24
Clean Rivers Clean Lake Conference May 1, 2014 Marsha Burzynski

2014 Clean Rivers, Clean Lake Conference -- Lincoln Park and MKE River Channel Sediment Projects

Embed Size (px)

Citation preview

Clean Rivers Clean Lake Conference

May 1, 2014

Marsha Burzynski

Site History

◦ Location

◦ Problem identification

Clean up Actions

◦ Blatz Pavilion

◦ Phase 1

◦ Phase 2

Project Area

Lincoln Park Project Area

Fish tissue sampling

found PCBs ◦ First consumption advisory

◦ issued in 1981

Studies in late

‘80s/early ‘90s identified

Lincoln Creek/West Oxbow

contaminated with PCBs

3 Priority Areas Identified

• 4700 cubic yards sediment

removed • 300 lbs of PCB removed • 100% State Funded

120,000 cubic yards sediment excavated

>5,000 pounds PCBs removed

>4,000 pounds PAHs removed

Funded through Legacy Act (65%) and State (35%)

September 2011

February 2012

Sept. 29, 2011

October 10, 2011

Found contamination we didn’t expect…

PAH contamination found in Phase I

area near north bridge cutoff wall

Sampling on upstream side of sheet

pile showed contamination at depth

Cut sheetpile off at sediment grade

after excavation to act as cutoff wall

Lincoln Park Phase 2

Additional Sampling ◦ Bathymetry

◦ NAPL (North Bridge)

◦ Sediment sampling

• Approximately 35,000 cubic yards

of non-TSCA sediment from 9

main deposits

• About 500 cubic yards TSCA

• No remediation needed in east

oxbow, or north of the oxbows

• Mechanical (dry) excavation for all

deposits except:

• Southern portion of 7-4 and

deposit 4-3

7 alternatives evaluated, including no-action

Recommended Alternative 4a: ◦ Dry Excavation, targeted hydraulic dredging and

offsite disposal ◦ FS Cost estimate about $15 million

Public Information Open House held August 20, 2013 ◦ Received concurrence with recommended

alternative

Areas disturbed as a result of remedial action will be restored

Restoration will directly follow each excavation area

Menu of techniques

developed that will be

tailored to each area

Administrative

o Phase II Remedial Action Application Submitted to EPA December 2013

o Milwaukee County/DNR presented to EPA January 2014

o Accepted by EPA March 2014

o Project Agreement Negotiations underway

Public Informational Open House o Third Week of May 2014 (time/location tbd)

Contractor selection – summer 2014

Begin mobilization late summer 2014

Remediation Complete winter 2014/2015

Habitat Restoration Complete Summer/fall 2015

US EPA GLNPO

Milwaukee County

Wisconsin DNR

EPA Contractors TBD