    Risk Management Audit Guidelinesfor MOM-Approved WSH Auditors

    &

    1

    Fung Chan HuaSr AD, ECB Branch/ICB Department

    Workplace Safety & Health Council

    u e nes or rgan sa ons an s

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    2/18

    Presentation Outlines

    Background

    RM Audit Guidelines

    Supplementary Guidelines for RMAF

    2

    uidelines for AR s & AR s

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    3/18

    Background

    RM audit requirements for

    bizSAFE Level 3

    direct entry to bizSAFE Star

    3

    Partner renewal

    Lack of comprehensive coverage

    Insufficient details in the report

    Defined work scope for ARCs

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    4/18

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    5/18

    - Alignment to Code of Practice

    on Risk Management (RMCP)

    RM Audit Guidelines

    - Evidence-based Audit requirements

    5

    1 WSH Policy

    The WSH Policy shows the

    organisations commitment to

    reduce WSH risks

    The WSH Policy is approved by top

    management

    The WSH Policy is communicated to

    relevant stakeholders

    WSH Policy with endorsement by top

    management

    Organisation chart

    Evidence of communication to

    stakeholders

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    6/18

    - Evidence of risk control measures in place forhigh risk activities

    RM Audit Requirements Examples of Evidence

    7 Risk Controls

    There is a reduction in risk level of work Documented evidence of the application of risk

    RM Audit Guidelines

    6

    activity after the implementation of

    prioritised risk controls

    Additional Risk Controls

    Recommendation of additional controls on top

    of the existing controls to further reduce risk

    levels, if appropriate

    control measures, targeting higher risk activities

    with respect to industry sectors:

    Work-at-Height for Marine / Construction

    Fire & explosion for Marine/ Chemical

    Confined space Marine/Construction

    Other high risk activity, as appropriate

    Documented evidence of risk reduction after

    implementation of risk control measures

    Evidence of implementation of hierarchy of

    control: elimination, substitution, engineering

    control, administrative control and PPE

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    7/18

    - Audit protocol and process with the followings:

    i. Opening meeting;ii. Assessment of written RM system;

    iii. Verification of the effective implementation of RM, review

    of documents, interviews of personnel and physical

    RM Audit Guidelines

    7

    inspection of RA (and SWP) implementation of all activities,etc;

    iv. Evaluation of findings; and

    v. Exit meeting.

    - Use of checklists, audit notes, work book, orequivalent to ensure adequate coverage of

    audit requirements and notes taking

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    8/18

    - Audit Report :

    Minimum content are defined

    Must be signed off by all WSH Auditors involved

    RM Audit Guidelines

    8

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    9/18

    The name, address, workplace number and profile of the client;

    Identification of the WSH Auditing Organisation and Auditorsinvolved;

    The normative references used in the RM audit; The audit objectives;

    RM Audit ReportIt shall include

    9

    ,

    processes audited; The dates, times (start and end times) and places the audit is

    conducted; Audit findings stating clearly the site activities audited, especially the

    RA and SWP of all activities, evidence, observations, conclusions; Persons involved in the opening meeting, exit meeting and

    interviews; Status updates of the findings from the previous RM and/or WSHMS

    audit, if applicable; and

    Others, as appropriate

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    10/18

    Supplementary Guidelines forRM Audit under RMAF

    - Risk Assessment Training:a) bizSAFE L1 for CEO or top managementb) bizSAFE L2 for at least the RM Champion

    10

    .

    in risk management by the ARC

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    11/18

    Supplementary Guidelines forRM Audit under RMAF

    - Risk Controls :1) At least 1 risk control measure to be

    implemented for every work activities as

    11

    .

    2) Appropriate risk controls for work-at-height(WAH) if this is an inherent part of the workactivities

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    12/18

    Risk Management Audit Guidelinesfor MOM-Approved WSH Auditors

    &

    12

    Workplace Safety & Health Council

    u e nes or rgan sa ons an s

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    13/18

    - Endorse any documents required by RMAFs

    Terms and Conditions- Advice & assist in developing a system for WSH

    risk management

    Duties of ARC Organisations

    and ARCs

    13

    - Arrange bizSAFE L1 course for CEO/topmanagement

    - Arrange bizSAFE L2 course for at least the RM

    champion- Train at least 20% of the workforce thru a

    training-led consultancy on RM course (at initial

    stage of the consultancy work)

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    14/18

    - Advice, assist, and/or establish on the followings:

    How RAs are done for key activities A risk register for work activities with RA done

    Prioritizing risk controls and implementation of all control

    Duties of ARC Organisationsand ARCs

    14

    measures At least 1 risk control measure implemented for every

    work activities as in Form 1A Risk ManagementAssistance Fund (with ARC services) Application Form

    A list (or an inventory) of work activities / processes

    Appropriate safe work procedures

    Reviewing the RA upon completion of risk controls

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    15/18

    Work of ARCsIt shall include

    - Formation of RM / RA teams

    - Conduct of Risk Assessment Hazard identification

    Risk evaluation

    15

    Risk controls

    - Risk communication

    - Record keeping

    Must have appropriate controls forWork-at-Height, such as FPP

    At least 1 risk control measure forevery work activities as in Form 1A

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    16/18

    Declaration

    - ARCO and all its ARCs are required to have read

    and understood the Guidelines for Approved RiskConsultant Organisations and Approved Risk Consultant

    16

    - ARCO and all its ARCs need to submit aprescribed declaration form to ICB/WSHC forhaving read and understood this guide

    - Submission of Declaration by: 1 April 2012

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    17/18

    - Ensure objectivity and impartiality in the RM

    Professional Ethic

    Independence of ARCOs, ARCs & WSH Auditors

    17

    - Exercise all due diligence when performing theirfunctions in relation to the conduct of riskconsultancy and RM audits

  • 7/27/2019 3_ Presentation on RM Audit ARC Guidelines

    18/18

    18