ALFA testbeam résumé
Dennis Petschull
Deutsches Elektronen-SynchrotronHamburg
DESY ATLAS Meeting, Zeuthen
D. Petschull ALFA testbeam résumé 2008-09-08 1 / 10
Motivation Testbeam results Conclusion & outlook
Outline
1 Motivation
2 Testbeam results
3 Conclusion & outlook
D. Petschull ALFA testbeam résumé 2008-09-08 2 / 10
Motivation Testbeam results Conclusion & outlook
Short reminder about ALFA
Figure: Elastic scattering event at IP1
ALFA setup and purposeAbsolute Luminosity For ATLAS
Roman Pots at ∼240m from IP1
Measure elastic scattering at very small angles
D. Petschull ALFA testbeam résumé 2008-09-08 3 / 10
Motivation Testbeam results Conclusion & outlook
Short reminder about ALFA
Figure: Exploded view of an ALFA Roman Pot Unit
Detector layoutMovable ”Roman Pots” approaching beam from top and bottom
Detectors using scintillating fibres on Ti-plates
Scint. light→ MAPMTs→ PMFs→ motherboard
D. Petschull ALFA testbeam résumé 2008-09-08 3 / 10
Motivation Testbeam results Conclusion & outlook
Why a testbeam?
Status before testbeamMechanics of one Roman Pot completely assembled
FE electronics debugging ongoing
DAQ and reconstruction software under development
Why going into testbeam?Test all components under ”real” conditions
Check if estimated resolution is achievable
Gain some experience with electronics and DAQ
D. Petschull ALFA testbeam résumé 2008-09-08 4 / 10
Motivation Testbeam results Conclusion & outlook
Why a testbeam?
Status before testbeamMechanics of one Roman Pot completely assembled
FE electronics debugging ongoing
DAQ and reconstruction software under development
Why going into testbeam?Test all components under ”real” conditions
Check if estimated resolution is achievable
Gain some experience with electronics and DAQ
D. Petschull ALFA testbeam résumé 2008-09-08 4 / 10
Motivation Testbeam results Conclusion & outlook
Testbeam schedule: forseen and real
Forseen scheduleH8 testbeam stand in the SPS experimental halls at CERN
Beamtime: July 15 - July 21 and August 6 - August 26Electronics-, LED- and possibly cosmics-test in bldg. 251 untilAugust 1⇒ move all equipment incl. Roman Pot Unit to H8 area afterwards
3 weeks of data taking
D. Petschull ALFA testbeam résumé 2008-09-08 5 / 10
Motivation Testbeam results Conclusion & outlook
Testbeam schedule: forseen and real
Real scheduleHeavy motherboard problems in bldg. 251; DAQ not running stable
August 12: test-setup dissambled in bld. 251 and moved to H8
Electronics still causing lot of trouble in H8
August 20: motherboard replaced with spare and testmotherboardsAugust 21: feedback from the detector; track patterns in the fibersand the silicon telescope with correlation between both
BUT: not using the final electronics which are going into LHC
August 25: actual motherboard (Lund) debugged and installed;still minor problems with DAQ software
D. Petschull ALFA testbeam résumé 2008-09-08 5 / 10
Motivation Testbeam results Conclusion & outlook
ALFA Electronics
Figure: Exploded view of an ALFA Roman Pot Unit
D. Petschull ALFA testbeam résumé 2008-09-08 6 / 10
Motivation Testbeam results Conclusion & outlook
ALFA Electronics
D. Petschull ALFA testbeam résumé 2008-09-08 6 / 10
Motivation Testbeam results Conclusion & outlook
Overall testbeam summary
(Temporary) problems:Electronics: motherboard and FE electronics not working together
Software: DAQ from silicon telescope and ALFA detector notworking together
Unstable beam conditions
Achievements:Collected altogether one million triggers with different parametersettings
In the end: several successful runs with Lund motherboard
All participants gained a lot of insight into ALFA electronics,mechanics and software
D. Petschull ALFA testbeam résumé 2008-09-08 7 / 10
Motivation Testbeam results Conclusion & outlook
More detailed testbeam results
Activities in bldg. 251LED instead of fibre detector
verify MAPMT and fibre mapping
measure S-curves
all kapton cables and different HV settings
D. Petschull ALFA testbeam résumé 2008-09-08 8 / 10
Motivation Testbeam results Conclusion & outlook
More detailed testbeam results
Activities in H8 area (chronological):Lund motherboard:
I ∼200 ns latency problem with motherboardI all kapton cables; delay scanning from 100 to 300 nsI ∼150.000 triggers counted
2 Orsay test boards:I only 2 kapton cables connected→ 10 PMTsI parameter scans: HV, kapton combinations, gain, DAC and x/yI ∼650.000 triggers counted
Lund motherboard:I all kapton cablesI measure S-curvesI reduced parameter scans: HV, DAC and x/yI ∼370.000 triggers counted
D. Petschull ALFA testbeam résumé 2008-09-08 8 / 10
Motivation Testbeam results Conclusion & outlook
Preliminary plots
Figure: First results from online reconstruction: beam profile on diamondshaped ALFA trigger counter (left); two possible tracks in fibre detector (right)
D. Petschull ALFA testbeam résumé 2008-09-08 9 / 10
Motivation Testbeam results Conclusion & outlook
Conclusion & outlook
ALFA testbeam with fully equipped Roman Pot at CERN inJuly+August 2008
Long struggle with electronics and unstable DAQ software
Finally (last 5 days) successful data-taking with actual electronicssetup
Testbeam data analysis will give details about ALFA project as awhole