    Benning Rd ReconstructionProject Field Office1322A H Street NEWashington, DC 20002(o) 202.388.3081 (f) 202.388.3083

    RECONSTRUCTION OF BENNING ROAD NEFROM 14TH AND H STREET TO OKLAHOMA AVENUE

    CONTRACT NO. POKA 2005 - C - 0031 CB

    CONSTRUCTION MANAGERS WEEKLY STATUS REPORTWEEK OF 3/11/10-3/17/10

    Workers placed concrete for the exposed aggregate sidewalk at the

    Starburst Plaza ramp.

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    2/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 2

    PROJECT SUMMARY

    Phased reconstruction of eastbound and westbound Benning Road NE from 14th

    and H Street to OklahomaAvenue, including portions of Maryland Avenue and Bladensburg Road. Work encompasses:

    Repaving road surface and building new brick gutters and granite curbs,

    Sidewalk restoration with pedestrian-friendly exposed aggregate surface treatment,

    Safety improvements crosswalks, wheelchair ramps, and driveway entrances

    New streetlights, upgraded traffic signals and timing

    Upgraded water mains, storm drains, inlet basins, and sewer lines,

    Landscaping upgrades, including construction of the Starburst Plaza with a historical mural andneighborhood attractions,

    Streetcar tracks installed on eastbound and westbound lanes of Benning Road from OklahomaAvenue to 14

    thand H Streets, and in the separate H Street Construction Project, along H Street from

    14th

    Street to 3rd

    Street.

    Original contract value -- $35,448,123.90. Prime contractor: Capitol Paving of DC, Inc. (CPDC)Notice to Proceed Date: December 12, 2007

    Projected completion dates:

    16th

    Oklahoma -- December 15, 2009, Substantially completed ahead of schedule.

    Starburst -- April 9, 2010Construction Progress -- This chart shows the percentage of work completed as of March 17, 2010in the principal categories of Streetcar Rail Installation, Roadway Paving & Sidewalk Construction, WASAWork, Washington Gas Work, and PEPCO Work.

    81% 86%

    99% 100% 100%

    0%

    20%

    40%

    60%

    80%

    100%

    % of Work Completed

    Streetcar Rail Installation Roadway Paving & Sidewalk Construction

    WASA Work Washington Gas Work

    PEPCO Work

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    3/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 3

    COMMUNITY RESPECT & OUTREACH

    During this reporting period, MACTEC provided notices to the community by e-mail and door-to-door distribution announcing the lifting of the restrictions on northbound 15th Street at BenningRoad, effective Saturday, March 20.

    DAY-TO-DAY WORK PERFORMED[The Benning Road component extends from 16

    thStreet to Oklahoma Avenue. The Starburst

    Intersection component encompasses portions of H Street, Morse Street, Maryland Avenue, 15th

    Street, and Bladensburg Road at their juncture.]

    Thursday 3/11/10

    Benning Road: Between 15th

    and 16th

    Streets, the graded aggregate base was placed in the intersection

    of the 15

    th

    Street median work. The exposed aggregate sidewalk and block pavers were placed at 16

    th

    Street. Topsoil was placed in the planter box in the median of the 1500 block. Line striping was carriedout on Benning Road from 14

    thStreet to 16

    thStreet.

    Bladensburg Road: Between Morse Street and Neal Street, the graded aggregate base was compactedand preparations were made for density testing. Flippo crew worked on the adjustment of severalmanhole tops in the median of Bladensburg Road.

    Starburst Plaza: On the east side, workers excavated and installed the catch basin, and connectingpipes from MH17B(S) to DI-8, MH17B(S) to DI-6 and stub to DI-7.

    Electrical Work: At Benning and Oklahoma Ave, traffic signal controller cabinet TC-8 was furnished andinstalled.

    Project-wide: Contractor performed general site cleaning and MOT maintenance.

    Friday 3/12/10

    Project-wide: Work cancelled due to weather conditions. Contractor performed general site cleaning andMOT maintenance.

    Saturday 3/13/10 No work scheduled.

    Monday 3/15/10 Major work activities cancelled due to weather conditions. Flippo crew worked on theadjustment of several manhole tops in the median of Bladensburg Road.

    Tuesday 3/16/10

    Starburst Intersection & Bladensburg Road: Continuation of the reset of manhole to grade at the

    Starburst Intersection in at Bladensburg and Benning Road and at 16th

    Street. Preparation for theinstallation of the sidewalk on the mall ramp and Maryland Ave. Flippo crew worked on the adjustment ofseveral manhole tops in the median of Bladensburg Road.

    Electrical Work: On the northeast corner of Benning Road and Bladensburg Road, the pedestrian countdownwas damaged in an accident and was repaired.

    Project-wide: Contractor performed general site cleaning and MOT maintenance, general road surfacecondition maintenance, and pothole repair.

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    4/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 4

    Wednesday 3/17/10

    Starburst Intersection & Bladensburg Road: Placement of the concrete for the exposed aggregatesidewalk at the Starburst Plaza walkway ramp from 45+18 to 42+46. Contractor began the excavationand placement of the aggregate base and site preparation for the placement of the exposed aggregatesidewalk on Maryland Ave on the east side. Continuation of the reset of manhole to grade atBladensburg and Benning Road and at 16

    thStreet. Flippo crew worked on the adjustment of several

    manhole tops in the median of Bladensburg Road.

    Electrical Work: At Benning Road and Bladensburg Road, the temporary portable concrete base for the 20steel traffic signal pole mounted on a transformer base was furnished and installed.

    Project-wide: Contractor performed general road surface condition maintenance, pothole repair, generalsite cleaning and MOT maintenance.

    UTILITIES RECONSTRUCTION

    PEPCO Benning Road Distribution Line Duct Bank Construction & Feeder Line Replacementcompleted February 11, 2009. Starburst Distribution Line Duct Bank Construction completed Aug 14,2009.

    WASHINGTON GAS -- Completed gas main upgrades and connections on January 14, 2009,except for the 1400 block of H Street where the work was completed in early January 2010.

    CLEAR CHANNEL -- Will relocate Starburst Plaza bus shelters after completion of other Starburstvicinity work.

    BENNING ROAD PROJECT -- TWO-WEEK LOOK AHEAD Mar 23 Apr 6, 2010Work days Monday thru Saturday unless otherwise indicated.

    Activity Locations Projected DatesProject site clean-up; erosion &

    sediment control, inspection &

    maintenance; MOT

    (Maintenance of Traffic) plans,

    inspection, repair, &

    maintenance

    Throughout the work

    siteDaily, except Saturdays

    Install OCS foundations &

    streetlight foundations1400 block of H Street Tue Mar 23 thru Fri Mar 26

    Install topsoil on Maryland Ave

    Starburst Plaza Area

    Tue Mar 23

    Open sidewalk on Maryland Ave Wed Mar 24

    Construct sidewalk on mall

    ramp & Maryland AvenueMon thru Fri Mar 15-19

    Place asphalt Bladensburg Road Tue & Wed Mar 23-24

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    5/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 5

    BENNING ROAD PROJECT -- TWO-WEEK LOOK AHEAD Mar 23 Apr 6, 2010Work days Monday thru Saturday unless otherwise indicated.

    Activity Locations Projected DatesPlace asphalt

    Benning Road 1500

    block

    Tue & Wed Mar 23-24

    Construct sidewalk, south sideWed Mar 24 thru Fri Mar 26

    Mon & Tue Mar 29-30

    Install cobblestones, south sideFri Mar 26

    Mon thru Wed Mar 29-31

    Install PCC base between

    median wall & granite curbThu & Fri Mar 25-26

    Excavate & place graded

    aggregate baseTue Mar 23 thru Fri Mar 26

    Weld rails Mon thru Wed Mar 29-31

    Install rail boot & ties Wed thru Fri, Mar 31 thru Apr 1

    Tie steel Fri Apr 2, Mon & Tue Apr 5-6

    PHOTOS OF WORK DURING THE WEEK OF 3/11-3/17/2010

    Placement ofconcrete for the ex

    Workers placed

    concrete for the

    exposed

    aggregate

    sidewalk along

    the Starburst

    Plaza ramp.

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    6/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 6

    CPDC excavated, (above left), did gradingwork (above right), and placed concrete forthe exposed aggregate sidewalk onMaryland Avenue.

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    7/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 7

    Workers, above left, compacted the graded aggregate base in the median ofBladensburg Road at Morse Street and, above right, did grading work in themedian of Benning Road at the Starburst intersection in preparation for asphaltpaving. PEPCO reconstruction of the manhole tops in the median of BladensburgRoad at Morse Street is shown below.

  • 8/3/2019 3 17 10+Benning+Road+Weekly+Report PUBLIC

    8/8

    CONSTRUCTION MANAGERS WEEKLY PROGRESS REPORT Benning Road ReconstructionWeek of 3/11/10-3/17/10Page 8

    Artist Steven Weitzman, second from left, and his colleagues took

    measurements at the Starburst Plaza fountain wall in preparation for installing

    Mr. Weitzmans terrazzo Cornerstones of History mural. Commissioned by

    the DC Commission on Arts and Humanities, the mural portrays the African-

    American heroes Duke Ellington, Bessie Smith, Dr. Martin Luther King Jr., and

    Rosa Parks.