Benning Rd ReconstructionProject Field Office1322A H Street NEWashington, DC 20002(o) 202.388.3081 (f) 202.388.3083
RECONSTRUCTION OF BENNING ROAD NEFROM 14TH AND H STREET TO OKLAHOMA AVENUE
CONTRACT NO. POKA 2005 - C - 0031 CB
CONSTRUCTION MANAGERS WEEKLY STATUS REPORTWEEK OF 3/11/10-3/17/10
Workers placed concrete for the exposed aggregate sidewalk at the
Starburst Plaza ramp.
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
2/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 2
PROJECT SUMMARY
Phased reconstruction of eastbound and westbound Benning Road NE from 14th
and H Street to OklahomaAvenue, including portions of Maryland Avenue and Bladensburg Road. Work encompasses:
Repaving road surface and building new brick gutters and granite curbs,
Sidewalk restoration with pedestrian-friendly exposed aggregate surface treatment,
Safety improvements crosswalks, wheelchair ramps, and driveway entrances
New streetlights, upgraded traffic signals and timing
Upgraded water mains, storm drains, inlet basins, and sewer lines,
Landscaping upgrades, including construction of the Starburst Plaza with a historical mural andneighborhood attractions,
Streetcar tracks installed on eastbound and westbound lanes of Benning Road from OklahomaAvenue to 14
thand H Streets, and in the separate H Street Construction Project, along H Street from
14th
Street to 3rd
Street.
Original contract value -- $35,448,123.90. Prime contractor: Capitol Paving of DC, Inc. (CPDC)Notice to Proceed Date: December 12, 2007
Projected completion dates:
16th
Oklahoma -- December 15, 2009, Substantially completed ahead of schedule.
Starburst -- April 9, 2010Construction Progress -- This chart shows the percentage of work completed as of March 17, 2010in the principal categories of Streetcar Rail Installation, Roadway Paving & Sidewalk Construction, WASAWork, Washington Gas Work, and PEPCO Work.
81% 86%
99% 100% 100%
0%
20%
40%
60%
80%
100%
% of Work Completed
Streetcar Rail Installation Roadway Paving & Sidewalk Construction
WASA Work Washington Gas Work
PEPCO Work
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
3/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 3
COMMUNITY RESPECT & OUTREACH
During this reporting period, MACTEC provided notices to the community by e-mail and door-to-door distribution announcing the lifting of the restrictions on northbound 15th Street at BenningRoad, effective Saturday, March 20.
DAY-TO-DAY WORK PERFORMED[The Benning Road component extends from 16
thStreet to Oklahoma Avenue. The Starburst
Intersection component encompasses portions of H Street, Morse Street, Maryland Avenue, 15th
Street, and Bladensburg Road at their juncture.]
Thursday 3/11/10
Benning Road: Between 15th
and 16th
Streets, the graded aggregate base was placed in the intersection
of the 15
th
Street median work. The exposed aggregate sidewalk and block pavers were placed at 16
th
Street. Topsoil was placed in the planter box in the median of the 1500 block. Line striping was carriedout on Benning Road from 14
thStreet to 16
thStreet.
Bladensburg Road: Between Morse Street and Neal Street, the graded aggregate base was compactedand preparations were made for density testing. Flippo crew worked on the adjustment of severalmanhole tops in the median of Bladensburg Road.
Starburst Plaza: On the east side, workers excavated and installed the catch basin, and connectingpipes from MH17B(S) to DI-8, MH17B(S) to DI-6 and stub to DI-7.
Electrical Work: At Benning and Oklahoma Ave, traffic signal controller cabinet TC-8 was furnished andinstalled.
Project-wide: Contractor performed general site cleaning and MOT maintenance.
Friday 3/12/10
Project-wide: Work cancelled due to weather conditions. Contractor performed general site cleaning andMOT maintenance.
Saturday 3/13/10 No work scheduled.
Monday 3/15/10 Major work activities cancelled due to weather conditions. Flippo crew worked on theadjustment of several manhole tops in the median of Bladensburg Road.
Tuesday 3/16/10
Starburst Intersection & Bladensburg Road: Continuation of the reset of manhole to grade at the
Starburst Intersection in at Bladensburg and Benning Road and at 16th
Street. Preparation for theinstallation of the sidewalk on the mall ramp and Maryland Ave. Flippo crew worked on the adjustment ofseveral manhole tops in the median of Bladensburg Road.
Electrical Work: On the northeast corner of Benning Road and Bladensburg Road, the pedestrian countdownwas damaged in an accident and was repaired.
Project-wide: Contractor performed general site cleaning and MOT maintenance, general road surfacecondition maintenance, and pothole repair.
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
4/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 4
Wednesday 3/17/10
Starburst Intersection & Bladensburg Road: Placement of the concrete for the exposed aggregatesidewalk at the Starburst Plaza walkway ramp from 45+18 to 42+46. Contractor began the excavationand placement of the aggregate base and site preparation for the placement of the exposed aggregatesidewalk on Maryland Ave on the east side. Continuation of the reset of manhole to grade atBladensburg and Benning Road and at 16
thStreet. Flippo crew worked on the adjustment of several
manhole tops in the median of Bladensburg Road.
Electrical Work: At Benning Road and Bladensburg Road, the temporary portable concrete base for the 20steel traffic signal pole mounted on a transformer base was furnished and installed.
Project-wide: Contractor performed general road surface condition maintenance, pothole repair, generalsite cleaning and MOT maintenance.
UTILITIES RECONSTRUCTION
PEPCO Benning Road Distribution Line Duct Bank Construction & Feeder Line Replacementcompleted February 11, 2009. Starburst Distribution Line Duct Bank Construction completed Aug 14,2009.
WASHINGTON GAS -- Completed gas main upgrades and connections on January 14, 2009,except for the 1400 block of H Street where the work was completed in early January 2010.
CLEAR CHANNEL -- Will relocate Starburst Plaza bus shelters after completion of other Starburstvicinity work.
BENNING ROAD PROJECT -- TWO-WEEK LOOK AHEAD Mar 23 Apr 6, 2010Work days Monday thru Saturday unless otherwise indicated.
Activity Locations Projected DatesProject site clean-up; erosion &
sediment control, inspection &
maintenance; MOT
(Maintenance of Traffic) plans,
inspection, repair, &
maintenance
Throughout the work
siteDaily, except Saturdays
Install OCS foundations &
streetlight foundations1400 block of H Street Tue Mar 23 thru Fri Mar 26
Install topsoil on Maryland Ave
Starburst Plaza Area
Tue Mar 23
Open sidewalk on Maryland Ave Wed Mar 24
Construct sidewalk on mall
ramp & Maryland AvenueMon thru Fri Mar 15-19
Place asphalt Bladensburg Road Tue & Wed Mar 23-24
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
5/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 5
BENNING ROAD PROJECT -- TWO-WEEK LOOK AHEAD Mar 23 Apr 6, 2010Work days Monday thru Saturday unless otherwise indicated.
Activity Locations Projected DatesPlace asphalt
Benning Road 1500
block
Tue & Wed Mar 23-24
Construct sidewalk, south sideWed Mar 24 thru Fri Mar 26
Mon & Tue Mar 29-30
Install cobblestones, south sideFri Mar 26
Mon thru Wed Mar 29-31
Install PCC base between
median wall & granite curbThu & Fri Mar 25-26
Excavate & place graded
aggregate baseTue Mar 23 thru Fri Mar 26
Weld rails Mon thru Wed Mar 29-31
Install rail boot & ties Wed thru Fri, Mar 31 thru Apr 1
Tie steel Fri Apr 2, Mon & Tue Apr 5-6
PHOTOS OF WORK DURING THE WEEK OF 3/11-3/17/2010
Placement ofconcrete for the ex
Workers placed
concrete for the
exposed
aggregate
sidewalk along
the Starburst
Plaza ramp.
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
6/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 6
CPDC excavated, (above left), did gradingwork (above right), and placed concrete forthe exposed aggregate sidewalk onMaryland Avenue.
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
7/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 7
Workers, above left, compacted the graded aggregate base in the median ofBladensburg Road at Morse Street and, above right, did grading work in themedian of Benning Road at the Starburst intersection in preparation for asphaltpaving. PEPCO reconstruction of the manhole tops in the median of BladensburgRoad at Morse Street is shown below.
8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC
8/8
CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 8
Artist Steven Weitzman, second from left, and his colleagues took
measurements at the Starburst Plaza fountain wall in preparation for installing
Mr. Weitzmans terrazzo Cornerstones of History mural. Commissioned by
the DC Commission on Arts and Humanities, the mural portrays the African-
American heroes Duke Ellington, Bessie Smith, Dr. Martin Luther King Jr., and
Rosa Parks.