1 Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 Page 1 Revised 2009 and Microsoft Project 2010 training course Administration Evacuation Timings, meals and facilities Mobile phones and emails Introductions Page 2 Introductions Your Name Experience in scheduling software PRINCE2 experience What you expect from the course Course attendance sheet. Course Agenda Course Agenda Day 1 Modules Day 1 Modules 1 Introduction Introduction 2 Creating a Project Schedule Creating a Project Schedule 3 Navigating and Setting the Options Navigating and Setting the Options 4 Creating Projects and Templates Creating Projects and Templates 5 Defining Calendars Defining Calendars Page 3 3 6 Adding Tasks Adding Tasks 7 Organizing Tasks Using Outlining Organizing Tasks Using Outlining 8 Formatting the Display Formatting the Display 9 Adding Task Dependencies Adding Task Dependencies 10 10 Network Diagram View Network Diagram View 11 11 Constraints Constraints Course Agenda Course Agenda Day Day 2 Modules 2 Modules 12 12 Filters Filters 13 13 Tables and grouping Tasks Tables and grouping Tasks 14 14 Views, Details Views, Details 15 15 Printing and Reports Printing and Reports 16 16 Tracking Progress Tracking Progress Page 4 4 17 17 Creating Resources and Costs Creating Resources and Costs 18 18 Assigning Resources and Costs to Tasks Assigning Resources and Costs to Tasks 19 19 Resource Optimization Resource Optimization 20 20 Updating Projects with Resources. Updating Projects with Resources. Module 1 – Introduction Introduction Topics: Purpose of the Course Required Background Knowledge Purpose and Aims of Planning Definition and Elements of a Plan Page 5 Plan Supporting Documents PRINCE2 Plan Levels Programme Planning in Microsoft Project Controlling a Project Organisation Responsibilities Planning Metrics and the Planning Cycle PRINCE2 Processes supported by Microsoft Project. Purpose of the course Provide a method for planning, scheduling and controlling projects using Microsoft Project, In a project environment using the PRINCE2 2009 methodology, Page 6 Up to an intermediate level.

101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

Embed Size (px)

Citation preview

Page 1: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

1

Welcome to theEastwood Harris Pty Ltd

PRINCE2TM

Revised 2009

Page 1

Revised 2009and

Microsoft Project 2010training course

AdministrationEvacuation

Timings, meals and facilities

Mobile phones and emails

Introductions

Page 2

IntroductionsYour Name

Experience in scheduling software

PRINCE2 experience

What you expect from the course

Course attendance sheet.

Course AgendaCourse AgendaDay 1 ModulesDay 1 Modules11 IntroductionIntroduction22 Creating a Project ScheduleCreating a Project Schedule33 Navigating and Setting the OptionsNavigating and Setting the Options44 Creating Projects and TemplatesCreating Projects and Templates55 Defining CalendarsDefining Calendars

Page 3

3

66 Adding TasksAdding Tasks77 Organizing Tasks Using OutliningOrganizing Tasks Using Outlining88 Formatting the DisplayFormatting the Display99 Adding Task DependenciesAdding Task Dependencies1010 Network Diagram ViewNetwork Diagram View1111 ConstraintsConstraints

Course AgendaCourse AgendaDay Day 2 Modules2 Modules1212 FiltersFilters1313 Tables and grouping TasksTables and grouping Tasks1414 Views, DetailsViews, Details1515 Printing and ReportsPrinting and Reports1616 Tracking ProgressTracking Progress

Page 4

4

1717 Creating Resources and CostsCreating Resources and Costs1818 Assigning Resources and Costs to TasksAssigning Resources and Costs to Tasks1919 Resource OptimizationResource Optimization2020 Updating Projects with Resources.Updating Projects with Resources.

Module 11 – IntroductionIntroductionTopics:

Purpose of the CourseRequired Background KnowledgePurpose and Aims of PlanningDefinition and Elements of a Plan

Page 5

Plan Supporting DocumentsPRINCE2 Plan LevelsProgramme Planning in Microsoft ProjectControlling a ProjectOrganisation ResponsibilitiesPlanning Metrics and the Planning CyclePRINCE2 Processes supported by Microsoft Project.

Purpose of the courseProvide a method for planning, scheduling and controlling projects using Microsoft Project,

In a project environment using the PRINCE2 2009 methodology,

Page 6

Up to an intermediate level.

Page 2: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

4

Purpose of Planning The ultimate purpose of planning is to build a model that allows you to predict which tasks and resources are critical to the timely completion of the project, then:

Strategies may then be implemented to ensure that

Page 19

Strategies may then be implemented to ensure that these tasks and resources are managed properly, thus ensuring that the project will be delivered both On Time and Within Budget.

Planning aims to: Identify the Products and Tasks required to deliver a project,Evaluate different project delivery methods,Identify and optimize the use of resources,Optimize time and evaluate if target dates may be met ,Id tif i k d t i iti

Page 20

Identify risks and set priorities,Provide a baseline plan against which progress is measured,Communicate the plan to all stakeholders, including what is to be done, when and by whom,Provide early warning of potential problems and enable proactive and not reactive action to be taken andAssist management to think ahead and make informed decisions.

Planning helps to avoid or assist in evaluating:

Increased project costs or reduction in scope and/or quality,Additional change over and/or operation costs,Extensions of time claims,L f li ’

Page 21

Loss of your client’s revenue,Contractual disputes and associated resolution costs,The loss of reputation of those involved in a project, andLoss of a facility or asset in the event of a total project failure.

Definition of a PlanPRINCE2 defines a plan as a proposal for doing or achieving something which specifies the what, when, how and by whom.

A Project Plan must at all times be able to deliver the expected benefits identified in the Business Case.

All plans m st ha e the app o al and commitment of

Page 22

All plans must have the approval and commitment of all the appropriate management levels.

A plan is therefore not just a Microsoft Project Gantt Chart (bar chart), although a Gantt Chart is an important output of the planning process.

Elements of a Plan – the PRINCE2 Definition

Products to be produced, both Specialist and ManagementTasks required to produce the ProductsTasks to validate the Products’ qualityResources required to produce the Products including

Page 23

Resources required to produce the Products, including management and qualityThe relationships or dependencies between the Products and TasksExternal dependencies that will influence Product creationTimings for the ProductsControl points to measure progressTolerances in time, cost and any other agreed variable.

Plan LevelsPRINCE2 defines three levels of plans below a corporate or programme plan:

Project

Stage

T

Page 24

Team

PRINCE2 also defines 5 types of plans as per the picture on the next slide, (which was created using the Microsoft Project Network Diagram function).

Page 3: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

7

Four modes or levelsThere are four levels in which planning and scheduling software may be used.

Planning Controlling

Page 37

Without LEVEL 1 LEVEL 2

Resources Planning without Resources

Tracking progress without Resources

With LEVEL 3 LEVEL 4

Resources Planning with Resources

Tracking progress with Resources

Understanding Your ProjectBefore creating a project schedule in Microsoft Project, it is important to understand the following types of documents:

A PRINCE2 project should have a Project Mandate to commence the Starting up a Project process

Project scope

Functional specification

Page 38

Requirements baseline

Contract documentation

Plans and drawings

Project execution plan

Contracting and purchasing plan

Equipment lists

Installation plan

Testing plan.

Level 1 – Planning Without ResourcesCreate the project

Define the calendars

Defining the WBS and other codes

Add tasks

Add the logic & constraints

Page 39

Add the logic & constraintsMandatory dependencies

Discretionary dependencies

External dependencies

Schedule the project and

Consider contingent time.

Creating Projects

Project Name

The Project Start Date (and perhaps the Finish Date)

It would be helpful to know other important information

To create the project in Microsoft Project, you will require the following information:

Page 40

It would be helpful to know other important information such as:

Client name, and

Other project data such as location, project number and stakeholders.

Defining the CalendarsThe finish date and time of a task is calculated from the start date and time plus the task duration over the calendar assigned to the task

Page 41

the task.

Microsoft Project Options for Product Based Planning

Microsoft Project was not entirely suitable to complete Product Based Planning with the older version of PRINCE2, but PRINCE2 2009 has relaxed some of the requirements making using Microsoft Project easier,

Page 42

We will make some suggestions on how to use Microsoft Project to create a PBS next,

Other option are:To invest in PRINCE2 planning software such as Change Aide, or

Use a word processor or spread sheets and indent the text to create a hierarchical structure, or

Use Microsoft’s OBS feature in Word or Excel.

Page 4: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

10

Task Early Start ConstraintA task will no longer start on the Data Date When a Start No Earlier Than constraint is assigned

This is more commonly known as an Early Start constraint.

Page 55

Start constraint.

Task Late Finish ConstraintThis picture shows a Finish No Later Than constraint assigned 4 days earlier than the calculated finish date

Thus Negative Float is created, representing the amount of time that needs to be caught up

Page 56

the amount of time that needs to be caught up

This is more commonly known as a Late Finish constraint.

Task Late Finish ConstraintThis schedule has a Finish No Later Than constraint assigned after the calculated finish dateThe Total Float is NOT calculated to the constraint date when the constraint date it is LATER the calculated Early Finish

Page 57

LATER the calculated Early FinishPositive Total Float is NOT created and a critical path of zero days float is maintained.

Risk Analysis and TolerancesAt this point in time you should consider conducting a Risk Analysis and adding Risk Mitigation tasks

Consider what Time Tolerances should be assigned and these may be added as tasks

Now print and issue the plan for review and approval

Page 58

Now print and issue the plan for review and approval.

Level 2 – Monitoring Progress Without Resources

Set the Baseline

Tracking and record progress

Entering in Actual Start Dates, Percent

Page 59

g ,Complete and Actual Finish dates

Take corrective action.

Level 3 – Scheduling WithResources and Costs

Are you estimating or planning for control?

Consider the balance between the number of Tasks and Resources

Page 60

Creating and using Resources

Creating and using Expenses

Task Type and Effort Driven option

Resource Optimization.

Page 5: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

13

Module 4 - Creating Projects and TemplatesTopics:

Starting Microsoft Project 2010

Creating a Blank Project

Opening an Existing Project

Page 73

Re-opening a Project

Creating a Project Template

Creating a New Project from a Template

Saving Additional Project Information

Using the Alt Key and Keystrokes to Access Commands

Saving a Project Closing Microsoft Project

Workshop 2 - Creating a Project.

Starting Microsoft Project 2010

When opening Microsoft Project 2010, you will be presented with a blank project, named Project1, which you may start working with immediately.

Page 74

Creating a Blank Project A blank project may be created from the New Project pane, which is displayed by:

Keying in Ctrl+N, or

Selecting File, New

Then clicking on Blank Project

A new project will be displayed and the project name

Page 75

A new project will be displayed and the project name is shown at the top center of the screen.

At this point the Project Start date is normally set in the Project Information form:

Current Date: – This field defaults to today’s date,

Status Date: – This is an optional field used when updating a project,

Calendar: – This is the project Base calendar that is used to calculate the durations of all tasks.

Opening an Existing Project and Re-opening a Project

To open an existing project display the Open form by selecting:

File, Open, or

Ctl+O

Th N P j t f i ti f b d

Page 76

The New Project from existing form may be used to open an existing project:

Select File, New, New from existing project,

Then select the file you want to open from the Open form,

Selecting File, Recent will show a list of recently opened project files.

Project TemplatesProject templates allow organizations to create standard project models containing default information applicable to the organization,

Create a template by saving a project, with or without tasks, in Template (*.mpt) format,

This template will be available when you select File, New,

Page 77

This template will be available when you select File, New, My templates,

To create a new project from a template:Select File, New and there are template location options:

My templates allows you to open templates on your computer and is covered in the next paragraph,

Recent templates takes you to your recently used templates,

Office.com Templates, this will allow you to access Microsoft’s templates.

Saving Additional Project Information

Often additional information about a project is required to be saved with the project such as location, client and type of project,

Page 78

This data may be saved in the File, Info, Project Information, Advanced Properties form and these fields may be inserted into reports.

Page 6: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

16

Module 66 – Adding TasksAdding TasksTopics:

Adding New Tasks

Understanding Change Highlight

Copying and Pasting Tasks

Milestones

Page 91

Reordering Tasks by Dragging

Sorting Tasks

Task Information Form

Elapsed Durations

Indicators Column

Assigning Calendars to Tasks

Workshop 4 - Adding Tasks.

Task DefinitionTasks should be well-defined, measurable pieces of work with a measurable outcome. Task descriptions containing only nouns such as “Bid Document” have confusing meanings,The limit for task names is 254 characters, but try to keep task descriptions meaningful yet short and concise so they are easier to print,

Page 92

y p ,When tasks are created, they are normally organised under the WBS which is created using Summary tasks,Normally the WBS would be added first but it is simpler to teach Microsoft Project by showing how tasks are added first and then demonstrate the Creation of Summary Tasks using Outlining,Tasks may also be organized under other coding structures such as Task Codes or Custom Fields.

Adding New Tasks Manually Scheduled tasks will not be covered in detail in this book,

This course will concentrate on the aspects required to produce a Critical Path schedule assuming all tasks are Auto Scheduled,

Page 93

,

The instructor will demonstrate how to add new tasks and insert new tasks between existing tasks.

Understanding Change HighlightNew tasks mat have Start and/or Finish dates highlighted,

This is due to Change Highlighting that highlights any changed dates and durations as a result of an edit, addition or deletion of another task,

Remove the highlighting produced by the last change

Page 94

by:Pressing the F9 key which will also recalculate the project, or

Saving the project, or

Entering a value into a changed cell twice,

Your should add the Display Change Highlighting button to the Quick Access Toolbar to hide/display the highlighting.

Copying and Pasting Tasks Tasks may also be copied from another project or copied from within the same project using the normal Windows commands such as right-click Copy andPaste or Ctrl+C and Ctrl+V,

Tasks are always inserted when pasted,

Page 95

y p ,

Note: Copy and Pasting Cells will always paste over existing data.

MilestonesA Milestone normally has a zero duration and is used to mark the start or finish of a major event,

A Milestone is a Start Milestone when it has no predecessors and is scheduled at the start of a work day,

Page 96

A Finish Milestone when it has predecessors and is scheduled at the end of a work day,

To create a Milestone either:Assign a task a zero duration, or

Click on the Task, Insert group, Insert Milestone button.

Page 7: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

19

Module 88 – Formatting the DisplayFormatting the DisplayTopics:

Formatting the ColumnsFormatting Time UnitsFormatting the BarsRow Height

Page 109

Format FontsFormat TimescaleFormat GridlinesFormat Links, Dependencies, Relationships, or Logic LinesFormat ColorsWorkshop 6 - Formatting the Bar Chart.

Formatting the DisplayThis chapter covers the formatting topics, whichare used to format the on-screen display and whichare also reflected in print preview and printouts.

Page 110

Formatting the ColumnsThe instructor will explain the following:

Format Columns group menu

Inserting Columns

Deleting Columns

Page 111

Adjusting the Width of Columns

Moving Columns

Formatting Columns

Using the Table Function.

Formatting Time UnitsSelect File, Options, Advanced, Default options for this project:

The Display options for this project: always specifies the time units, for example day, dy or d.

Uncheck the Add space before label check box to remove a space between the value and label in date

Page 112

columns which allows a narrower Duration column to be displayed.

Formatting the BarsMicrosoft Project has several options for bar formatting:

All the bars may be formatted to suit user definable parameters, or

Individual bars may be formatted,

The instructor will demonstrate:

Page 113

Formatting all task tars using the Bar Styles form,

Format Bar Styles group menu,

Gantt Chart Styles group menu,

Formatting Bars Using the Gantt Chart Wizard,

Note: Projects formatted with the Gantt Chart Wizard and projects created in earlier versions of Microsoft Project will have formatting that is incompatible with the Microsoft Project 2010 Format, Bar Styles group buttons.

Row HeightRow heights may be adjusted to display text that would otherwise be truncated by a narrow column,

The row height of one or more columns may also be adjusted in a similar way to adjusting row heights in Excel, by clicking on the row and dragging with the mouse,

Page 114

mouse,

If all the rows are to be adjusted, then click on the Select All button above row number 1, to highlight all the tasks,

Microsoft Project 2010 has introduced a Wrap Text command found on the Format, Columns group, Column Settings, Wrap Text which automatically adjusts the row height to fit the text into the available column width.

Page 8: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

22

Lag Calendars and Elapsed LagsLags are calculated on the Successor Calendar (except with Microsoft Project 2002 and earlier which uses the Project Calendar),

Lags may be assigned Elapsed durations, therefore they will be based on a 24-hour, 7-day per week. To

Page 127

y , y penter an elapsed lag type an “e” before the unit, e.g. 5 ed:

Restrictions on Summary Task Dependencies

Dependencies may be made between summary tasks and detail tasks of a different summary task,

There is a built-in dependency between summary and detail tasks. Detail tasks may be considered as Start-to-Start successors and Finish-to-Finish predecessors

Page 128

pof their summary task,

Summary tasks may only have FS and SSdependencies; you will receive a warning message when you attempt to enter an illegal dependency,

Note: It is recommended that dependencies be maintained at the detail level. This is particularly important when moving tasks from one summary task to another since the dependencies will still be valid.

Displaying the Dependencies on the Gantt Chart

The dependencies may be displayed or hidden with the Layout form,

Select Format, Format group, Layout to open the Layout form and click on the radio button under the style you require,

Page 129

The color of the dependency line is inherited from the color of the predecessor task,

To display a Critical Path on the relationship lines you will need to format the bars as critical.

Adding DependenciesThe instructor will demonstrate the following methods of adding relationships:

Graphically Adding a Dependency

Using the Link and Unlink Buttons

Task Linking Using the Keyboard

Page 130

g g y

Adding and Deleting Predecessors with the Task Information Form

Predecessor and Successor Details Forms

Editing or Deleting Dependencies Using the Task Dependency Form

Autolink New Inserted Tasks or Moved Tasks

Editing Relationships Using the Predecessor or Successor Columns.

Scheduling the ProjectOnce you have your tasks and logic in place, Microsoft Project calculates the tasks’ dates/times,

More specifically, Microsoft Project has Scheduledthe project to calculate the Early Dates, Late Dates, Float and the Critical Path of the project,

To prevent the Automatic Calculation of your

Page 131

project’s start/end dates select File, Options, Schedule tab, Calculation, click on Off,

To calculate the schedule with the calculation mode set to manual:

Press the F9 Key, or

Click on the Select All button, top left-hand corner of the Gantt Chart view, right-click to open a menu and select Calculate Project, or

Add a Schedule Project button to the Ribbon or Quick Access Toolbar.

Workshop 7- Adding the Relationships

You have determined the logical sequence of tasks, so you may now enter the relationships.

Page 132

Page 9: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

25

Task Constraint TypesOther Constraint Types:

As Soon As Possible. This is the default for a new task. A task is scheduled to occur as soon as possible and does not have a Constraint Date.As Late As Possible. A Task will be scheduled to occur as late as possible and does not have any particular Constraint Date. The Early and Late dates have the same date. A task with this constraint has

Page 145

no Total Float and delays the start of all the successor activities. Start No Earlier Than. This constraint sets a date before which the task will not start. Start No Later Than. This constraint sets a date after which the task will not start. Must Start On. This constraint sets a date on which the task will start. Therefore the task has no float. The early start and the late start dates are set to be the same as the Constraint Date.Continued…..

Task Constraint Types continued

Other Constraint Types:

Must Finish On. This constraint sets a date on which the task will finish and therefore has no float. The early finish and the late finish dates are set to be the same as the Constraint Date.

Page 146

Finish No Earlier Than. This sets a date before which the task will not finish.

Finish No Later Than. This sets a date after which the task will not finish.

Deadline Date. This is similar to applying a Finish No Later Than constraint. This offers the only opportunity of putting a second constraint on a task.

Assigning ConstraintsConstraints may be assigned from:

Using the Task Information Form

Using the Constraint Type and Constraint Date Columns

Typing a Date into the Task Information or Details Form

Page 147

Using the Task Details Form

The instructor will now demonstrate each of these methods.

Deadline DateDeadline Date allows the setting of a date that a task should be complete,

A Deadline Date is similar to placing a Finish No Later Than constraint on a task and affects the calculation of the Late Finish date and float of the task,

Page 148

A second constraint such as an Early Start constraint may also be assigned to a task with a Deadline Date.

Task NotesIt is often important to note why constraints have been set. Microsoft Project has functions that enable you to note information associated with a task, including the reasons associated for establishing a constraint,

The Task Information form has a Note tab, which has some word processing-type formatting functions:

Page 149

has some word processing type formatting functions:

Workshop 9 - ConstraintsManagement has provided further input to your schedule,

The client requires the submission on 26 Jan 12,

Because the Format, Bars Styles group Slackbutton only displays the Free Float and does not

Page 150

button only displays the Free Float and does not display the Total Float or Negative Float we will use the Gantt Chart Wizard to format the bars to show these important pieces of information.

Page 10: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

28

Tables A table selects and formats the columns of data to be displayed in a View,

The formatting of tables is covered in the Formatting the Display module,

A table may be applied to one or more Views which display data in tables,

Page 163

There are two types of tables:Task tables that are applied to Task Views and

Resource tables that are applied to Resource Views.

A View is permanently changed when it is assigned a different Table,

The instructor will demonstrate how to create a new Table and edit an existing Table.

Custom Fields

A Custom Field is an existing Microsoft project field that may be:

Renamed to suit your projects requirements,

Tailored to display specific data in a specific format,

A i d li t h li t f l l th t

Page 164

Assigned a list, such as a list of values or people, that may be assigned from a drop-down list, or

Assigned a formula for calculating data from other fields,

The instructor will demonstrate how to create a Custom Field.

GroupingGrouping allows grouping of tasks under data items such as Customized fields, Durations, Constraints, etc:

Page 165

The instructor will demonstrate the Grouping function.

Workshop 11 - Reorganizing the Schedule

We want to issue reports for comment by management,

We will group the tasks by their float value and show the WBS columns,

We will also look at the Outline Codes and then Group

Page 166

We will also look at the Outline Codes and then Group the Tasks by the people responsible for the work, which we will enter into a text column.

Module 14 Module 14 -- Views & DetailsViews & DetailsApplying an Existing View

Understanding Views

Creating a New View

Details Form

Page 167

Timeline View

A Logical Process for Developing a View

PRINCE2 Product Flow Diagram View

Workshop 12- Organizing Your Data Using Views and Tables .

Applying an Existing ViewAll Views, except the Timescale view which is normally displayed above the Gantt Chart, may be applied by:

Clicking the appropriate button from the Ribbon View, Task Views and Resource Views groups,

Page 168

Clicking on the down arrow by a View Name on View, Task Views and Resource Views ,

There are more views available than the Views listed on the Ribbon menu,

These may be applied from the More Views… form which may be accessed from many places,

The instructor will leave you through some existing views.

Page 11: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

31

Manual Page Breaks Manual page breaks are inserted by:

Placing the Manual Page Break button on the Ribbon or Quick Access Toolbar,

Highlighting the row above where a page break is required. Then click on the Manual Page Breakbutton,

Page 181

,

A dotted line will indicate the location of the manual page break,

To remove a manual page break, highlight the row above where there is a page break and the Manual Page Break button,

Note: Manual page breaks did not print on the author’s install of Microsoft Project 2010, this issue may be resolved at a later time with a software upgrade.

Reports The Reports are found at the Project, Reportsgroup. There are two types of reports:

Visual which were introduced with Microsoft Project 2007 and

Reports which have been available for a long time,

Page 182

Reports which have been available for a long time,

The instructor will demonstrate these two functions.

Completed Schedule Check ListThis check list should be used to check a schedule before it is submitted.

Page 183

Workshop 13 - ReportsWe want to issue a report for comment by management.

Page 184

Module 1515 – Tracking ProgressTracking ProgressTopics:

Setting the Baseline

Practical Methods of Recording Progress

Understanding Tracking Progress Concepts

Updating the Schedule

Page 185

Updating the Schedule

Simple Procedure for Updating a Schedule

Procedure for Detailed Updating

Comparing Progress with Baseline

In-Progress Schedule Check List

Corrective Action

Workshop 14 - Updating the Schedule and Baseline Comparison.

The main steps for monitoring progress are:Set the Baseline Dates. These are the dates against which progress is compared,

Approve the work to commence in accordance with the plan,

R d k t th St t D t

Tracking Progress Steps

Page 186

Record or mark-up progress as at the Status Date,

Update the schedule with Actual Start and Actual Finish dates where applicable, and adjust the task Actual and Remaining durations and/or % Complete,

Compare and Report actual progress against planned progress and revise the schedule, if required, to forecast future tasks and milestones,

Implement any corrective action to bring the project back on schedule.

Page 12: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

34

In-Progress Schedule Check ListThis check list may be used to check an in-progress schedule before it is published.

Page 199

Corrective ActionThere are two courses of action available with slippage:

The first is to accept the slippage. This is rarely acceptable, but it is the easiest answer,

The second is to examine the schedule and evaluate how you could improve the end date,

Suggested techniques to bring the project back on

Page 200

Suggested techniques to bring the project back on track include:

Reducing the durations of tasks on the Critical Path,

Providing more time by changing calendars,

Changing task relationships so tasks take place concurrently,

Change the method of execution, for example moving work off-site,

Reducing the project scope and hence deleting tasks.

Workshop 14 - Updating the Schedule and Baseline Comparison

At the end of the first week you have to update the schedule and report progress and slippage,

The instructor will demonstrate this workshop.

Page 201

Module 1717 – Creating Resources Creating Resources and Costsand CostsTopics:

Creating Resources in the Resource Sheet

Grouping Resources in the Resource Sheet

Resource Information Form

Page 202

Resource Calendars

Workshop 15 - Defining Resources.

Understanding ResourcesA resource may be defined as something or someone that is assigned to a task and is required to complete the task. This includes people or groups of people, materials, equipment and money,

It is recommended that the minimum number of resources be assigned to tasks when it is planned to

Page 203

status a schedule. Avoid cluttering the schedule with resources that are in plentiful supply or are of little importance. Every resource added to the schedule will need to be statused. Therefore the scheduler’s workload increases as resources are added to tasks,

Microsoft Project 2007 has introduced a Cost resource in addition to the existing Work and Material resources. This allows the entry of Costs as a resource without requiring a quantity,

Microsoft Project also has an Expense function.

Using ResourcesIndividual Resources – Individual people often responsible for completing the task or tasks associated with tasks to which they have been assigned,

Group Resources – Represent groups of people, such as trades or disciplines on a construction site,

Crews – Representing a mix of trades and mobile

Page 204

Crews Representing a mix of trades and mobile equipment,

Input Resources – These resources are required to complete the work and represent the project costs,

Output Resources – These could be the project deliverables or outcomes and could have a direct relationship to the project income.

Page 13: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

37

Assignment of Resources to Summary Tasks

Summary tasks may be assigned Fixed Costs, Work Resources, Costs Resources and Material Resources,

You must also be aware that when a Work resource is assigned to a summary task the task type is set to

Page 217

g y ypFixed Duration and that setting may not be changed,

Thus, any change in duration of a summary task due to rescheduling of associated detail tasks will result in a change to the work assignment and the calculated costs of a summary task.

Assigning Resources Resources may be assigned a number of ways including using the:

Resource Assignment form

Task Details form

T k I f ti f

Page 218

Task Information form

Resources column

The instructor will demonstrate some of these functions by completing the workshop.

Rollup of Costs and Hours to Summary

The summary task Cost and Work fields are calculated from the sum of the costs and work assigned to the related detail tasks and those of the summary task,

Summary tasks have the costs and work rolled up to give you a cost at any Outline level.

Page 219

Tasks Contour the Resource Assignment

A Resource Assignment may be assigned to a task with a non-linear profile.

Open the Assignment Information form by:Double-clicking on a resource in the Task Usage orResource Usage view or

Page 220

Resource Usage view, or

Right-clicking on a resource and selecting Information(Assignment) from the menu.

Workshop 16 - Assigning Resources to Tasks

The resources must now be assigned to their specific tasks.

Page 221

Module 1919 – Resource OptimizingResource OptimizingTopics:

Resource Graph FormResource Graph View Resource Tables View

Page 222

Detailed Styles Form Team Planner View Printing Resource Profiles and Tables Creating Resource Graphs, Crosstab Tables, S-Curves in a Spreadsheet Resource OptimizationWorkshop 17 – Resource Graphs and Tables.

Page 14: 101231 P2 2009 and MSP 2010 presentation.ppteastwoodharris.com/DL/SS/101231_P2_2009_and_MSP_2010_Sample_Slides.pdf · PRINCE2 also defines 5 types of plans as per the picture on the

40

Statusing a Resourced ScheduleIt is often considered best practice to update a project between 10 and 20 times in its lifecycle. Some companies update schedules to correspond with accounting periods, which are normally every month. This frequency is often too long for projects that are less than a year in duration, as too much

Page 235

y ,change may happen in one month. Therefore, more frequent updating may identify problems earlier,Statusing a project with resources employs a number of preferences and options, which are very interactive and will require a significant amount of practice by a user to understand and master them,It must be decided if the software will calculate the Actual costs and units from the percentage complete or if this data is to be collected and entered into the software.

Preparing to Status a Resourced Schedule

After this course and before working on a live project, inexperienced users should gain confidence with the software by:

Creating a new project and setting the Options to reflect the method you wish to enter information and

Page 236

how you want Microsoft Project to calculate the project data,Creating two or three tasks and then assigning two or three resources to each task,Update the Tasks and Resources as if you were updating a schedule and observe the results,Alter the preferences and defaults if you are not receiving the result you require. Re-update and note the preferences and defaults for future reference.

Updating a Resourced ScheduleUpdating a project with resources takes place in two distinct steps:

1. The dates, durations and relationships are updated using the methods outlined in the Tracking Progress chapter, and

Page 237

p ,

2. The Resource, Expenses Units (hours and quantities) and Costs, both the Actual to Date and To Complete, are then updated.,

Note: These values may be either:

Automatically updated by Microsoft Project from the % Complete or

Imported from accounting and timesheet systems.

Understanding Baseline Dates, Duration, Costs and Hours

Baseline Dates and Baseline Duration were covered earlier,

Baseline Costs are also known as Budgets and represent the original project cost estimate. These are the figures against which the expenditures and

Page 238

g g pCost at Completion (or Estimate at Completion) are measured,

Baseline Work is also known as Budgeted Quantity and represents the original estimate of the project quantities. These are the quantities against which the consumption of resources are measured,

Note: If resources have been assigned then the Baseline Costs and Work are recorded at the same time as the Baseline dates.

Understanding Baseline Dates, Duration, Costs and Hours

The picture below shows the display of Baseline data:

Page 239

Understanding the Status Date The Status Date was covered earlier,

Actual Costs and Quantities/Hours or Actual Workoccur before the Status Date,

Costs and Quantities/Hours To Complete or Work to Complete occur after the Status Date.

Page 240

p

Note: The Status Date is by default set at the end of each day.