6
AVAILABILITY BASED TARIFF  India was demarcated into five regional grids, which operate independently. KSEB is the part of the Southern Grid comprising Andhra Pradesh, Tamil Nadu, Karnataka, Kerala and Pondicherry.  In order to meet the increasing power requirements of the states, inaddition to their own generating stations, they have capacity entitlement on Central Generating stations owned by NTPC, NLC and NPC.  ABT is a rational tariff structure for accounting the transaction of energy from Interstate Generating Stations in the Central Sector.  The Central Generating Stations covered under ABT in the Southern Region are the following:  1. Coal based Thermal station of NTPC at Ramagundam.   3*200 + 3*500 MW Stage III           1*500 MW Total                 2600 MW  2. Lignite based thermal stations of NLC at Ney veli NLC II Stage I     3*210 MW NLC II Stage II     4*210 MW NLC I Exp           2*210 MW Total                    1980 MW  3. Coal based thermal station of NTPC in Talcher (Stage II) in Orissa. (Even though the station is in Eastern Region it is constructed for Southern Region) 4*500 MW  4. In addition Southern Region beneficiaries are having some share in Eastern Region NTPC stations at Thalcher I, Kahalgaon and Farakka.  Stations not covered under ABT are  1. Nuclear power station (MAPS) of NPC at Kalpakkam      2*170 MW  2.   Nuclear power station (KAPS) of NPC at Kaiga  2*220 MW  Bilateral transaction and inter regional transaction also come under the preview of ABT ABT has been introduced in Southern Region with effect from 01.01.2003. Pre – ABT Regime  In the Southern Grid, there is a wide variation between the demand and supply. The distinct features of the Southern Grid before introducing ABT are Low frequency during peak-load hours, with frequency going down to 48.0 – 48.5 Hz for many hours every day.

Availability_Based_Tariff

Embed Size (px)

Citation preview

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 1/6

AVAILABILITY BASED TARIFF

 India was demarcated into five regional grids, which operate independently.

KSEB is the part of the Southern Grid comprising Andhra Pradesh, Tamil Nadu,

Karnataka, Kerala and Pondicherry.  In order to meet the increasing power requirementsof the states, inaddition to their own generating stations, they have capacity entitlementon Central Generating stations owned by NTPC, NLC and NPC.

 

ABT is a rational tariff structure for accounting the transaction of energy fromInterstate Generating Stations in the Central Sector.

 

The Central Generating Stations covered under ABT in the Southern Region are thefollowing:

 

1. Coal based Thermal station of NTPC at Ramagundam.   3*200 + 3*500 MW

Stage III           1*500 MWTotal                 2600 M

 

2. Lignite based thermal stations of NLC at NeyveliNLC II Stage I     3*210 MW

NLC II Stage II     4*210 MW

NLC I Exp           2*210 MWTotal                    1980 MW

 

3. Coal based thermal station of NTPC in Talcher (Stage II) in Orissa. (Even

though the station is in Eastern Region it is constructed for Southern Region)

4*500 MW 

4. In addition Southern Region beneficiaries are having some share in EasternRegion NTPC stations at Thalcher I, Kahalgaon and Farakka.

 

Stations not covered under ABT are 

1. Nuclear power station (MAPS) of NPC at Kalpakkam       2*170 MW

 2.    Nuclear power station (KAPS) of NPC at Kaiga   2*220 MW

 

Bilateral transaction and inter regional transaction also come under the preview of ABTABT has been introduced in Southern Region with effect from 01.01.2003.

Pre – ABT Regime 

In the Southern Grid, there is a wide variation between the demand and supply.The distinct features of the Southern Grid before introducing ABT are

• Low frequency during peak-load hours, with frequency going down to 48.0 –48.5 Hz for many hours every day.

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 2/6

• High frequency during off-peak hours, with frequency going up to 50.5 – 51.0Hz for many hours every day.

• Rapid and wide changes in frequency, one Hz change in 5-10 minutes being acommon phenomenon.

• Very low voltages, for substantial period.

• High voltages during off-peak hours, to the extent that even 400 KV trunk lines are required to be switched off to contain the over-voltages.

• Very frequent grid disturbances, causing tripping of generating stations,interruption of supply to large blocks of consumers, and disintegration of the

Regional grids.

Before introducing ABT, the two-part tariff system was prevailing, i.e. the fixedcost and the variable cost  are charged from the beneficiary states/SEBs in the

proportion of the actual energy drawn during a particular period.

Before introducing ABT, if a beneficiary over draws a portion of the otherbeneficiary’s share of power, there was no penalty on those who get the benefit or

there was no compensation for those who suffered.

 ABT Regime 

  Methodology under ABT includes

1. UI charges:  - a payment for deviations from schedule at a ratedependent on system conditions.

The UI charges are payable /receivable if 

(a) a beneficiary overdraws power, thus by decreasing thefrequency

(b) a beneficiary under draws power, thus by increasing the

frequency

(c) a generator generates more than the schedule, therebyincreasing the frequency

(d) a generator generate less than the schedule, there by decreasing

the frequency.Thus, any of the beneficiaries get undue benefit from

overdrawing from the grid, he shall liable to pay to the

affected parties at the UI rates prevailing at the point of time.

The UI rates with effect from 1-10-2004 are given below:-

Average frequency                               

 

50.5 Hz and above                               Below 50.5 Hz to 49.8 for every 0.02 Hz decrease                6.0Between 49.8 Hz to 49 HzFor every 0.02 Hz decrease                            

Below 49.00 Hz                                

2. Capacity charges:- towards reimbursement of the fixed cost of plant,linked to the plants capability to supply MWs,

3. Energy charges:- to reimburse the fuel cost for scheduled generation.

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 3/6

4. Incentive:- Incentive is payable when actual generation is above target

PLF. It is shared as per scheduled ratio.5. Wheeling charges:- States to get wheeling charges based on the actual

energy wheeled.

6. VAR charges:- Ideally all reactive load should be compensated locally.

This basically requires installation of sufficient quantity  of capacitors atSEBs end. In ABT regime there is incentive for reactive energy injection

at low voltages and drawal at high voltages. Similarly there is penaltyfor reactive energy injections at high voltages and drawal at low

voltages.  This mechanism helps to maintain the grid voltage within

permissible limits, thereby ensuring quality supply.  The reactivecharges payable at present are 5.105 Ps/KVARh.

 

 

Scheduling and Load Dispatching under ABT

• Each day of 24 hours starting from 0.00 hour is being divided in to 96 time

blocks of 15 minutes duration.• Each generating station shall make advance declaration of the capacity

available for generation in terms of MW delivery of ex-bus in each timeblock.  The generator shall also ensure that, the capacity available during

peak hours is not less than the capacity available during off-peak hours.

• Based on the declaration of the generating station, the RLDC shallcommunicate to the beneficiary SEBs, their respective share of theavailable capacity.

• The beneficiary shall prepare their schedules from the above, based on theinternal generation availability, variable cost of generation of their own

thermal stations, power purchase facility from other sources and the cost,

system constraints and limitations etc.• Based on the request from the beneficiaries as well as declaration from the

generators, the RLDC shall prepare the generation schedules and drawal

schedules from the CPS for each time blocks after taking into account thetransmission constraints and other systems constraints if any.

• For transmission losses shall be apportioned among the beneficiaries inproportion of their drawls.

• In the case of any constraints, the RLDC have right to revise the schedule,which shall become effective from 4th time block.

• The generator and beneficiaries are also allowed to revise their scheduleduring a day, but such revisions shall be effective only from the 6

thtime

block. 

ABT regime and UI Mechanism have effectively been utilized by KSEB to

optimize the overall cost of purchase of energy.With the introduction of ABT, the performance of the grid has improved

considerably. Number of Grid separation and cascading has been reduced considerably.

The operating frequency band is stable with occasional deviation during system

contingencies. The voltage profile has also improved considerably. All these

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 4/6

achievements can be attributed to the UI mechanism under ABT, which penalizes any

activity against grid security.Presently, KSEB has a total hydel capacity of 1807 MW and has two LSHS based

thermal stations Brahmapuram Diesel Power Plant (BDPP) (106 MW) and Kozhikkode

Diesel Power Plant (KDPP) (128 MW) In addition to this, there are three deemed IPPs

(Independent Power Projects) within the State to meet the power need of the State viz.BSES Kochi 157 MW, NTPC Kayamkulam – 360 MW and KPCL 20 MW.  The present

power allocations from CGS stations are given below. 

CGS Share Details As On 31/08/05

 

Station Installed Capacity % ENTITLEMENT

RSTPS 2100 14.74 309.54

RSTPS U 7 500 15.77 78.85

NLC II Stage I 630 11.63 73.27NLC II Stage II 840 12.32 103.49

MAPS 340 6.27 21.32

KAPS 440 13.12 57.73

NLC I Exp 420 18.53 77.83

Talcher II 2000 17.52 350.40

FSTPS 1600 3.68 58.88

KHSTPS 840 1.36 11.42

TSTPS 1000 1.96 19.60

TOTAL 1162.32 

After the introduction of ABT, KSEB is strictly following the merit order

dispatch based on the variable cost of energy.  The present merit order stack of different

sources based on the variable cost is given below.

Station VC/unit

Rs./Kwh

RSTPS 0.94

RSTPS u 7 1.08

TALCHERII #3,4&5 0.69

TALCHER II #6 0.56

NLC II Stage 1 0.74

NLC II Stage 2 1.01

NLC I Expn. 1.32

MAPS 2.03

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 5/6

KAIGA u#1 3.25

KAIGA u#2 3.25

FSTPP 1.36

KHSTPP 1.41

TSTPP 0.65

RGCCPP 5.26

BSES 5.08

KPCL 3.68

BDPP 3.71

KDPP 3.31

 KSEB is preparing the daily dispatch based on the expected demand and energy

availability from internal sources, the demand of the previous week and previous day,climate, water availability in the hydel  reservoirs, possibility of spill, machine

availability in  the power plants and variable cost of generation of KSEB thermal stations,

BSES, NTPC-Kayamkulam, KPCL and Import power from different sources.During 2004 - 05 our UI import was 497.892 MU at an average rate of 211

PS/unit and export 158.083 MU at 244 PS/Unit.

 

DETAILS OF UI ACCOUNT

UI IMPORT UI EXPORT

Month

ScheduledEnergy from

CGS &ER(at SR

periphery) inLU

BilateralTrading

(PTC,GEL)

Sale ofKYCCPP

Power Qty in LURate

Rs./ unit Qty in LURa

Rs./

Jan 03 to Mar03 12534.58 329.04 2163.41 2305.76 1.62 -22.68 2.3

2003-04 51444.08 815.91 10308.39 7713.03 1.83 -1106.88 3.1

2004-05 58647.01 0.00 5471.67 4978.92 2.11 -1580.83 2.4

  

We have been able to exploit the provisions of UI favorably on several occasions. 

Low frequency regime prevailed in the southern grid during May 05 due to the outages

RSTPS and subsequently in the AP grid. Our generation was maximized to takeadvantage of the situation. To meet the demand, the BDPP, KDPP and IPP’s had to be

scheduled.   Our consumption also touched the all time peak of 41.11MU during this

8/7/2019 Availability_Based_Tariff

http://slidepdf.com/reader/full/availabilitybasedtariff 6/6

period in the absence of pre monsoon showers. By scrupulous and watchful operation of 

the SLDC, we could receive substantial amount as UI charges. We have made a net gainof about Rs.16crores during this period by the timely action taken by SLDC. It is also to

be noted that KSEB had been the constituent, which aided the grid to the maximum

extent during this period. The effective planning and judicious use of our internal

resources for the entire water year helped us in making this achievement.