight in the section.
Special Note to our Students: If you are a 1 Exam Prep student, here is how to really get the most from
these 1 Exam Prep Tabs. Follow the above instructions, but before placing the tab, find the tab's topic in the
outline of your appropriate module. Now locate and highlight several items listed in the outline just before
the topic, and just after. See how the topic fits in the outline and how it relates as a concept to the broader
concept spelled out in the outline. If you take a few minutes to do this, when you take the test key words in
the test questions will remind you of where the information is in the manual!
1 Exam Prep Tab Page # Section Reason/Highlight
Table of Contents I Table of Contents
Thermal and Moisture 1 27203-13 Thermal and Moisture Protection
Protection
7 1.0.0 Safety Requirements for Insulation Projects: In
addition to working at elevations, the following
other potential hazards may be encountered on an
insulation project: 4 bullets.
1.2.0 Materials Handling: Safety data sheets
Many insulation and roofing materials contain
chemicals that may be hazardous if not handled
properly.
Insulation 10 2.0.0 Insulation and its Characteristics: A vapor
barrier is any material that prevents the passage of
water.
2.1.0 Determining R-value Requirements: Heat loss
can be significantly reduced by using insulation
sheathing.
12 Figure 2: Typical R-value identification
1 Exam Prep – Study Guide for Commercial Carpentry 2
1 Exam Prep Tab Page # Section Reason/Highlight
The term R-value refers to the resistance to
conductive heat flow through a material or gas. R-
value is expressed as: (equation).
13 Table 2: R-values of Common Materials
14 2.2.0 Flexible insulation: Flexible insulation is usually
manufactured from fiberglass in blanket form and
… in 15” or 23” widths.
In general, insulation must be installed where any
exterior surface … These are: 5 bullets.
15 Fiberglass batt insulation at a 3 ½ thickness may
be used on exterior walls between the studs.
2.3.0 Loose-Fill Insulation: In new construction, it is
usually blown or poured and spread over ceiling
joists in unheated attics.
The required number of bags or pounds … the
bag-label charts for the desired R-value.
2.4.0 Rigid or Semi-rigid Insulation: It is available in
widths up to 4’ and lengths up to 12’. Structural
insulating boards come in densities ranging from
15 to 31 pounds per square foot. Their primary
purpose is structural, while their secondary
purpose is insulation.
Nonstructural rigid foam board … is usually light
weight sheet or board made of fiberglass or
foamed plastic such as … expanded perlite.
Table 3: Recommended R-Values of Insulation
19 The most common rigid and semi rigid and semi-
rigid insulation types include the following:
-Rigid expanded polystyrene
- Rigid extruded polystyrene
- Rigid polyurethane and polyisocyanurate
- Semirigid Fiberglass
1 Exam Prep – Study Guide for Commercial Carpentry 3
1 Exam Prep Tab Page # Section Reason/Highlight
2.5.0 Reflective Insulation: usually consists of
multiple layers of aluminum foil bonded to inner
layers of aluminum foil bonded to inner layers of
various materials for strength. The number of
reflective surfaces determines its insulating value.
To be effective the metal foil must face an open
air space that is ¾” or more in depth.
20 2.6.0 Misc. Types of Insulation:
- Foamed-in-place
- Sprayed-in-place insulation
- Lightweight aggregate
22 3.1.0 Installing Flexible Insulation:
- Step 1:
- Step 2: If stapling to the face of the studs; on the
sides, space them about 6” apart.
- Step 3:
23 3.2.0 Installing Loose-Fill Insulation
- Step 1:
- Step 2: Permanently install strike-off boards.
- Step 3:
26 Figure 18 – Leveling loose-fill insulation
3.3.0 Installing Rigid or Semi-Rigid Insulation:
Insulation is only applied around the perimeter of
the slab, anywhere from 24” to 36”from the edge
of the slab.
Figure 19 – Rigid insulation installed under a
concrete slab.
Moisture Control, 28 4.0.0 Moisture Control, Waterproofing, and
Waterproofing & Ventilation Ventilation
4.1.0 Moisture Control: Water vapor contained in air
can readily pass through most building materials
used for wall construction.
To prevent the concentration of this damaging
moisture, some precautions must be taken in
original design of structure: 4 bullets
1 Exam Prep – Study Guide for Commercial Carpentry 4
1 Exam Prep Tab Page # Section Reason/Highlight
Basements usually have the most trouble with
condensation in summer during humid weather.
29 To keep moisture from rising up into the basement,
6” of course gravel should be placed over the
compacted earth to provide drainage to the
perimeter drain before the slab is poured.
Figure 21: Effects of insulation and vapor barrier.
4.1.1 Interior Ventilation: One of the best ways to
reduce or eliminate the chances of moisture damage
in attics or in the space between the rafters and the
finished roof.
In insulated attics, baffles (blocking strips are used
to … vented areas.
24 The ventilation requirement for a gable roof is 1 sq.
ft. of free air ventilation for every 300 sq, ft. of
ceiling area.
4.1.2 Vapor Barriers: Vapor materials are any material
or substance that will not permit the passage of
water vapor or will do so only at an extremely low
rate. The permeability of a substance … The
measure of water vapor permeability is the perm.
4.1.3 Materials: Common vapor barrier materials include
asphalted … and polyethylene film.
Table 5: Perm Ratings of Various Vapor Retarder
Materials
31 Polyethylene film is applied over the studs and
ceiling joists after the insulation is installed.
The film should be overlapped 2” to 4” and sealed
with special mastic or tape.
4.1.4 Installation in Crawl Spaces: The ground under
a ventilated crawl space should be covered with a
vapor barrier ground cover to protect the
underside of the house from condensation.
1 Exam Prep – Study Guide for Commercial Carpentry 5
1 Exam Prep Tab Page # Section Reason/Highlight
The normal requirement is 1 sq. ft. of free air
ventilation for every 160 sq ft of crawl space area
when vapor barrier ground cover is used.
4.1.5 Installation in Slabs: Up to 80 percent of the
moisture entering a structure does so by migrating
from the ground beneath the structure.
Vapor barriers should be continuous under the
slab.
32 Figure 25: Vapor barrier installation for crawl
spaces.
Figure 27: Surface-mounted vapor barrier on a
slab.
4.1.6 Installation in Walls: Adjacent sheets of film are
overlapped 2” to 4” and are sealed with special
mastic or tape.
33 4.2.0 Waterproofing: The single most critical area for
waterproofing construction is the below-grade
foundation wall.
Figure 28: Applying waterproofing materials
Do not place backfill for 24 to 48 hours after
application.
4.2.1 Waterstops are thin sheets of rubber, plastic …
water through the joint. PVC water stops may be
used for installations in … and roofs.
34 4.2.4 Air Infiltration Control: In addition to
insulation, the exterior sheathing of a structure
should be covered to prevent wind … To achieve
maximum energy efficiency in a structure; air
infiltration must be strictly controlled.
The material is usually furnished in rolls in
various sizes from 18” wide 10’ wide and lengths
from 1000’ to 200”
1 Exam Prep – Study Guide for Commercial Carpentry 6
1 Exam Prep Tab Page # Section Reason/Highlight
Nails with large heads, nails, or screws with
plastic washers or 1”-wide staples may be used to
secure the wrap to wood … gypsum board.
35-36 House or building wrap is generally installed as
follows: - Step 1: Secure the wrap to the corner at 12” to 18”
intervals.
- Step 2: Secure the wrap vertically at 12” to 18”
intervals on each stud.
- Step 3: make sure that the bottom edge … 6” to
12”.
- Step 4
- Step 5
- Method 1: Uninstalled Windows/Doors
- Method 2: Window and Doors with Flanges
- Step 6
37 Figure 36: Installing flashing around an opening
Estimating Insulation 39 5.0.0 Perform the following steps to calculate the
amount of required insulation material:
Note: Know all formulas and calculations for
each step.
- Step 1:
- Step 2:
- Step 3:
- Step 4:
40 Table 6: Typical Insulation Coverage for Various
Types of Packaging and R-Values.
Exterior Finishing 59 1.0.0 Exterior Finishing Safety: Work shoes are
probably the most important item of clothing.
1.1.0 Working at Elevations: OSHA subpart M
requires fall protection … that are 6’ or higher
than the ground or level below it.
1.1.1 Ladders: general guidelines for the safe use of
ladders are as follows: 14 bullets.
1.1.2 Scaffolds: Per OSHA if a scaffold is more than
10’ high, it must be equipped with top rails …
arrest systems.
1 Exam Prep – Study Guide for Commercial Carpentry 7
1 Exam Prep Tab Page # Section Reason/Highlight
61 1.2.0 Tools, Equipment, Materials, and Related
Safety
63 1.2.3 Material safety: SDSs are used to properly
manage, use, and dispose of hazardous materials
safely.
For housewrap, a 6” to 12” lap at 3’ lap from both
sides is usually recommended.
64 2.0.0 The primary purpose of any exterior finishing is
to provide protection from the elements.
At corners a 3’ lap from both sides is usually
recommended.
64-65 2.1.0 Wood Siding: Siding, casing, box, finish, ring-
shank, or spiral-shank … The siding nail is
considered the best nail for wood siding except in
high-wing areas.
66 Figure 5: Common wood siding styles
68 Figure 6: Commonly used nails
2.1.1 Beveled Siding: Beleveled siding is available in
plain or bungalow and rabbeted. Rabeted beveled
siding provides a somewhat snugger lap … then
beveled siding.
2.1.2 Board-and Batten Siding: The most widely used
is the vertical placement of wide boards with the
joints covered by narrow battens.
69 2.1.4 Board-on-Board Siding: For board-on-board
siding, apply the under boards first spacing them
to allow a 1 1/2” overlap by the outer boards at
both edges … with one 8d nail per bearing.
69-70 Drive 10d siding nails so that the shanks clear the
edges of the underboards by approximately ¼”.
70 2.1.5 Tongue and Groove Siding: On the exterior
elevations of the construction drawings … The
most common angle is 45 degrees.
1 Exam Prep – Study Guide for Commercial Carpentry 8
1 Exam Prep Tab Page # Section Reason/Highlight
Figure 13: Tongue-and-groove siding.
Figure 14: Styles of shiplap siding.
71 2.1.6 Shiplap Siding: Plain shiplap siding can be
installed, vertically, horizontally, or diagonally.
Any shiplap siding that is 6” or narrower can be
face-nailed 1” from the bottom … The general
rule is that nails should be long enough to
penetrate at least 1 ½” into the studs, or the studs
and wood sheathing combined.
2.1.7 Red cedar or cypress is normally used to make the
shingles or shakes.
72 2.1.9 Plywood Siding: Because of its strength,
plywood is nailed directly to the studs,
eliminating the need for sheathing.
2.2.0 Vinyl and Metal Siding
73 2.2.1 Vinyl and Metal Siding Components
74 2.3.0 Fiber-Cement Siding: Like wood siding, it is
available in single-lap siding ranging from 6” to
12” wide and as vertical panels.
The recommended finish is 100 percent acrylic
latex paint over alkali-resistant primer.
2.3.6 Header Assembly: The two types of headers that
are most commonly built from … A third type is
a steel angle in shape of an L-header.
2.4.0 Veneer Finishes
75 2.4.1 Stucco (Cement) Finishes:
- Scratch coat
- Brown coat
- Finish coat
77 2.5.0 Specialty Finishes: In most cases, the substrate is
a fiber-cement or a fiber-glass coated …
nonstructural sheathing.
1 Exam Prep – Study Guide for Commercial Carpentry 9
1 Exam Prep Tab Page # Section Reason/Highlight
78 2.6.0 Flashing
81 3.0.0 Installing Exterior Finishing Materials
3.1.0 Preparing Surfaces
3.2.0 Furring and Installation Techniques
83 3.3.0 Establishing a Straight Reference Line
3.4.1 Installing Beveled Siding: Follow these
guidelines to install the siding.
Make sure the story poke is plumb before
marking the wall.
92 3.5.2 Installing Outside Corner Posts: The siding is
later butted into the corner and then nailed into
place … 1/16” to ¼” space between the post and
the siding for expansion purposes.
95 3.5.6 For precision cutting, a power saw is the most
convenient to use.
102 3.6.0 Installing Cement Siding
3.7.0 Installing Cornice
107 3.7.1 Aluminum or Vinyl Fascia and Soffits: A
lookout is the horizontal siding member used to
support the overhanging portion of a roof.
112 4.0.0 Estimate Exterior Finish Materials
113 4.1.3 Estimating Nails for Siding
Table 4: Board-on-Board Lumber
Requirements
Cold-Formed Steel 123 Cold Formed Steel Framing
Framing
130 1.1.0 Cold Formed Steel Framing Safety Guidelines:
Cold Formed Steel Framing Safety Guidelines are
as follows: 4 bullets.
1 Exam Prep – Study Guide for Commercial Carpentry 10
1 Exam Prep Tab Page # Section Reason/Highlight
132 1.2.1 Identification of Framing Materials: The Steel
Stud Manufacturers Association representing
more than 80 percent of all … The third final part
of the designator is the mil thickness expressed in
1/1000.
Table 1: Minimum Base Steel Thickness of
Cold-Formed Steel Members
133 1.3.0 Steel Framing Tools and Fasteners
- Screwgun: Speed range 0 to 2,500
- C-clamp
141 1.4.3 Studs: Determine the number of studs needed,
use the following procedure: Step 1, Step 2
142 2.1.1 In-line Framing: Cold-formed steel framing
members are aligned vertically so that the … stud
web is within ¾” of the center line of the web
joist below.
146 2.2.1 Steel Curtain Walls
149 2.3.1 Layout: Steel framing is typically spaced at 24”
on center to take full advantage of the framing
member.
159 3.1.0 Steel Floor and Roof Assemblies
160 3.2.0 Ceiling Systems: The furring channel is commonly
clipped or wire tied, perpendicular to the underside
of the U-channel at appropriate intervals.
Drywall Installation 171 Drywall Installation
179 1.0.0 Drywall Assembly Components
1.1.0 Types of Gypsum Products: Various
thicknesses of drywall are available in regular,
Type X , water-resistant, and architectural boards:
Table 1: Types and Uses of Drywall
185 1.2.2 Screws
1 Exam Prep – Study Guide for Commercial Carpentry 11
1 Exam Prep Tab Page # Section Reason/Highlight
186 1.2.3 Adhesives
194 2.1.0 Fastening Schedules: Fastening schedules
provide information about the proper spacing of
fasteners.
194 2.2.0 Tools Used for Drywall Application
- Rasp
- Drywall saw
- Jab saw
- Light box cutter
196 2.3.0 Sound-isolation Construction
202 2.4.0 Installing Drywall: A butt joint is where two
sheets of wall board with untapered sides meet …
A flat joint is the intersection of two bevel-edged
wall boards.
207 2.5.0 Special Applications
209 3.1.0 Single-ply application: Multi-ply systems have
two or more layers of drywall to increase …
thereby reducing the number of fasteners.
212 3.2.2 Fire-stopping
214 Endothermic materials block heat by releasing
chemically bound water, which causes them to
absorb heat.
These ratings are as follows:
- F rating
- FT rating
- FH rating
- FTH rating
215 3.3.1 Attaching the base ply to metal framing or
Furring: Base-ply drywall is normally attached
to steel framing … 5/16” longer than the
thickness of the board.
217 3.4.0 Prioritizing Walls: In general, the overall
priority of wall construction is as follows, from
highest priority:
1 Exam Prep – Study Guide for Commercial Carpentry 12
1 Exam Prep Tab Page # Section Reason/Highlight
218 Table 4: Fastening Materials Required for
1,000 Square feet of Drywall.
4.2.0 Fasteners: For single layer application 16” OC,
approximately 1,000 screws … for ¼” wallboard
to 7 pounds of nails for 1 ¼” wallboard.
Reinforcing Concrete 229 Reinforcing Concrete:
238 1.1.0 Resistance of Forces by Reinforcing Bars:
Reinforcing bars are most effectively used in the
following applications. 2 bullets
240 Column ties and column spirals act to prevent
buckling.
241 1.2.2 Bridges:
- A beam bridge is commonly used for short
spans. If a single span is used, the end supports
are called abutments or end bents.
- A rigid-frame bridge
- The arch bridge
242 1.3.0 Post Tensioned Concrete: There are two types
of post tensioning: bonded and unbounded. A
tendon consists of a bar or strand, along with …
and sheath. The strand is typically made from
steel wires that are twisted together.
245 2.0.0 Working with Reinforcing Steel: ACI 318-95
includes the following guidelines for concrete
cover: 6 bullets.
246 2.1.0 General Safety Precautions: The following
general safety precautions apply to the placing
and tying of reinforcing bars.
246 2.2.0 Reinforcing Bars: The standard configuration for
reinforcing bars is the deformed bar.
Deformed bars are designated by a number in 11
standard sizes.
1 Exam Prep – Study Guide for Commercial Carpentry 13
1 Exam Prep Tab Page # Section Reason/Highlight
Grade 420 is the most commonly used rebar. Bars
are normally supplied from the mill bundled in
60’ lengths.
Table 1: ASTM Standard Metric and Inch-
Pound Reinforcing Bars
248 Figure 17: Reinforcing bar identification
249 Table 3: Reinforcing Bar Grades
2.3.2 Fabricated Bars: Each dimension of the
standardized bar bends has been assigned a letter.
250 Figure 18: Typical bar bends
251 2.3.4 Bar-List Information: These types are
as follows:
252 Table 4: Standard Hook Specifications
253 2.3.7 Tolerances in Fabrication: The usual tolerances
are as follows:
- Straight bars
- Hooked bars
- Truss bars
- Spirals
- Column ties
Each bundle of bars should contain bars of one
size … Bundles are generally secured by wraps of
#9-gauge wire spaced 10’ to 15’ apart.
258 2.4.3 Other Types of Bar Supports: These types are
as follows:
- Straight Bars
- Heavy bending bars
- Light bending bares
- Special bending bars
260 2.5.0 Welded-Wire Fabric Reinforcement
262 2.5.2 Deformed Welded-wire fabric Reinforcement:
The wires are manufactured from D-1 to D-45 …
is replaced by a D or an MD.
1 Exam Prep – Study Guide for Commercial Carpentry 14
1 Exam Prep Tab Page # Section Reason/Highlight
Table 6: Plain Wire Sizes
263 Table 7: Common styles of Plain Welded-Wire
Fabric
Table 8: Deformed Wire Sizes
265 3.1.0 Cutting Rebar: Rods up to ½” in diameter may
be cut quickly and easily using manual rebar
cutters.
265 3.2.0 Bending Rebar: Reinforcing bars should be bent
cold. Rebar may be bent using a tool called a
hickey bar.
268 4.1.0 Tying and Splicing Reinforcing Steel: The wire
used for tying rebar is usually 13-gauge black-soft
annealed wire.
A general rule of thumb for tying preassembled
mats … 25 percent to 50 percent unless the job
specifications require otherwise.
269 Figure 36: Types of Ties
271 4.2.1 Placing Bars in Footings and Foundations:
The function of a footing is to transmit the
concentrated load of a structure to the ground at
pressure that is a safe and not willing to settle the
structure.
273 4.2.2 Placing Bars in Walls: The single-curtain wall is
a type of reinforced concrete wall in which a
single layer reinforcing steel is placed … A
retaining wall which may be either a single-
curtain or double-curtain wall, is used to hold
earth or fill in place.
275 4.2.3 Placing Bars in Columns
279 Figure 53: Standing column ties
280 Figure 54: Closed column ties
1 Exam Prep – Study Guide for Commercial Carpentry 15
1 Exam Prep Tab Page # Section Reason/Highlight
281 To place reinforcing steel in beams, proceed as
follows: Step 1 -5.
Trenching and 295 Trenching and Excavating
Excavating
301 1.1.0 Foundation Excavation Safety: A registered
professional engineer must design protection for
excavations more than 20’ deep.
302 The soil cohesiveness will determine the angle
of the slopes and the depth of each tier.
303 1.2.0 Trench Safety: One cubic yard of earth weighs
approx 2,700 pounds.
306 1.2.2 Guidelines for Working In and Near a Trench
309 1.2.4 Trench Failure: There must be minimum of 2’
between the trench wall and the spoil pile.
310 1.3.0 Shoring, Shielding, and Sloping Systems
313 Following these safety guidelines when using a
trench shield:
314 Table 3: Maximum Allowable Slope
317 2.1.1 Classifications: - Type A soils are cohesive soils
that have a compressive strength least 1.5 tons
open square foot.
- Type B
- Type C
318 2.2.1 Soil Density: The most important part of a
building site is …. Ratio of a soils weight to its
volume.
318 2.2.3 Excavating Soil: Soil is measured in cubic units
with cubic yards being the most common.
319 Table 5: Loadbearing Capacity
1 Exam Prep – Study Guide for Commercial Carpentry 16
1 Exam Prep Tab Page # Section Reason/Highlight
319-320 2.3.0 Fill volume falls into the following three
categories:
- Native
- Loose fill
- Banked fill
321 3.0.0 Compacting and Testing Soil: Compaction is
usually specifically addressed in the construction
specifications.
Vibratory equipment provides vibration and
pressure for compaction.
323 3.1.0 Moisture Content: Soil is commonly sprayed
with water as it is being placed in excavation so it
may be compacted to the specified density.
323 3.2.0 Compacting Soil by Layers
323 3.3.0 Checking Quality: There are tests that will
determine if the compaction performed meets the
test specifications. There are three types of tests:
the sand cone test, nuclear testing, and electrical
density testing.
324 3.3.1 Sand Cone Test: Many engineers consider this
the most accurate testing method.
3.3.2 Nuclear Testing
3.3.3 Electrical Density Testing
326 4.0.0 Surface Water, Groundwater, and Rock
Mitigation: Surface Water and Ground water
must be mitigated for the safety of workers.
327 4.1.1 Surface Water: Erosion is the eating away soil
by water or wind, while sediment refers to soil
that has been moved from its original place by
wind, water, or other means.
331 4.2.0 Rock Mitigation: Block holding is used for very
large boulders.
1 Exam Prep – Study Guide for Commercial Carpentry 17
1 Exam Prep Tab Page # Section Reason/Highlight
Vertical Formwork 347 Vertical Formwork: At one time concrete forms
were built in place on the job site and torn down
after a single use.
353 1.0.0 Concrete Wall Forms: At one time, concrete
forms were built in place on the job site and torn
down after a single use.
353 1.1.0 Planning Formwork: Formwork represents
one-third to one-half of the total installed cost of
concrete.
355 1.2.1 Parts and Accessories:
- Strongback
359 1.4.0 Gang Forms: Final gang form may be 40’ to 50’
wide.
362 2.1.0 Curved Wall Forms
365 2.2.0 Framing Wall Openings: A vibrator hole is
needed in the lower spreader of a window buck to
allow the concrete below the buck to be properly
vibrated.
369 3.1.0 Assembling Forms: The formwork is first laid
out in accordance with the supplier’s shop
drawings.
369 3.2.0 Setting Forms: The following is the typical
sequence: Step 1 – 13.
372 4.0.0 Column Forms: Round column forms are made
of fiber, fiber-glass … or steel.
372 4.1.1 Fiber Forms
377 Figure 28: Typical spacing of round-column
form clamps
378 Figure 29: Column form clamps
379 5.0.0 Vertical Slipforming: A slip-form system
consists of the form itself, as well as upper and
lower work decks.
1 Exam Prep – Study Guide for Commercial Carpentry 18
1 Exam Prep Tab Page # Section Reason/Highlight
379 5.1.0 Slip-form Component
380 Figure 32: Slip form assembly
383 6.0.0 Stair-Forms: The following are examples of the
IBC requirements: 7 bullets
The following are examples of the IBC
requirements: 7 bullets
384 Figure 37: Basic stair layout
389 7.0.0 Vertical Architectural and Specialty Forms:
390 7.2.0 Creating Textured Surfaces
390 7.3.0 Insulating Concrete Forms: ICFs which remain
in place after the concrete has hardened … foam
panels.
Tilt-Up Wall 401-402 Tilt-up Wall Panels: While each tilt-up Panels
construction project is unique … is as follows:
Step 1 – 16.
407 1.0.0 Overview of Tilt-up Walls
408 1.1.0 Preparing the Casting Bed: A release agent
must be sprayed on the casting bed before any
forming work is done… should not be left more
than the manufacturer dry time.
409 1.2.0 Forming Tilt-up Panels
410 Figure 6: Tilt-up panel layout drawing
Release Agent Test: To tests for adequate
application of the release agent … Water will
bead as it does on a wax finish if the release agent
is correctly applied.
413 1.4.0 Placing Reinforcement: In tilt-up construction
reinforcement is used to limit cracking and
bending stresses.
To avoid rust that could stain the tilt-up panel.
1 Exam Prep – Study Guide for Commercial Carpentry 19
1 Exam Prep Tab Page # Section Reason/Highlight
Rebar or welded-wire fabric should be placed on
plastic chairs or on metal chairs with plastic tips
in order
414 1.5.0 Positioning Inserts and Embedments: Inserts
should be placed so they are about 1/8” below the
surface of the concrete.
415 1.6.0 Placing and Finishing Concrete
416 Figure 20: Applications of form inserts
417 In cold-weather, where the air temperature is
consistently below 40 F, use heating equipment to
protect the concrete.
Concrete Slump: Concrete slump for tilt-up
panels should be in the 4” to 5” … for every
gallon of water added to a cubic yard of concrete.
419 2.1.2 Power Hyphen Tool Safety
420 2.1.3 Erecting and Bracing Safety: Prior to any panel
erection activities, a site specific safety meeting
should be conducted.
2.2.0 Erecting and Bracing Panels:
422 Panels containing lintels usually require
additional strongbacks to the panel before it is
raised … support is obtained by attaching
additional support during the lift …
424 Figure 34: Cross section of a strongback
429 How to Use Coil Face Insert
430 How to Use A Ground Release System
431 How to Remove the Ground Release Plastic
Recess Plug
Site Layout II 437 Site Layout II - Angular Measurement
442 Length Conversion Multipliers
1 Exam Prep – Study Guide for Commercial Carpentry 20
1 Exam Prep Tab Page # Section Reason/Highlight
446 3-4-5 Rule
2.2.1 Right Triangle Calculations
453 3.0.0 Laser Instruments
457 3.5.0 Laser Instrument Safety
458 4.0.0 Site Layout Instruments and Equipment
474 8.0.0 Measuring Horizontal and Vertical Angles
Welding (Elective) 497 Welding (Elective)
500 1.2.0 Welding
501 2.0.0 Safety
2.1.0 Personal Protective Equipment
523 5.3.0 Performing Cutting Procedures
526 6.0.0 Shielded Metal Arc Welding
533 7.0.0 Shielded Metal Arc and Welding Electrodes
534 The meaning of marking are: 4 bullets
540 8.0.0 The Welding Process
553 10.3.0 Gas Metal Arc Welding
557 11.0.0 Welding Symbols
Specialized Materials and 569 Specialized Materials and Techniques
Techniques
577 1.1.0 Installing Pier-and-panel Barrier Walls
578 1.2.0 Installing Continuous Walls: To function
properly this wall must be supported on a
continuous foundation usually made of reinforced
concrete.
1 Exam Prep – Study Guide for Commercial Carpentry 21
1 Exam Prep Tab Page # Section Reason/Highlight
581-582 2.1.0 Understanding Arch Design: Figure 11
shows the various parts of an arch. 14 bullets.
583 2.2.1 Semicircular Arches
585 2.3.3 Laying the Arch Brick
589 2.4.3 Laying the Jack Arch in Mortar
591 3.1.0 Using Acid Brick: Acid brick structures do not
resist tension well.
592 3.2.2 Membranes: Membranes act as barriers between
the chemical resistant masonry units and the
supporting substrate.
Membranes fall into two classes: true and semi
membranes
595 3.3.5 Expansion Joints: There are basically three
types of expansion joint materials used with acid
brick linings: 3 bullets
598 4.1.0 Understanding Refractory Brick: The clays
used for making firebrick are flint fireclays …
and kaolin.
602 4.2.2 Floors and Hearths: Concrete loses considerable
strength when temperatures increase above 750 F.
604 4.3.0 Curing and Heating up Refractory Brick: The
best temperature range for laying and curing
refractory work is 60 to 90 F.
After curing… increase the temperature to about
250 F.
609 5.1.3 Laying Structural Glazed Tile
610 Structural Glazed Tile Nomenclature
611 5.2.1 Properties
1 Exam Prep – Study Guide for Commercial Carpentry 22
1 Exam Prep Tab Page # Section Reason/Highlight
615-616 6.1.0 Understanding Applications and Uses of Glass
Block: The three categories of glass block are:
- Functional
- General purpose
- Decorative
616 6.2.0 Understanding Variations of Glass Blocks: A
¼ inch mortar joint is standard with glass block.
621 6.3.3 Curved-panel Construction
Rigging Equipment 633 Rigging Equipment
641 Figure 4: Round pin and screw pin shackle
Figure 5: Spacers used with a shackle to keep it
hanging.
648 Table 1: Example of a Wire Rope Sling Capacity
Table
650 Taglines
656 8.0.0 Jacks
Rigging Practices 669 Rigging Practices
675 2.1.0 Verbal Modes of Communication
2.2.0 Nonverbal Modes of Communication
688 3.6.0 Load-Handling Safety
700 Table 3: ASTM Standard Metric and Inch
Pound Reinforcing Bars
Index 713 Index