    You are working as the project manager of a large international contractor.

    Your company has just been awarded a contract by the Japanese Government to de-

    commission and demolish a 1,000 MVA nuclear power station in Hokkaido Island, Japan. The

    nuclear power plant has been in use since late 1970s, and must be de-commissioned as soon

    possible in view of the recent meltdown disaster in Fukushima nuclear power plant after the

    earthquake and tsunami in March 2011.

    The project will include shutting down the nuclear power plant, disposal of the unused nuclear

    materials and nuclear waste, decontamination the entire plant of radioactive materials,

    dismantling the entire structure, levelling the ground, disposal of rubbish, and replanting with

    grass, shrubs and trees at on the site.

    The project is expected to take a total of three years to complete.

    Due to the urgency and time constraints of the project, the resources will be sourced from the

    following:

    Technical Expertise: French supplier of the nuclear plant

    Skilled and Unskilled Labour: From Philippines and China

    Managers and Supervisors: From Japan and Malaysia

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    2/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 2 of 36

    Earth Moving Machineries: From Japan

    The project has a tight deadline and the penalty for late completion is severe.

    Describe how you would manage the contract to ensure that the project organisation and its

    execution will lead to a win-win situation for both your company and your client (and the

    owner). Use all the knowledge and techniques you have learnt from the Contract Management

    module. Arrange your presentation in the following areas:

    Ex-ante incentivisation and flexible, far-sighted ex-post governance

    Standard forms of contracts and sources

    Contract laws

    Global management

    Differences in culture, communication

    (Approximately 4 marks for each of the 5 areas selected)

    [TOTAL: 20 MARKS]

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    3/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 3 of 36

    1. PROJECT TITLETo de-commission and demolish a 1,000 MVA Tomari Nuclear Power Plant (NPP), in

    Hokkaido Island, Japan.

    2. PROJECT BACKGROUNDThe nuclear power plant has been in use since late 1989, and must be de-commissioned as

    soon possible in view of the recent meltdown disaster in Fukushima Daiichi Nuclear Power

    Plant after the earthquake and tsunami in 11th of March 2011, the Japanese government has

    take a drastic step whereby any nuclear power plant reached the lifetime period of 30 to 40

    years operations need to be shut down.

    Photo 1: A View of Reactor 1, 2 and 3, Tomari Nuclear Power Plant,

    Hokkaido Island, Japan (Wikipedia).

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    4/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 4 of 36

    Although Tomari Nuclear Power Plant (NPP), in Hokkaido Island, Japan has not reach it

    lifetime period but its owner Hokkaido Electric Power Company had plan to decommission

    and demolish the plant due to safety reason and protest from the people.

    Photo 2: Arial View of Reactor 1, 2 and 3 of Tomari Nuclear

    Power Plant, Hokkaido Island, Japan (Google Earth).

    The Tomari Nuclear Power Plant is the only nuclear power plant in Hokkaido, Japan. It is

    located in the town of Tomari in the Furuu District and managed by the Hokkaido Electric

    Power Company. All of the reactors in this plant are Mitsubishi designs. The plant site totals

    1,350,000 m2

    (334 acres), with an additional 70,000 m2

    of reclaimed land.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    5/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 5 of 36

    Its geographical WGS84 coordinates are stated below;

    43210N 1403045E, 43.03611N 140.5125E43210N 1403045E, 43.03611N 140.5125E

    Tomari Nuclear Power Plant consists of three (3) reactors as tabulated below;

    Unit Type Commission date Electric Power

    Tomari - 1 Pressurized water

    reactors June 22, 1989 579 MW

    Tomari - 2Pressurized water

    reactorsApril 12, 1991 579 MW

    Tomari - 3 Pressurized waterreactors

    December 22, 2009 912 MW

    Figure 1: Tomari Nuclear Power Plant, Hokkaido Island, Japan Location Plan (Google Earth).

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    6/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 6 of 36

    3. PROJECT SCOPE

    Since the Project brief only mentioned to de-commission and demolish a 1,000 MVA Tomari

    Nuclear Power Plan, then I would assumed that we are only required to decommission Reactor

    Tomari 3, other reactors will be done by other contractors. "Decommissioning" a nuclear

    power plant can be defined as the cessation of operations and the withdrawal of the facility

    from service, followed by its transformation into an out-of-service state and eventually, its

    complete removal.

    Decommissioning activities are intended to place the facility in a condition that provides for

    the health and safety of the general public and the environment, while at the same time

    protecting the health and safety of the decommissioning workers.

    Decommissioning involves thus all the admisnistrative and technical operations allowing

    withdrawing a facility from the list of licensed facilities.

    The administrative operations concern particularly the elaboration of decommissioning plans

    and the obtainment of authorisations and free release certificates for the facilities and the site.

    The decommissioning process shall cover the following works;

    Shutting down the nuclear power plant shall require necessary permit.

    Disposal of the unused nuclear materials shall require necessary permit.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    7/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 7 of 36

    Disposal of nuclear waste entire and place those high radioactive waste to safe

    store yard.

    Decontamination the entire plant of radioactive materials except for high

    contaminated sections e.g. reactor building and vessel.

    Dismantling the entire structure and place those high radioactive component to safe

    store yard. Those cannot dismantle will be entomb.

    Figure 2: Removal of other structures and to be kept at safe store yard

    (Modified from Tomari I).

    Entombment.

    The fastest method to decommission a nuclear power plant. This option involves

    encasing radioactive structures, systems and components in a long-lived substance,

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    8/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 8 of 36

    with Lead/Concrete. The encased plant would be appropriately maintained, and

    surveillance would continue until the radioactivity decays to a level that permits

    termination of the plants license, with little or no additional decontamination.

    Figure 3: Entomb the Reactor Vessel (Modified from Tomari I).

    .

    Levelling the ground.

    Disposal of rubbish.

    Replanting with grass, shrubs and trees at on the site.

    Project duration to be stated in the contract is three (3) years to complete. Man power

    resources were identified;

    i. Technical expert: French supplier of the nuclear plant.

    ii. Skilled and unskilled labor: from Philippines and China.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    9/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 9 of 36

    iii. Managers and Supervisors: from Japan and Malaysia.

    iv. Earth moving machineries: from Japan.

    4. EX-ANTE INCENTIVISATION AND FLEXIBLE, FAR-SIGHTED EX-POSTGOVERNANCE.

    Ex ante incentivization

    The ability of a contract to provide ex-ante incentivization is illustrate in Figure 4, and were

    described by three parameters and they are the reward provides the motivation the contractor

    to share the owners objectives and perform, the associated risk and the safeguard provided by

    the owner to shield the contractor from the risk

    Figure 4: A simple contractual schema for ex-ante incentivization

    In ex-ante incentivization project management, if there is no risk, no need for any safeguard,

    and the reward surely low. If there is risk, there may or may not be a safeguard. If there is no

    safeguard, the contractor buys the risk from the owner, and a high reward may required. In the

    RiskPresent High Incentive Medium Incentive

    Absent Low IncentiveNO safeguard or

    Incentive necessary

    Absent Present

    Safeguard

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    10/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 10 of 36

    other hand shall there is a safeguard but the owner underwrites the contractors risk, the

    incentive can be lower.

    In some cases the safeguard is only provided against extreme risk and for lower levels of

    uncertainty, the contractor takes the risk, for extreme events, the client underwrites the risk.

    This is the case for target price contracts, or where the contractor only claims for variations

    over a certain size.

    However, in these cases the reward is less shall there is no safeguard. Ex-ante incentivization

    only can be adopted where the project conditions were entirely predictable throughout its life.

    With that Im afraid this project contract management is not applicable in the

    decommissioning of a nuclear power plant project as the risks are high and also unpredictable.

    Flexible, Farsighted, Ex-post governance

    If in the ex-ante incentivization the safeguard can only be given for all foreseen risks, ex-post

    governance in the other hand if properly motivated, the projects participants should together

    try to achieve clients common goal to complete the project within time, at estimated budget

    and acceptable performance with safety and sustainability.

    InFlexible, farsighted, ex post governance project contract management, it is opened to deal

    with unforeseen circumstances. Williamson (1995) suggested this kind of project contract

    management to provide four parameters which are the incentive intensity, the ease of making

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    11/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 11 of 36

    uncontested, bi-lateral adaptations, the reliance on monitoring and related administrative

    controls, (transaction costs) and the reliance on court ordering.

    In this contract incentive intensity where greater incentive intensity will elicit greater

    performance and sustained effort from the contractor to achieve the projectr's objectives, and

    greater flexibility in accepting changes to adapt the unforeseen circumstances. Bi-lateral

    adaptation where the ability of the parties mutually to accept changes should be imposed with

    collaboration, cooperation and cordial approach. Any Reliance on monitoring and

    administrative controls will only incur additional cost on the client.Thus, incentive intensity

    has a stronger impact on project costs than reducing control. If appropriate incentives are

    chosen, there may be no need for monitoring and control procedures, with the contractor

    working on their own.

    Reliance on court ordering should be reduced as much as possible and the contract should

    encourage client and contractor to settle their differences in ways other than settling them in

    court. Shall involve with arbitration or litigation the project will become a conflict and all

    parties will be in lose- lose situation. This adversarial approach should be replaced with trust.

    Surely in decommissioning of a nuclear power plant shall involve and face a lot of uncertainty

    and the risk are high e.g. possibility of explosion, high radioactive reading, fatality and many

    more. Thus, farsighted post governance project contracts management are more likely to be

    chosen in this project as it is able to face any new risks or uncertainty that may arise

    throughout the project duration. It is able to deal with unforeseen events, whether adverse or

    advantage. As the complexity and risk of this project is very high all parties should play their

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    12/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 12 of 36

    roles to achieve the project objectives. In order to encourage the contractor to do that client

    should offer the contractor with incentive and to provide flexible, farsighted governance to

    deal with incompleteness, but at minimum transaction costs

    In a high risk, large, complex, multi-stage, expensive and a fast track project like this the risk

    should be shared among the client and the contractor although it may not equally distributed.

    This is important as the decommissioning of a nuclear power plant will involves in securing a

    lot of works permit and authorities issues. The client should play their role to assist the

    contractor in securing all these necessary work permits.

    In my opinion the cost plus management contract where cost plus the incentives and the

    contractor fees (c+if) should be applied for this project. The contractor is paid for their cost,

    management fees with incentive for their contribution in solving the problems and completing

    the given task. Basically in this type of project the risk to the contractor is in the product and

    as well the work process.

    5. STANDARD FORM OF CONTRACT AND SOURCES

    Standard form of contract generally produced within a range of industries typically by

    professional bodies serving those industries or by committee specifically set up for the

    purpose. Therefore it is wisely to use the common standard form of contract shall they are in

    the same industry as you are for one reason they have been tested compared to bespoke

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    13/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 13 of 36

    contract where while designing it you might left out some certain important conditions. It is

    not easy to produce a standard form of contract as it requires a lot of effort and cannot

    undertake lightly.

    For example in 1998 the UKs Association for Project Manager published standard terms for

    the appointment for a project manager took some two years to draft. The intention of standard

    forms of contract is to provide a representative viewpoint of the industry which they serve. In

    a modern contract strategy the standard form of contract should not be one sided. It should

    share the risk equitably (in our case) between the client and the contractor.

    In Malaysia we also have a few of our own version standard form of contract issued by

    Pertubuhan Arkitek Malaysia (PAM) issuance of the PAM2006 (coming fast at the heels of

    PAM1998), Construction Industry Development Board (CIDB) of Malaysias various forms

    (CIDB2000, model terms for domestic sub-contracts, etc) IEM (The Institution of Engineers,

    Malaysia) Conditions of Contract and Jabatan Kerja Raya (JKR) Malaysia issuance of

    JKR203A edition 2007 where they indicate the perceived agreement that the source of

    conflicts and disputes might be traced to the contract. Other well known international standard

    forms of contract are also practiced in Malaysia especially by the international companies and

    when a contract involved international contractors. Some of the common international

    standard form of contract can be used in this contract and namely below;

    FIDIC standard form of contract is very widely using in the construction industries. FIDIC

    stands for Fdration Internationale Des Ingnieurs-Conseils in French or it mean The

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    14/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 14 of 36

    International Federation of Consulting Engineers, Its foundation started in 1913 by three

    countries namely Belgium, France and Switzerland each wholly or partly francophone.

    JCT standard forms of contract are also widely used in the construction and engineering

    industries. JCT means Joint Contracts Tribunal, who produces standard forms of contract,

    guidance notes and other standard documentation for use in the construction industry.

    Established in 1931,

    ICE the Institution of Civil Engineers founded on 2 January 1818, is an independent

    professional association, based in central London, representing civil engineering. The majority

    of its current members are British engineers, but it also has members in more than 150

    countries around the world. NEC Engineering and Construction Contract is one of its

    products.

    In my opinion any type of international standard forms of contracts can be used in this

    contract. The most important thing it should not be one sided and shares the risk equitably

    between the client and the contractor. The usage of standard forms of contract would be highly

    recommended especially in the field of construction in order to avoid ambiguity among

    different standards adopted by each country. After all these international common standard

    form of contract have been tested and used for quite many years and therefore their successful

    are almost definite.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    15/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 15 of 36

    The main issue of using the standard forms of contract is, clients are demonstrating that they

    wish to abide by industry standards and not impose unfair terms that shift the balance of

    power too much in their favor.

    6. CONTRACT LAW

    Normally the contract law to be used is the law of the country that the works is going to be

    carried out. If a choice is given I would like to propose to use the international law or the

    British Law as they are very established and tested in the past few centuries.

    In standard contract there are four fundamental elements for a binding contract to be formed

    between two companies and there are:

    Offer Acceptance The intention to be legally bound Consideration

    For this case study, it is assumed that the our company was awarded by the Hokkaido Electric

    Power Company the owner of Tomari Nuke Plant a USD 1 billion worth of contract. This

    constitutes an offer by the client and acceptance by the company by virtue of law. A tender

    was called among short listed contractors.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    16/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 16 of 36

    The contractor was quoted a USD 1 billion during the tender exercise. When the contractor

    had successfully won the tender, the client will award the contract to the contractor (an offer).

    When this offer being accepted it means an acceptance have been made. The contract

    specifically stated that the contractor need to decommissioning the nuclear power plant by

    carry out the shutting down the nuclear power plant, disposal of the unused nuclear materials,

    disposal of nuclear waste, decontamination the entire plant of radioactive materials,

    dismantling the entire structure and place those high radioactive component to safe store

    yard, entombment, levelling the ground, disposal of rubbish and replanting with grass, shrubs

    and trees at on the site. In this huge international contract the offer surely come with a letter of

    award and followed by everybody signing the contract document, this means the project is

    legally bound. The amount of contract worth USD 1 billion stated in the Letter of award is a

    considered a consideration therefore the contract are legally bounded.

    It is a norm when we carry out a project in foreign country we shall bounded to their law.

    Therefore in this case the work in Japan shall be subject to Japan Contract Law. Japanese

    contract law allows greater ambiguity than American contract law. A Japanese contract, for

    instance, does not require clear statements of offer, acceptance, or consideration: most simply

    begin with a declaration, e.g. "Company X and Company Y hereby enters into this following

    agreement." Their contracts also tend to contain very little detail, with the parties working out

    complications as they arise.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    17/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 17 of 36

    Although normally Japanese contract is less detailed, Japan's tort system sees considerably

    less activity than tort systems in Western Europe and North America. The reason for this is

    that attorney's fees are based on the amount of damages sought in the suit, not the actual

    damages won. Because Japan does not use juries, judges decide the outcome of cases, and are

    usually not easy to sway emotionally. As a result, many individuals choose not to sue when

    their odds of winning seem low, and when they do sue, they tend to sue for small amounts of

    damages.

    As we shall buy a lot of other materials from varies country e.g. lead metal panel from China,

    concrete cement truck with from Germany, steel from Australia and many more we will also

    requires to use their law especially shall any legal matter arises. This also goes on how the

    payment term will be, and normally the suppliers will ask for the money before the do the

    shipment. We also need to know whether the insurances for the shipment covered by the

    supplier are door to door or until it reach the first port. This shall give a big impact to project

    and not only on the cost but also the risk that we need to take.

    7. GLOBAL MANAGEMENT

    To manage a contract of this magnitude (about USD 1 Billion contract worth) with its myriad

    of complexities pertaining to huge materials, different parties involved, high risk and lethal

    activities, requires a lot of resources, various regulations and permit, personnel from different

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    18/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 18 of 36

    countries and continents and name all other difficulties, an contract management approach that

    is aimed in achieving a cooperative organization is paramount for it success.

    Companies that operate across the international borders need executives and managers who

    understand cross-cultural customs and business practices and how to promote efficiency and

    optimize profitability in that part of global environment. Many corporations purchase supplies

    or sell products in other countries. A construction project in Japan might require buying the

    materials from all over the worlds. The design works were to be carried out by the technical

    expertise from head office in France while the contractor hailed from Malaysia, skilled and

    unskilled workers from China and Philippines, managers and supervisors from Japan and

    Malaysia and the earth moving machines are from Japan.

    Global Management techniques are requires in order operating under these kinds of

    conditions. The following are the issues that the contractor might face while carrying out this

    project;

    Obtaining permits to run a business or construction licence in Japan.

    Complying with the rules for foreigners working in Japan.

    Understanding the employment laws of Japan.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    19/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 19 of 36

    Figure 5: Map of Hokkaido Showing Airport Locations, Roads/Highway and

    Railway track Networking.

    Understand the regulations for import and export construction of materials in and out

    of Japan. For example the import tax for importing lead metal for radioactive

    protection for China the biggest lead exporter in the world.

    Logistics wise e.g. the distances of the job site to all the focal points, terrain of the

    project site and the vicinity, transportation services by air, sea, land or train. This is

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    20/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 20 of 36

    important for delivery of materials for construction works e.g. sand, concrete,

    reinforcement, lead panel and etc. Also required to export of radioactive waste and

    radioactive structures for safe store. Import big truck carrying cement pump for

    entombment construction.

    Infrastructure matters e.g. road, ports, railway and airport for import and export

    materials for construction works. Is going to be used for construction activities and

    also for the workers and machineries to come to the jobsite.

    Facilities such as equipment, telecommunication, electricity, internet and others.

    Despite basic need for workers, telecommunication and internet are also very vital as

    the resources are coming from various parts of the world therefore a lot of

    coordination works need to be done. The telecommunication also important for

    reporting and communicating as the design head office for the French technical

    expertise are based in France. Surely they need to communicate often as complex

    construction will face problem long the process.

    Time zone and physical distance might contribute negative factors. Problem in

    communication to HQ, suppliers and others. Workers might spent night time

    contacting family and love one and might affect their sleep time.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    21/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 21 of 36

    Photo 3: Good road and railway network are requires for transferring the radioactive

    fuel assemblies and sections of the reactor vessel internals to thedry cask storage yard Safe Store area (Connecticut Yankee).

    Government stability, whether the area are safe from riots, war and etc. Any issues on

    the stability might incur the project cost and risk.

    To understand the laws difference as we do not want to offence Japanese laws.

    Sometime the law might differ and therefore we do not want to get trap.

    Finances issues for example the currency stability in order for us to cost the currency

    exchange rate, finance cost and the risk to the project.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    22/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 22 of 36

    Resources consistency This is important as the company might need to mobilise some

    resources e.g. machineries from other countries shall the back up here is in sufficient

    of not consistent. Additional cost might incur as contractor might need to have these

    machineries or equipment in house

    Health and hygiene matters This is important in order for the company to take any

    extra precaution to ensure the workers health and safeties are conserved.

    Security Extra precaution must be considered shall the workplace or the safe store

    yard is unsafe e.g. got pirate or gangs in the vicinity.

    Supervision of workers that come from various places also requires good interpersonal

    skills.

    Project risk. The far the project location from the company head office will normally

    add to higher the risk. This is due to logistic, communication and management of

    resources and reporting.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    23/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 23 of 36

    Photo 4: A truck carrying a cement pump that can extend nearly 200 feet is loaded onto an

    Antonov 124 plane in Stuttgart, Germany. A few of them flown to Japan to help atstricken the Fukushima nuclear power plant.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    24/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 24 of 36

    8. DIFFERENCES IN CULTURE, COMMUNICATION.

    Differences in culture and communications are another two aspects that may ruin the

    successful of global contract shall they have not been address properly.

    Differences in culture

    When talked about culture we cannot denied about the customs, the religion and the mind sets

    as in a way they are somehow rather are interrelated.

    Culture and attitude In order not to create culture confliction with the locals, their

    way of life (Japanese people) should be understood. The things that we all accepted

    well might not be accepted here. It also goes to the staff as the workers are coming

    from various countries, background and races in order keep the harmony and cordial

    working environment, optimise their productivity and interact well with locals, extra

    effort are requires in order to avoid any complications.

    Relevant festive season as the off days also need to be identified and considered in our

    work schedule to avoid unnecessary lost of day work or productivity as some workers

    they will not turn to work on this event with or without the company approval.

    Behaviour. For some workers from different country they might not get along or surely

    will have a conflict if they are requires to work side by side or work along each other.

    A good management should anticipate this matter and split these workers to ensure

    work can goes well and conflicts can be avoided.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    25/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 25 of 36

    Religion is another sensitive issue. Some religion may have some restriction and

    therefore all sensitive issues should be stopped from taking in into the jobsite and may

    need to consider some festive season as off day.

    Understanding the business culture of Japan might help us to manage the project in a

    better manner. Japanese people not easy to trust somebody that they have just met. It is

    a challenge that we need to take.

    Understanding social customs of Japanese people will be an advantage to the project

    other then we need to interact outside the workplace but quite a big number of

    personnel and the suppliers are also Japanese people.

    Communication

    Project communication is a link which connects the major goals of a project: time schedule

    quality expected cost estimated and safety requirement. Communication is important

    because depending on the thoroughness, comprehensiveness and effectiveness of the

    communication; the goals of the project would be perfect and as expected or not.

    From this viewpoint, the objective of this report is to study on various factors impact to

    communication in construction projects and how to improve the communication in

    construction so that it can help and support the construction management team to get the

    planned targets effectively and conveniently.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    26/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 26 of 36

    One of the traits and probably the most important factor in all successful construction projects

    is communication both internal and external. So, how the communication would be helpful for

    construction targets? What effective measures and medium should be used in modern

    construction now? What is the adverse way/manner in construction communication that

    should be avoided and eliminated for ensuring smooth and as good as practice

    performance/activities in construction?

    Communication is the process by which information is exchanged between individuals through a

    common system of symbols, signs, or behaviour. Communication is a two-way process: between the

    sender and the receiver(s). Hence, it is important to consider the receiver not just as a passive recipient.

    Proper communication is vital to the success of a project.

    Most failures in communication can be traced to misunderstandings of the symbols that play an

    important part in the process of human communication. This is mainly due to inadequacies in creating,

    transmitting, and receiving these symbols, both written and spoken. In most companies, executives are

    bombarded with information communicated to them through frequent meetings and dozens of weekly

    status reports provided by every functional area of the business.

    It is an undisputed fact that the quality and frequency of information moving down the organisational

    chart is less consistent. Lack of quality assurance and control in engineering documentation creates the

    opportunity for errors by those who use the documentation in their work. However, in the engineering

    disciplines a great amount of communication within project teams involves symbols that are more

    precise in their meaning compared to the management disciplines.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    27/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 27 of 36

    Basically a project is linked together by its system of communications. The role of the project manager

    (PM) is similar to that of the central server in the local area network of a computer system. The PM is

    responsible for the continuous and comprehensive flow of information to and from team members,

    whilst focusing on communicating information and decisions that may influence the project team

    work.

    The project manager needs to maintain communication links with all project stakeholders. However,

    certain stakeholders require direct and ongoing communication, they are:

    Customers (owners, users).

    Project team members.

    General managers.

    Functional managers.

    Regulatory agencies.

    Subcontractors.

    Suppliers

    Effective project communications ensure that the right information gets to the right person at the right

    time in a cost-effective manner. Communication that is effective consists of:

    An exchange of information.

    A verbal or written message.

    An act or instance of transmitting information.

    A technique for expressing ideas effectively.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    28/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 28 of 36

    A process by which meanings are exchanged between individuals through a common system of

    symbols.

    Most project managers communicate laterally, whereas line managers communicate vertically

    downward to subordinates. Much of the day-to-day work on a project is accomplished by informal

    exchanges of information among team members. Most project managers prefer to communicate

    verbally and informally, one reason also being that formal communication can be costly.

    Project communications includes distributing and channelling information on decisions made, work

    authorisations, negotiations, and project reports. Project managers in excellent companies believe that

    they spend as much as 90 percent of their time on internal interpersonal communication with members

    of their team. Figure 4.3 illustrates the communication channels used by a typical project manager.

    Figure 6: Communication channels used by Project Manager (OUM notes)

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    29/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 29 of 36

    Project team members need to be proactive in initiating timely communication with other team

    members and the project manager. Communications management is the formal or informal

    process of conducting or supervising the exchange of information either upward, downward,

    laterally or diagonally.

    Communications management is vital for effective project performance. Project members

    need to know and understand the action that is to be carried out on a project. It is important to

    consider the following basic concepts of communication theory and practice:

    Only one common language (English) to be used in the project.

    Be as specific, simple, precise and clear as possible about the information to be

    conveyed.

    Know who the receiver is and what are the receivers expectations.

    Design and develop the message with the receiver in mind, keeping in mind the

    receivers role in the project.

    Prompt & instant

    Internal & external

    Suitable & proper for any circumstance

    Effective and productive

    Timely and synchronous

    Friendly and appropriate

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    30/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 30 of 36

    Communication is always an indispensable necessity and demand of individual, collectivity,

    community, and organization. In construction and for construction projects, especially for big

    project or trans-countries project, such regard becomes more and more important. It plays a

    vital role for the link of all resources to create a collective and common force for the well-

    performance of the project, hence bring benefits to every involved individual and team/group,

    company, community and society.

    Building an effective and powerful communication system for a construction project is not a

    simple/easy work at all. It demands good background, expertise platform, life experienced and

    a brain-storming as well as an open soul and inspiration; and of course subject to the

    specificity, particularity and size of the desired construction project.

    All manners and measures are settled for the ultimate goal: the success of the project - meant

    benefits brought to the clients, contractors, supplier, all parties involved, community and

    society.

    The success of construction project also mean success in every phase of the project. Therefore

    the communication plan or method applied to the project should be deployed and mobilized

    effectively and productively through every stage of the construction project such as:

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    31/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 31 of 36

    Planning stage:

    Quite understand the intention of the client; the purposes and functions of the project.

    Deeply discuss and consult with the client for common understanding.

    Collect experience from expert on each specific and particular disciplines of the

    constructed project, to learn the best estimation on technique, technology, cost and

    schedule.

    Anticipate and evaluate the pros and cons for the project; and then exchange, dialogue

    with the client and project team.

    Create a harmonious team which will result in perfect teamwork consists of project

    management, conceptual architects, quantity surveyors and the authorized

    representatives of the client.

    Design stage:

    Clearly classify and discriminate sets of drawings: architectural, structural, mechanical,

    electrical, plumbing, faade, curtain wall, interior, setting-out, schematics, plan and

    section layout.

    Collect and then select a qualified list of designers with the approval from the client.

    Timely and validly update for revised set of drawings or bulletin so that any update of

    drawings is always recorded, documented and controlled.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    32/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 32 of 36

    Construction stage:

    All contractors, subcontractors, suppliers, installer, and others must conform to and

    comply with a very clear, strong and powerful project procedure.

    A very effective and valid method and means of communication is media. This will not

    be interrupted and limited as much as expected on the variant, deformation or

    distortion of the information transmitted to the destination.

    Have an effective mechanism of sending, receiving and feed-back of information.

    A very clear, transparent, friendly and open-minded mechanism for inter-

    communicating between the client, project management and contractors, suppliers.

    Instruction or notices should be prompt, timely, and accurate.

    Close-out stage:

    Clear instruction and schedule for contractors to hand-over.

    Close coordination with the client for taking-over

    Thorough checking for the compliance of local and international codes.

    Documentation of all paper works for hand-over and take-over process.

    External relations and communication:

    To court, to win the popularity, especially for the supports from local authorities and

    press, public opinion.

    To strictly keep the security of adjacent community and environment.

    Keep informing and communicating positively with press and media.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    33/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 33 of 36

    To create opportunity and influence for any possible chance.

    Always consider the very important role of external communication, public and media, and

    especially the support from local authorities and community.

    Important role of ICT and advanced technology:

    Role of ICT information & communication technology plays important and efficient factors

    in project communication. Telecom and Communication equipment/devices in a construction

    project should be sufficient, redundant, back-up and standby and as advanced as possible.

    Computers, servers and routers used in construction site, document control as well as project

    management should be powerful and durable; sufficient to handle a lot of information coming

    at the same time. And also be ready for a satellite leased lines for contingency.

    For a very big project or trans-country/trans-border construction project, an intermediate

    server and/or share-point; share-archive is recommended for convenience and help for inter-

    communication.

    Communication in construction project is the art of control, monitoring, verification, recording

    and documentation. Obviously, a lot of factors affect to the process; positively and negatively

    as well. This requires the project management to be smart to filter and identify what are the

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    34/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 34 of 36

    helpful and active things that bring the advantages and conveniences to the project

    implementation.

    Some common problems that may suffering due to many problems in communication

    management. Are as follows;

    1. Usually skipping communication management or just approaching it shallowly due to lack

    of knowledge in this area.

    2. Problems related to interpersonal communication (such as face-to-face meetings), intra-

    group communication (such as interactions between team members) or inter-group

    communication (such as interactions between main contractors and sub-contractors) occur

    very frequently at many projects. Consequently, projects communication often breaks down

    and projects are likely to be failed.

    3. Unable to determine project stakeholders needs for information, unable to determine

    communication channels in projects, insufficient interaction between project management and

    team members or between main contractor and sub-contractors or within team members,

    inappropriate communication media, etc.

    4. Timing of distributing information, correct information to correct stake holders, wasting a

    large amount of time and resources for unnecessary meetings, etc.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    35/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 35 of 36

    5. Unable to combine verbal communication and non-verbal communication in order to

    achieve targets.

    6. Abusive using of bad emotional methods during interaction between project management

    and team members such as fear and threats, aversive stimulation, etc.

    It is important to understand the nature of the problems and to find ways to solve them in

    order to be able to develop an effective communication management system in construction

    projects. Mr. Nguyen Canh Toan made a study which objectives were to: (1) investigate the

    communication interactions within construction project team so that communication problems

    causing project interruption can be identified; and (2) propose recommendations on how to

    improve communication management within construction project team.

    In order to avoid similar communication problems, recommendations are given below:

    1. Project Manager shall prepare project management plan including communication plan in

    the beginning of the project.

    2. Strictly following the communication plan. Incentives shall be provided to encourage

    everybody to carry it out properly, and also treatments or even punishments for bad

    behaviours.

  • 7/28/2019 Assignment-EMCM (Contract Management) Q2

    36/36

    Name: Mohd. Norizam Bin Md. Salleh

    Matriculation No.: CGS 00534317

    Intake: September 2010

    Assignment EMCM5103

    Question 2 - Page 36 of 36

    3. Document controller position must be stable as much as possible in order to ensure that the

    information distribution process is in order.

    4. In case of ISO certified company, Project Manager should give feedback to the companys

    Quality Manager to add in personality test forms together with Job Application Assessment

    Procedures forms. That will save Project Managers time whenever there is new job applicant

    coming to job site for interviewing.

    5. Using new information-conveying methods such as: web-based data distribution, e-meeting,

    etc. in order for easy document control and timing of document distribution.

    6. Organizing trainings for the team members in order for them to know how to use both

    verbal and non-verbal communication effectively.

    7. Outside activities such as playing football, parties, etc. are recommended to improve

    relationships among team members and between the main contractor and subcontractors.