Page 1: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

www.beveridge-associates.co.uk

BEVERIDGE ASSOCIATES PARTNERSHIP LTD RAIL CAPABILITY STATEMENT

Page 2: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 2 of 44

www.beveridge-associates.co.uk

BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED CAPABILITY STATEMENT – RAIL

1.0 PRACTICE DETAILS

1.01 Name: Beveridge Associates Partnership Limited

1.02 Address for Commission: Regency House Station Road Harold Wood Romford RM3 0BS

1.03 Telephone Number: 01708 336 969

1.04 Preferred Contacts: Neil Jones [email protected]

Alex Foreman [email protected] Gary Paxton [email protected]

2.0 SCOPE OF SERVICE

2.01 Beveridge Associates Partnership Ltd are a practice of Consulting Engineers, who as members of the Association of Consulting Engineers (ACE), Construction Line and Link-Up, the approver of Rail associated companies, provide a range of professional services to their Clients.

2.02 The practice has been working in the rail industry since 1986 and has expertise and experience in the following fields:

a) Electrical Supply and Distribution (including HV, LV, AC and DC)

b) Lighting and Emergency Lighting

c) Cable Management Systems

d) Uninterruptible Power Supplies and Standby generation

e) Earthing, bonding and Lightning Protection

f) Fire Detection and Alarm Systems

g) Fire Suppression, Hydrant and Extinguishing Systems

h) Communication systems including CCTV and PAVA

i) Lifts and other Vertical Transportation Systems

j) Heating Systems

k) Air Conditioning and Comfort Cooling

l) Ventilation and Extract systems

Page 3: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 3 of 44

www.beveridge-associates.co.uk

m) Hot and Cold-Water Systems

n) Public Health and Drainage

o) Compressed Air

p) BMS, lighting and other control systems

2.03 Beveridge Associates Partnership Ltd have particular experience of transport works having undertaken extensive Consultancy works for London Underground, Metronet (previously), Tube Lines, DLR, Network Rail and Transport for London. In addition, the practise has undertaken work for numerous private companies both on the pre-contract stage (for Architects and civils engineers) and in the post contract stage (for D&B Contractors)

3.0 KEY PERSONNEL

3.01 Brief CV’s of the following key personnel are attached as Appendix A. These key members of staff are supplemented with other engineers experienced in Rail projects to suit the size and complexity of the project.

Neil Jones – Director Alex Foreman – Director Gary Paxton – Director Dean Barker – Associate Chris Govey – CAD Manager

3.02 All of the key Designers used are be Chartered Engineers / senior members of the

company. The company as well as being in the Association of Consulting Engineers are also represented with Membership of the Chartered Institute of Building Services Engineers (CIBSE), the Institute of Engineer Technology (IET formerly the IEE) and the Institute of Energy.

4.0 PREVIOUS EXPERIENCE 4.01 Beveridge Associates Partnership Ltd and Staff have extensive experience of a wide

range of project work schemes. Appendix B includes a full list of rail projects undertaken (which exceeds 200no). The following list gives a short list of examples:

Ealing Depot London Underground Maintenance Depot Design work included LVAC design, DC traction design, Shore Supply system, lighting small power and compressed air and cable containment. BA involvement was to prepare a detailed design including working drawings.

Page 4: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 4 of 44

www.beveridge-associates.co.uk

Upminster Depot Maintenance shed This involved lighting, power, main distribution and earthing design. BA involvement was in a design assurance, and site supervision role. Ilford Crossrail Depot BA have been acting as the client representative fire engineer on his project which is on the critical path for the Crossrail project. Great Western Electrification project Including works to Bath, Keynsham, Oldfied Park and Chippendham Station. BA involvement was for electrical and telecommunications design. Marble Arch Station Modernisation Project involves the complete refurbishment of and existing station including the Ticket Office and Hall. BA involvement includes electrical, mechanical and fire engineering designs.

Page 5: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 5 of 44

www.beveridge-associates.co.uk

Shepherds Bush New Station Project involves the complete rebuilding of the station including the Ticket Office and Hall. BA involvement includes electrical, mechanical and fire engineering designs. Bank Station Design of the electrical. Mechanical, fire and Communication services for the new Walbrook (Bloomberg) entrance into Bank Station. LVAC design for signalling supplies Providing on the SSR network in 2008 (to allow for the temporary signalling solution prior to the ATC upgrade). Designs included conventional power supply solutions as well as the provision of rotary frequency converter solutions. Northern Line and Jubilee Line Upgrade Design on power supplies associated with 79no new SERs as well as a new SER and Switchroom at Neasden Depot. District Line Signal Main Upgrade Design calculations for the new 600V 125Hz rotary converter fed signal main along the eastern section of the District Line (Aldgate to East Ham). Various works at Neasden Depot Including renewal of South Ring, design of a new SER switchroom at Neasden Depot and Shed heating and lighting upgrades.

Page 6: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 6 of 44

www.beveridge-associates.co.uk

Design of the main electrical distribution system for the London Underground Back Up Service Control Centre at Pelham Street, South Kensington. Thameslink Tunnels Designs in relation to power supplies, tunnel lighting and fire mains for the inner area tunnels (north of Kings Cross to Blackfriars) on the Network Rail Thameslink Upgrade. Network Rail Substation upgrades Design of DNO back up supplies to signalling supplies at 6no Network Rail substation (South London and Kent). Dockland Light Railway Works to Bank DLR station including staff accommodation, lighting and congestion relief works. Network Rail Regeneration Project Works to over 100no stations and 9no Depots including East Ham, Selhurst, Hastings and Ramsgate to upgrade services. Works included electrical and mechanical system upgrades.

Page 7: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 7 of 44

www.beveridge-associates.co.uk

4.02 In relation to transport works (which it the subject of this document), a full list of Transport projects over the last 15 years amounting to over 200no projects, is included as Appendix B of this document. Further details of other works or specific project information can be provided upon request.

4.03 Beveridge Associates Partnership Ltd Clients in the rail industry include:

1. Transport for London 2. London Underground (including Metronet and Tube Lines) 3. Network Rail 4. Docklands Light Railway 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17.

Virgin Rail Thales Bombardier Transportation Siemens Hotchief Galliard Try Margal Major Projects Mott MacDonald Tony Gee and Partners Pell Frishmann Peter Bretts Assocaites Tony Meadows Associates Balfour Beatty

QUALITY POLICY STATEMENT 4.04 Beveridge Associates are committed to providing a high-quality service to ensure

that the needs of our Client’s are met.

4.05 To achieve this aim adequate resources are allocated to every project, using only competent and suitably qualified staff. All work is checked and approved by a senior member of the Practice at relevant stages of the project.

4.06 Our aim is to adopt a quality philosophy for the whole project, from conception to completion, ensuring all decisions are correctly considered and verified.

4.07 To meet our stated Policy the Practice operates a Quality Management System which is certified to ISO 9001:2015. All personnel employed by, or working on behalf of, the Practice are required to conform to the Quality Management System. In the spirit of this Standard it is our aim to continually improve the system and service we provide.

4.08 Periodic audits are carried out to ensure the system works effectively and efficiently.

4.09 The Directors have the ultimate responsibility and authority for ensuring that the system is soundly understood, implemented and maintained in compliance with ISO 9001: 2015 and is effective at all levels in the Practice.

Page 8: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 8 of 44

www.beveridge-associates.co.uk

APPENDIX A

CVS OF KEY PERSONNEL FOR

ANTICIAPTED PROJECTS

Page 9: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 9 of 44

www.beveridge-associates.co.uk

NAME: Neil D Jones

QUALIFICATIONS: BEng (Hons), CEng, MCIBSE, MIET, MEI

EXPERIENCE: Trained as an Electrical Engineer with Troup, Bywaters and Anders. Progressed

from a trainee to a full Design Engineer and gained experience in a variety of

industrial, commercial and public-sector projects.

In 1986 joined the London Borough of Waltham Forest as an Electrical Engineer

responsible for ‘Capital’ projects. Was responsible for the design and

specification of a large number of local authority projects.

In 1991 took up a position with the City of London and carried out the design

and specification of a wide range of projects. Gained particular experience in

commercial office projects and listed buildings, as well as specialist projects

such as the part refurbishment of the London Metropolitan Archives storage

facility designed to meet the exacting requirements of BS5454.

Joined Beveridge Associates in 1996 in the position of Associate and has since

become a Director of the practice.

Has undertaken work for a wide range of Clients at Beveridge Associates

including the Barbican Centre, City of Westminster, The City of London,

Employment Services, GlaxoSmithKline, Gartmore Investment Management,

Leyton Orient F.C., London Underground Limited, London Boroughs of Barking

and Dagenham, Camden, Havering, Islington and, Lambeth, Network Rail,

Orbiton Estates, Southwark and Waltham Forest, Network Rail, Dockland Light

Railway, The Prudential, UBS Bank, and others.

Has extensive design experience in relation to all aspects of electrical design

including electrical distribution and generation (including DC), lighting, power

and data systems, fire alarms, security systems, earthing and lightning

protection. Projects include small works to £multi-million projects such as the

Metropolitan Line Upgrade, the new Shepherds Bush Underground Station,

Ealing Depot upgrade, new electrical distribution to City Point and London Wall

Buildings, the new District Line East Power (Signal Main) Supply project, the

rewiring of the Barbican Centre, Thameslink Tunnel upgrade and many others.

Has worked in the rail sector since first joining Beveridge Associates in 1996 had

first hand design experience on a large number (over 100no) of Railway projects

including, the following projects where extensive engineer design and the role

of Project Engineer was also included and a number of projects where he has

acted as CRE.

Page 10: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 10 of 44

www.beveridge-associates.co.uk

Ealing Depot – major upgrade project for S& train stock. Acting as Project

Engineers and also carrying our design work for the DC Shore Supply system.

Co-ordinating all other disciplines includes the LVAC, mechanical and specialists

systems (e.g. screen wash and de-icer systems).

Upminster Depot – work as E&M Engineer seconded into LU for the S7 train

upgrade project at the Depot. Responsible for all aspects of the electrical

assurance and for dealing with site queries and project handover.

Northumberland Park Depot – Design of a new emergency lighting installation

for the Maintenance and Lifting sheds. Design of a new points heating

installation.

Shepherd’s Bush Station – Major works designed in a way that allowed the

station to remain open. The Project involved the complete demolition of the

station at street level and replacement of a new station building. Services

included two new sub-stations, new electrical distribution, a new fire alarm

system as well as the usual mechanical, electrical and fire services for the

building.

Marble Arch Station – This was a station modernisation project for Metronet

undertaken as part of the PPP contract. Works included the reconfiguration of

the ticket office level to relieve congestion, and all works were planned to

ensure the station remained open. System renewals included electrical

distribution, lighting, small power, PA, CCTV, help points, staff HVAC, the fire

alarm system and public health systems.

LVAC Power Supplies for Metropolitan and District Line – Design of power

supplies to Signalling equipment at 30no Metropolitan and District Line sites.

New District Line Signal Main – Design of a new 600V 125Hz Signal Main with

three injection points covering all new signal supplies between Campbell Road

(Bow) to Barking Sidings.

Knightsbridge Station – Design of the CMS and lighting in relation to the station

modernisation at the station.

Thameslink Tunnels – Design of new lighting within the inner area tunnels for

Thameslink, including the design of new power injection positions at various

sites along the route.

Bank Station – various feasibility studies in relation to congestion relief. These

developed into various work streams including Involvement in the full design of

the new Walbrook Entrance planned for the Waterloo and City line part of the

Page 11: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 11 of 44

www.beveridge-associates.co.uk

station. Undertook a Project Engineers role covering the D&M, Comms, Fire and

Systems Engineering.

Tower Hill Station Step Free Access – new scheme to provide step free access

to a station where a developer was constructing a building over the station.

Various Network Rail Station and Depot upgrades (Station Regeneration

Project) – involving works to various M&E systems at approximately 100no

stations and 9no Depots covering the South Coast to the Norfolk coast. This

project lasted for over 5 years and involvement was form feasibility stage

through to completion with work ranging from minor equipment replacements

to full Depot upgrades.

Kennet Station and Charing footbridges – Lighting, earthing and electrical

design for a new footbridge replacing a level crossing. Acted as NR CRE for the

project.

LU Piccadilly Line Power Upgrade – Power Engineer role for the design of the

upgrade of substations at Manor House LU Substation and Mansell Street LU

substation.

Uckfield Line – platform extension early stage design for 8no stations. Lighting,

earthing, Comms and electrical design. Acted as CRE for the project.

London Overground New Gatelines – new Gatelines at Woodgrange Park and

Wanstead Park Stations including new lighting, small power, containment and

EMC assessment.

DLR Bank – several project works including a review and feasibility design into

an updated smoke vent system; a project for new staff accommodation in the

DLR part of the station and a role as Fire Engineer for the blockade works during

the station upgrade.

DLR Royal Victoria – Project Engineer for the E&M and Comms systems for the

new canopies project, including the provision of a new LVAC Switchroom.

Dockland Light Railway – lighting upgrade to 4no stations (West India Quay,

Heron Quay, Pontoon Dock and Tower Gateway. New containment, earthing

and consideration of EMC issues.

Page 12: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 12 of 44

www.beveridge-associates.co.uk

NAME: Alex G Foreman

QUALIFICATIONS: BEng (Hons), CEng, FCIBSE

EXPERIENCE: Joined the industry in 1986 and trained as a Mechanical Design

Engineer with Troup Bywaters and Anders, after a period of

apprenticeship in manufacturing.

Progressed from Trainee to senior Engineer over a period of nine

years, gaining experience on a wide range of projects, including

education, entertainment, healthcare, commercial, leisure and judicial

buildings. Also experienced in large site infrastructure schemes.

Experienced in design, on-site supervision, commissioning and

preparation of expert witness reports for litigation and arbitration.

Joined Beveridge Associates in the position of Associate in 1996 and

has become a Director of the practice.

Has particular interest in low energy schemes and has worked on a

number of projects involving the use of solar hot water heating, grey

water reclamation and other renewable energy sources.

Has undertaken work for a wide range of Clients at Beveridge

Associates including Atlantic Estates, Barbican Arts Centre, City of

Westminster, The City of London, Employment Services,

GlaxoSmithKline, UBS Warburg, Gartmore Investment Management,

Leyton Orient F.C., London Underground Limited, London Boroughs of

Barking and Dagenham, Camden, Havering, Islington, Lambeth,

Newham, Southwark and Waltham Forest, Network Rail, The

Prudential, UBS Bank, and Xansa Plc and others.

Has extensive design experience in relation to all aspects of

mechanical design including heating, ventilation, air conditioning,

control systems, hot and cold-water distribution and drainage.

Projects include small works to £multi-million projects such as the

new the Job Centre Plus roll out programme (100+ sites),

refurbishments of 4no Network Rail Depots, upgrading of UBS City of

London premises and the Bank Walbrook development.

Page 13: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 13 of 44

www.beveridge-associates.co.uk

SPECIFIC RAIL PROJECTS (selection):

Has had first hand design experience on a large number of Railway

projects including, but not limited to, the following projects where the

role of Project Engineer was also included:

East Ham and Ilford Depot – Undertook the role of Lead Mechanical

Designer (HVAC and Public Health). Major upgrade of services to allow

for the new train operating companies to be made responsible for

future maintenance. System renewals included water distribution

systems, mechanical plant, lighting and electrical distribution. Led the

services design team in terms of co-ordination.

Willesden and Wembley Depots – Undertook the role of Lead

Mechanical Designer (HVAC and Public Health). Projects to improve

environmental conditions at the Depots. The major works within the

projects included new fuel storage and delivery systems.

Bank Station DLR – Undertook the role of Lead Mechanical Designer.

Project for DLR and London Underground to design the replacement of

Major Smoke Extract fans in the DLR part of the station. The design was

to fit in the confines of the existing station, with work required to be

carried out in a way allowing the station to remain open whilst

increasing the capacity by 100%.

Bank Station LU – Undertook the role of Lead Mechanical Designer

(HVAC and Public Health). First involved in various feasibility studies in

relation to congestion relief. This then developed into a full design of

the new Walbrook Entrance planned for the Waterloo and City line

part of the station.

Moorgate Station – MEP Works for 21 Moorfields (LU) – Lead

Mechanical Designer (HVAC and Public Health). Major works at station

to create space for the 21 Moorfield development, designed in a way

that allowed the station to remain open. The ‘works included a new

CER, rerouting of the station sub-main system, new electrical supplies,

station wide smoke ventilation, drainage, cooling, lighting, fire and

communications works.

Shepherd’s Bush Station – Lead Mechanical Designer (HVAC and Public

Health). Major works designed in a way that allowed the station to

remain open. The ‘Above Ground Project’ involved the complete

Page 14: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 14 of 44

www.beveridge-associates.co.uk

demolition of the station at street level and replacement of a new

station building. Services included two new sub-stations, new

electrical distribution, a new fire alarm system as well as the usual

mechanical, electrical and fire services for the building.

Marble Arch Station – Lead Mechanical Designer (HVAC and Public

Health). This was a station modernisation project for Metronet

undertaken as part of the PPP contract. Works included the

reconfiguration of the ticket office level to relieve congestion, and all

works were planned to ensure the station remained open. System

renewals included electrical distribution, lighting, small power, PA,

CCTV, help points, staff HVAC, the fire alarm system and public health

systems.

Gray Inn Road – Lead Mechanical Designer. Design of Mechanical

Services for London Underground office support staff.

Baker Street Control Room – Lead Mechanical Designer. Design of new

HVAC system for control room requiring to operational 364 days a year.

Ramsgate and Hastings Depots – Lead Mechanical Designer for water

distribution renewals at the Depots.

Piccadilly Circus Station – Lead Mechanical Designer for a project to

investigate and design replacement cooling at the station.

Thameslink Tunnels – Undertook the role of Mechanical/Fire

Engineer. The project included the design of new lighting and fire

mains within the inner area tunnels for Thameslink, including the

design of new LFEPA inlet connection points.

Cockfosters Depot – Undertook the role of Lead Public Health Engineer

for the design of a new drainage system within the main Shed Building

at the Depot.

Neasden Depot – Undertook the role of Lead Mechanical Designer for

various works at the Depot. Key work included woks to the gas main

distribution about the site; the design of heating for the wheel lathe

shed and cooling for equipment rooms.

Eurostar Training Facility – Undertook the role of Project Engineer

and Lead Mechanical Design for a new training facility at the Eurostar

Depot to allow fire fighter and evacuation training for staff.

Page 15: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 15 of 44

www.beveridge-associates.co.uk

NAME: Gary R Paxton

QUALIFICATIONS: BEng, MSc, CEng, MCIBSE, MIET

EXPERIENCE: Served a formal electrical apprenticeship with an

NICEIC, ECA approved electrical contractor and learnt various aspects

of the installation, testing and commissioning of electrical services in

buildings.

In 1979 joined the Corporation of London as a Junior Engineer and

responsible for carrying out surveys and preparing design drawings.

Also, organised contractors to carry out minor maintenance and

breakdown repairs. Promoted to a Design Engineer at the Corporation

of London in 1983 undertaking the design and specification of a

number of local authority and commercial projects.

In 1985 joined Troup Bywaters and Anders as an Electrical Design

Engineer and widened his experience by carrying out the design and

specification of a broad range of projects in health care, school,

commercial offices and retail.

In 1986 joined the Corporation of London as a Senior Electrical Design

Engineer responsible for the design and contract administration of

electrical engineering services for all types of construction works,

including commercial offices, schools, housing and specialist

installations at the Museum of London and the London Metropolitan

Archive storage facility etc. In addition, was responsible for the line

management of mechanical and electrical Design Engineers.

Promoted to Group Engineer at the Corporation of London in 1990.

During this period was appointed project lead on high value

engineering projects and also gained extensive experience in project

management.

Joined Beveridge Associates in 2007 as a Director. Since joining has

gained experience on a variety of electrical projects including a City

office refurbishment for a prestigious Client, London Underground

transport projects such as the provision of new electrical services for

Signal Equipment Rooms along the Jubilee, Northern and Piccadilly

railway Lines, Local Authority school extension and the

refurbishment of electrical services within the City of London

Guildhall Library and Guildhall School of Music and Drama.

Page 16: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 16 of 44

www.beveridge-associates.co.uk

SPECIFIC RAIL PROJECTS (selection):

Has had first hand design experience on Railway projects including,

but not limited to, the following projects:

Tube Lines new Signalling System – Undertook the role of Lead

Electrical Design Engineer for Signal Equipment Rooms a project

involving an electrical design for new Signal Equipment Rooms at

every station on the Jubilee and Northern Lines for the new Thales

signalling system.

Neasden Depot SER – Undertook the role of Lead Electrical Design

Engineer for a new Signalling Equipment Room and associated new

Switchroom at the Depot.

Neasden Depot Electrical Distribution – Undertook the role of Lead

Electrical Design Engineer for a new electrical distribution system (the

north ring main distribution system).

Great Western Electrification Project – Undertook the role of Project

Engineer and Lead Electrical Design Engineer for the line electrification

project in the Bath area, including station works at Bath, Keynsham,

Oldfield Park and Chippenham. Design works include power supplies,

lighting, earthing and telecommunications.

Victoria Line UPS Assessment – Undertook the role of Electrical

Design Engineer on this project to investigate, report and make

recommendations on UPS systems and associated hydrogen emissions

for all Victoria Line stations.

Metropolitan Line Signal Equipment Rooms – Undertook the role of

Lead Electrical Design Electrical and fire design for a new trance of

Signal equipment rooms for the Metropolitan line.

Parsons Green Stations – Undertook the role of Electrical Design

Engineer for a Staff Accommodation upgrade at the station including

locker accommodation, training rooms, mess areas and offices.

Highgate Service Control Centre – Undertook the role of Lead

Electrical Design Power Supply design for the new Northern Line

Page 17: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 17 of 44

www.beveridge-associates.co.uk

Service Control Centre including a modular UPS system and electrical

distribution.

Paddington Station and Hammersmith Depot – Undertook the role of

Lead Electrical Design Engineer for a project to provide Power

supplies for point heating kiosks at these sites. Hammersmith includes

the design of an IT supply.

Ilford Crossrail Depot – Undertook the role of Electrical Engineer, in

an advisory capacity to the Design Team and for Crossrail.

ATC Signaling Project – Undertook the role of Lead Electrical Design

Engineer for works at Old Dalby Test track to investigate the new

signalling system. The design included extensive IT power system

design for trackside equipment.

Sub-Surface Station Upgrade – Undertook the role of E&M Discipline

Engineer in a secondment arrangement to London Underground. The

work includes the design of 50+ SERs and the design work undertaken

included CMS and power design.

End State Track Layout Project – Undertook the role of Project

Engineer, electrical Surveyor and Engineer for survey and

investigation works at Aldgate and Edgware Road stations for systems

at platform ends.

London Underground Back Up Services Control Centre (BUSCC) –

Undertook the role of Lead Electrical Engineer for the Back Up Control

Centre project at Pelham Street, South Kensington, including design

for electrical distribution and robust back up power systems for the

building.

Eurostar Training Facility – Undertook the role of Lead Electrical

Engineer for a new training facility at the Eurostar Depot to allow fire

fighter and evacuation training for staff.

District Line Earthing – Undertook the role of Lead Electrical Engineer

on a project investigating and addressing earthing issues on District

Line station platforms.

OPO Upgrade Project – undertook the role of Electrical Design

Engineer for the OPO project covering the District Line stations. The

design work included power supply and cable route management

systems for Communications equipment.

Page 18: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 18 of 44

www.beveridge-associates.co.uk

NAME: Dean Barker

QUALIFICATIONS: Associate, HNC, APMP

EXPERIENCE: Joined the industry in 1986 and trained as a

Mechanical Design Engineer with Troup Bywaters and Anders, after a

period of apprenticeship based on site to get an understanding of site

works, inspection and commissioning.

Joined John Lewis Partnership in 1990 as a Mechanical Design

Engineer progressed to Senior Project Engineer. Undertook HVAC

detailed design projects for Waitrose supermarkets and John Lewis.

Progressed to overseeing consultants and contractor’s designs on

HVAC, refrigeration, sprinkler and public health works packages in a

senior managerial role.

Took up an Associate Director position with Cunnington Clark Ltd in

2005 Gained substantial renewable energy experience as a Low

Carbon Consultant and gained BREEAM accreditation.

Clients included London Borough of Tower Hamlets School Projects,

Huntingdonshire Regional College, Hampton Community School,

Peterborough, Anglian Ruskin University, Honda Car Showrooms,

IKEA, Center Parcs, Batchwood Golf and Bowls Pavilion, Rezidor Hotel

Chain, Park Inn Hotels Broad Lane Residential Development, Damien

Court Housing Development, National Grid Hurst Power Station-

Bexley, Warminster Town Council Offices and Shanks Recycling

Centre.

Joined Beveridge Associates in the position of Senior Mechanical

Engineer in 2013. Since joining has worked on transport projects for

clients such as London underground, Transport for London and

Network Rail. Has also undertaken key local authority projects

including the Capita works programme for the London Borough of

Newham Education department.

Became an Associate in the company in 2016 and has taken a lead

role in many key projects.

Page 19: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 19 of 44

www.beveridge-associates.co.uk

SPECIFIC RAIL PROJECTS (selection):

Moorgate Station – MEP Works for 21 Moorfields (LU) – Mechanical

Designer (HVAC and Public Health). Major works at station to create

space for the 21 Moorfield development, designed in a way that

allowed the station to remain open. The ‘works included a new CER,

rerouting of the station sub-main system, new electrical supplies,

drainage, cooling, lighting, fire and communications works.

Moorgate Station: Smoke Ventilation System – Lead Mechanical

Engineer for the design of a new smoke ventilation system to cover

the Metropolitan Line area of the station (platforms 1 to 6). Complex

design required to fit large plant into an existing operation station.

The project includes significant interfaces with many parties.

Norwich Crown Point Depot – Undertook the role of Lead Mechanical

Design Engineer for a project involving replacement and upgrading of

the Mechanical heating and domestic water services installation within

the maintenance shed and Amenity Block.

Ealing Common Depot – Undertook the role of Lead Mechanical / Fire

Design Engineer Concept design for new elevated 45,000 litre fire main

tank for the site., as well as new compressed air, heating and a

specialist de-icer and screen wash distribution system.

Westminster Station – Undertook the role of Lead Mechanical Design

Engineer Concept design of mechanical services infrastructure for 2no

new retail concessions at platform level and another at upper

concourse level in the station.

Ilford Crossrail Depot – Undertook the role of Mechanical Engineering

Surveyor for surveys of existing mechanical service infrastructure and

commentary on consultant’s proposals for new proposed building

works within the existing Tunnelling Academy Building.

Sub-Surface Station Upgrade – Undertook the role of E&M Discipline

Engineer in a secondment arrangement to London Underground. The

work includes the design of 50+ SERs and the design work undertaken

included ventilation and cooling design for the SERs. Part of the role

included mechanical strategy decision making and company

presentations.

Page 20: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 20 of 44

www.beveridge-associates.co.uk

NAME: Christopher Govey EngTech LCIBSE

QUALIFICATION: CAD Manager

Incorporated Engineer

LCIBSE

EXPERIENCE: Trained as an Architectural Technician on drawing board, and later as

a CAD Technician at HKL Associates where project experience

comprised of commercial and residential projects.

Later joined EF Engineering and specialised in plant and equipment

production drawings including 2D and 3D presentations and complex

assembly drawings. Gained experience in different engineering

disciplines including electrical supplies, and air/water cooling systems.

Joined Beveridge Associates in 2002 as a CAD Technician. He has since

specialised in Mechanical and Electrical co-ordination works and

multi-service integration. He is skilled in the use of AutoCAD, Bentley

Microstation and BIM, and manages the in-house CAD Department.

Chris has gained extensive experience on a variety of transport

projects including complex electrical, mechanical, communication and

public health projects. Can produce detailed complex co-ordinated

services drawings in 2D and 3D formats.

EngTech Qualification and LCIBSE Membership acquired May 2013.

Recent project experience includes Barbican Centre, Guildhall School

of Music and Drama, Queen Elizabeth Hunting Lodge, various Schools

for the London Borough of Newham and Islington.

Railway projects includes extensive works on over 100no projects

including large scale projects such as such as Shepherds Bush new

station, Marble Arch Station Modernisation, Waterloo International

Terminal Platform 19 and 20 conversion, Jubilee and Northern Line

Signalling Upgrade, New District Line Signalling Main, Bank Walbrook

new Entrance, Moorgate station and many others.

Page 21: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 21 of 44

www.beveridge-associates.co.uk

APPENDIX B

RAIL EXPERIENCE OVER THE LAST 15 YEARS

Page 22: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 22 of 44

www.beveridge-associates.co.uk

Job No. Direct Client Project Title Project Description BA Involvement

CURRENT PROJECTS

17070 Network Rail / IPS St Pancras Station Survey, review and recommendations on works to 14no UPS systems about the station

Survey, report and design work – UPS systems

17067 London Underground / PBA Woodford Station and Leyton Station

Open area platform relighting to address issued with poor CCTV images

Survey and electrical design

17057 London Underground Upminster Depot Extension of Roads 35 and 36 to the east of the Lifting Shed

Electrical design and CAD assistance for LU internal civils and drainage

17034 London Underground Earls Court Station New power supply for point heating kiosks, includes the design of an IT supply

LVAC electrical design

17026 London Underground Farringdon Station New power supply for point heating kiosks, includes the design of an IT supply

LVAC electrical design

17025 London Underground / PBA Park Royal and Sudbury Town stations

New public area lighting for the 2no stations Survey, electrical design including lighting containment and distribution

17020 London Underground Tower Hill New power supply for point heating kiosks, includes the design of an IT supply

LVAC electrical design

16080 London Underground / Pell Frischmann

Ealing Depot – Maintenance shed

Major upgrade to the Depot to allow for the maintenance of the new S7 train stock

Complete E&M design including DC, LVAC, lighting, power and mechanical services

16080A London Underground / Pell Frischmann

Ealing Depot – new De-Icer and Screen Was distribution system

Design of a novel system for Depots to distribute de-icer and screen was fluid about the site

Specialist design for these systems

16061 Docklands Light Railway / SMB West India Quay, Heron Quay, Pontoon Dock and Tower Gateway DLR stations

New public area lighting for the 4no stations Survey, electrical design including lighting containment and distribution

Page 23: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 23 of 44

www.beveridge-associates.co.uk

16020 Land Securities Moorgate Station Smoke Ventilation System

Design of a smoke control system for the Metropolitan area of the station (platforms 1 to 6), including dual electrical supplies and a new electrical incomer

E&M and fire design

15029 Network Rail / Tony Gee Great Western Line, Bath Corridor Electrification Scheme

Design to allow for the electrification of the trains along he Bath corridor including station works at Bath, Keynsham, Oldfield Par and Chippenham

Electrical, earthing &telecommunications design

15028 London Underground Moorgate Station MEP Enabling

The design of a major relocation of services to allow for the construction of a new development over the station

E&M, Comms and Fire design with associated civils and premises

14051 Crossrail / MM Ilford Depot Remodelling of the existing Network Rail Depot at Ilford for Crossrail

E&M surveys; E&M design reviews; Client Fire Engineer

RECENT PROJECT (LAST 5 YEARS)

17016 Galliford Try Wolverhampton Station New major station building to provide increased capacity to the station along with new retail facilities

EMC Engineering and NR CRE

17004 London Underground Lillie Bridge Depot New power supply for point heating kiosks LVAC electrical design

16068 London Underground / Balfour Beatty

Farringdon Station Decommissioning of existing communications and electrical services to allow for future works

Electrical and comms design

16017 Network Rail / Tony Gee Peckham Rye Access for All A step free access project involving the installation of 3no lifts into an operational station

E&M and Lift design

16007 London Overground / Pell Frishmann

Gospel Oak to Barking, New Gatelines

New Gateline design for Wanstead Park and Woodgrange Park stations

Electrical design

16004 & 15050

London Underground Paddington Station and Hammersmith Depot Kiosks

Power supplies for point heating kiosks at these sites. Hammersmith includes the design of an IT supply

Electrical power design

15050 London Underground Hammersmith Power Design Design for power to point heater and signalling assets at Hammersmith Depot

Electrical design

16075 Galliford Try Newton-le-Willows Station New station building with step free access EMC Engineering and NR CRE

15048 Network Rail / Tony Gee Eridge Station Step Free Access

Provision of step free access via a new lift, new stairs and the demolition of an existing overbridge

E&M and telecoms design

15047 Network Rail / Tony Gee Earls Court Southern Deck New over-decking of an existing rail section (500m) to form a new tunnel

Electrical and fire design

Page 24: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 24 of 44

www.beveridge-associates.co.uk

15034 London Underground New SERs for the LU signalling upgrade

Construction and fitting out of 50no SERs for the Thales signalling upgrade

Electrical and Mechanical design assistance

15012 DLR / Pell Frishmann Royal Victoria Station Canopy renewal

Renewal and extension of platform canopies including new lighting and Comms

E&M and Comms design

14085 London Underground Piccadilly Line Substation Upgrades

Major substation upgrade programme. BA involvements at several locations including Cobourg Street, Manor House, Boston Manor and Mansell Street

HV Power and E&M design

14061 London Underground Upminster Depot Remodelling of the existing London Underground Depot for S7 train stock

E&M Client Site Engineer Role

15055 London Underground / Hawkins Brown

Stanmore Station Step Free Access

Feasibility Study for step free access options E&M, Comms and Fire design

15016 London underground / Pell Frishmann

Colindale station Capacity Enhancement

Provision of a new station building to replace the existing. E&M and Comms design

14027 DLR / Pell Frishmann DLR Blackwall Station, new access

New access and egress from the station E&M and Comms design

14101 Jenkins and Potter Ealing Common Depot Fire Tank

New 45,000 litre fire tank for the Depot E&M Design

14098 Keltbray / Margal Moorgate Station Temporary works design for the 21 Moorfields Development over the station

E&M, Comms and Fire design

14095 Network Rail / KN Ravensborne Station Temporary platform and overbridge lighting to allow bridge refurbishment

E&M Design

14094 Transport for London Westminster Station Provision of two retail units on the platforms of the D&C Line

E&M and structural design

14088 London Underground End State Track Layout Project E&M surveys of station and trackside facilities at Aldgate and Edgware Road

E&M Surveys and report

14083 Network Rail / Tony Gee Uckfield Line platform lengthening project

Major platform extensions to 8no stations on the Uckfield Line

E&M and Comms feasibility

14082 London Underground / Margal Baker Street Under Platform lighting

Design of new LED under platform lighting (for trial purposes)

E&M Design

14077 London Underground Neasden Depot – Schematics Surveys of the existing electrical distribution system in order to provide an up to date set of schematic diagrams for the site

Electrical surveys and schematics

Page 25: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 25 of 44

www.beveridge-associates.co.uk

14097 TMA West Brompton Station Feasibility study for the provision of step free access t the station

E&M, Comms and Fire Feasibility

14074 London Underground/ CB Services Canary Wharf Station Retail Units

Conversion of staff accommodation and toilets to retail units

Mechanical design

14073 London Underground / KN Hammersmith Service Control Centre

Upgrade of the electrical distribution system Preparation of isolation plans

14072 London underground Hammersmith Depot – De-Icer plant

Installation of Glycol plant for de-icing purposes within the Depot

Fire Strategy and risk assessment

14066 Lynch IEI 4no Jubilee Line Stations Replacement of C50 distribution boards Preparation of isolation plans

14065 London Underground / Margal Upminster Station Lighting for extended platform area E&M Design

14047 London Underground / Emico Parsons Green Sidings New trip cock lighting E&M Design

14045 London Underground Cockfosters Depot New drainage installation of the main shed E&M Design

14039 network Rail / BAM Nuttell Emmanuel School Bridge across track – Battersea Rise

Lighting, water and power design works associated with a anew bridge being installed to allow for retaining wall works

E&M design

14036 Transport for London Paddington Station – new retail opportunities

Services design associated with new retails faculties E&M, Comms and Fire design

14007 Network Rail / Emico Norwich Crown Point Depot Heating and boiler room replacement works Mechanical design

14004 Network Rail / Tony Gee Motts Lane Footbridge Lighting of a new substation footbridge near Witham Station

Lighting and electrical design

14002 London Underground / TEIS Neasden Depot Lighting and heating upgrades to the Wheel Lathe Shed E&M Design

13061 London underground / Pell Frischmann

Hammersmith Station entrance works

New entrance to the station for congestion relief purposes E&M design

13025 Network Rail / Tony Gee Kennet Footbridge A new footbridge at Kennet station Lighting and service diversion design

13059 Crossrail / Morrison Water diversion works – East London

Diversion of water and drainage utility pipework to allow Crossrail works

Water and drainage design

Page 26: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 26 of 44

www.beveridge-associates.co.uk

13045 Dyer & Butler S7 Stopping markers – District Line

Installation of new platform end equipment at 8no station Earthing design

13025 Network Rail / Tony Gee Charing Footbridge A new footbridge at Charing station Lighting and service diversion design

13012 TMA Elephant and Castle Station Future Stations Project

Feasibility study into increased capacity at the station E&M, Fire and Comms advice

13008 London Underground Upminster Depot Power Supply Reinforcement

Provision of new dual HV supply to the Depot Electrical feasibility study and scope document

12111 London Underground Back up Supply – Service Control Centre (BUSCC)

Electrical power design for the supplies to the back up control centre for the SSL lines

Electrical design

1261 TMA Bank Walbrook New entrance for Bank Station Electrical, mechanical, fire and Comms design

1258 Network Rail / Siemens 6no NR Substation signalling backup power supply

Provision of backup power supplies to signalling equipment 6no network rail substations

Electrical design

1256 TMA DLR Beckon Project to enhance and improve the station entrance Electrical and lighting design

0739 Thales Rail Signalling Solutions Ltd (for Tube Lines)

Jubilee and Northern Line Upgrade (Signalling systems)

LVAC works in relation to the Signalling upgrade on the two lines, including the design of electrical services within SERs at 79no station / Depots.

Electrical

12109 Eurostar Training simulator Construction of a replica area of the Channel tunnel and Euorstar for training purposes

E&M and Fire design

12101 Network Rail / Siemens Ardsley Sub-station replacement

Installation of a new substation to serve track supplies at Ardsley

LVAC design

1299 DLR Bank Station 2012 / 2013 blockade works

Works to track and DLR station during the Christmas / New year network closure and station blockade

Fire Strategy

1270 TMA Embankment Station Future Stations Project

Feasibility study into increased capacity at the station E&M, Fire and Comms advice

1294 LU / Margal Platform Train Interface – Lighting works

Upgrade to lighting at 6no stations due to the new PTI works

Lighting and associated electrical design

Page 27: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 27 of 44

www.beveridge-associates.co.uk

1293 Network Rail / Tony Gee Stockley Close Site Distribution

Electrical design for a 48no cabin site enclosure Electrical distribution design

1291 Emico / Network Rail Nottingham TTO Electrical, Mechanical and Comms design for a temporary ticket office at Nottingham station

BA are acting as design checker

1280 IPS / London Underground OPO TT CCTV at 27no stations New track to train OPO system at 27no District Line station Electrical and CRMS design

1271 London Underground Neasden Depot Main Cable Works

Replacement on main LV South Ring serving Depot Electrical design and project management

1270 TMA Victoria Station Future Stations Project

Feasibility study into increased capacity at the station E&M, Fire and Comms advice

1269 TMA Holborn Station Future Stations Project

Feasibility study into increased capacity at the station E&M, Fire and Comms advice

1215 Birse Oxford Circus CTP Cooling the Tube project at Oxford Circus station and adjacent Western House

Misc E&M and Fire design for parts of the project

1137 Network Rail / McNicholas / Emico Thameslink Upgrade (Inner Area Tunnels)

Designs for various works within the Inner Area tunnels (North of Kings Cross to Blackfriars) in particular new power supply sites, tunnel lighting and tunnel fire main

Electrical and mechanical design

1237 First Group City Thameslink power failures Investigation into power failures at City Thameslink Station Electrical surveys and investigations

1227 Network Rail / Tony Gee Bedford Footbridge New footbridge in area over Bedford Depot and main line track

Electrical and lighting design

1221 Network Rail / Tony Gee London Bridge Condition Survey

Survey and condition report on existing station prior to major works

Electrical, mechanical, fire and Comms

1203 London Underground Neasden Depot Site Utilities Upgrade of fire mains and gas supplies across the site Fire main and gas design

PROJECTS 5 YEARS +

1186 Network Rail / IPS East Croydon Station Design works in relation to refurbishment of the Staff accommodation

Electrical and mechanical design

Page 28: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 28 of 44

www.beveridge-associates.co.uk

1179 Network Rail / Margal Beaconsfield Station Refurbishment

Works in relation to new canopy lighting and the lighting of a new temporary over-bridge as part of the station refurbishment works

Electrical design

1155 YJLi / IPS Highbury and Islington Station New Entrance

Design in relation to a new entrance to the station for congestion relief purposes

Electrical design

1148 DLR Canning Town Congestion Relief

Designs associated with new stairs and infill of platform areas for congestion relief purposes during the Olympics

Electrical and Comms design

1171 Tube Lines Green Park Station New Lighting for the escalator machine chambers and incline

Electrical Design

1171 Tube Lines Dollis Hill Station New lighting controls and miscellaneous works to the platform lighting

Electrical Design

1175 TMA Tower Hill Station Step Free Access Scheme for the station Electrical, mechanical, fire and Comms design

1169 DLR Three Gates Project New entrance area arrangements for Custom House, Greenwich and Prince Regent stations

Electrical Design

1145 London Underground Neasden Depot Fire Alarm Fire Alarm design for three buildings within Neasden Depot Fire Design

1070 Birse Metro Goldhawk Road / Gloucester Road / Royal Oak Platform Extension

Electrical and mechanical designs in relation to platform extensions at a number of stations

Electrical and Mechanical

1009 Tube Lines Highgate SCC Design for UPS and associated distribution system for the SER and main control room at the Northern Line Service Control Centre

Electrical

0956A DLR Bank DLR Station Formation of a new Adit though to the platform along with new staff accommodation

Electrical, Mechanical and Fire Design. Comms performance

Page 29: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 29 of 44

www.beveridge-associates.co.uk

specification.

0917 YJL Notting Hill Gate Station Assurance for fire services and mechanical services in relation to the Station Modernisation scheme at the station.

Assurance

1161 London Underground Harrow-on-the-Hill Station Design works in relation to staff accommodation works Electrical and mechanical works

1151 Network Rail / Emico East Ham and Ilford Depots Heating Replacement

Reviewer and CRE for heating replacement works at these Depots

Mechanical review and approval

1148 DLR Canning Town Congestion Relief

Designs associated with new stairs and infill of platform areas for congestion relief purposes during the Olympics

Electrical and Comms design

1144 London Underground Neasden Depot TMR Control Room refurbishment

Fit out design for refurbished control room Electrical and mechanical design

1133 DLR Stratford Station new DDA Access

Electrical and Comms outline design in relation to DDA access from DRL platforms to the Network Rail part of the station

Electrical and Comms design

1127 London Underground Lillie Bridge Depot – locker rooms

Fire Strategy for new locker rooms Fire Strategy

1120 London Underground Bromley-by-Bow Station New entrance for the station along with a new overbridge and upgrading of the existing overbridge

Electrical and mechanical

1125 London Underground Lillie Bridge Depot – staff accommodation

Fire strategy for new staff accommodation at the Depot Fire Strategy

1067 London Underground West Kensington Station New potable building for S&T Staff Accommodation Fire Strategy

Page 30: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 30 of 44

www.beveridge-associates.co.uk

1053 London Underground Ruislip Cleaning Depot Maintenance access platforms to cleaning shed, new Escape Lighting to Cleaning Shed and staff accommodation

Fire Strategy, outline fire design and escape lighting design

1062 London Underground Barking Station discussed building Wakering Road

Refurbishment of an existing building for use as S&T Staff Accommodation

Electrical, Mechanical and Fire Design. Fire strategy

0983 Track Alliance West Ham Station Enabling works for Cross Rail including new point heaters and external walkways

Electrical

1016 London Underground District Line Signalling Main Design for new Signalling Main serving signalling equipment between Campbell Road (Bow) to Barking Sidings

Electrical

1010 London Underground Ruislip Depot New Portable Building for Signal Engineers accommodation. Fire design and fire strategy.

Fire / Fire Strategy.

0823 London Underground Bank Station New Walbrook Entrance

New entrance to the Waterloo and City Line from Walbrook EC4. Design currently within Stage D.

Electrical, Mechanical and Fire Design. Comms also within remit but sub-contracted to Atkins

1042 London Underground Car Park Charges for electric Chargers

Feasibility report in relation to available power supplies for the installation at charger points within 60no stations

Electrical

1040 YJLi Lillie Bridge Depot New portacabins for staff accommodation Fire Strategy

1011 London Underground Neasden Depot – Hovis Building

Fire Strategy for change of use of building Fire Strategy

1001 London Underground Stepney Green Station Fire Strategy for new signalling equipment Fire Strategy

1030 London Underground St Mary's Station Fire Strategy for new signalling equipment Fire Strategy

1023 KN Networks Edgware Road Feasibility Study in relation to new SER building Electrical report

1020 Birse Metro Southfields Station Assurance of electrical design Assurance

Page 31: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 31 of 44

www.beveridge-associates.co.uk

0976 Thales Neasden Depot Design of secure power supplies for SER and associated equipment

Electrical

0972 London Underground Notting Hill Gate and Marble Arch Station – Cooling the Tube

Fire Strategies in relation to the ventilation works proposed at those stations

Fire Strategy

0970A London Underground Bank Station Smoke Fan Replacement

Fire Strategy in relation to the replacement smoke extract fans serving the DLR station at Bank

Fire Strategy

0970B DLR Bank Station Blockade Multi-project fire strategy to pick up 6no projects being undertaken at Bank DLR station during the 2009/10 Christmas / Jan blockade

Fire Strategy

0962 Iceberg Air Cond Barbican Station Design of cooling for IMR Mechanical

0958 London Underground Aldgate Station Fire Strategy for civils works at end of platform to enable longer trains into the station

Fire Strategy

0956 DLR Bank DLR Station Masterplan for an upgrade to the station including new lighting and finishes

Electrical, Mechanical and Fire Design. Comms performance specification

0804 Metronet Rail LVAC Works in relation to the Signalling Immunisation Works

Electrical design and design integration in relation to 13no Metropolitan Line sites and 10no District Line sites required for the Signal Immunisation Works for these two lines.

Electrical

0839 Metronet Rail Piccadilly Circus – new HVAC system

Detailed feasibility study into various options for a complete new station HVAC system for the station.

Mechanical

0947 Simmons Earls Court Station Replacement Stairs

Replacement Stairs between District Line and Piccadilly Line platforms

Fire Strategy

0941 Metronet Rail Baker Street Platform Extension

Extension of Platforms at Baker Street to cater for the new S8 rolling stock

Fire Strategy

0934 Metronet Rail New SSL SERs New Signal Equipment Rooms at 59no sites including Section12 stations, surface stations, Depots and track side locations

Fire Strategy

0933 Metronet Rail Bank Station – Relocation of platform hydrant

Relocation of fire hydrant on platform to assist in congestion relief

Mechanical and Fire

Page 32: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 32 of 44

www.beveridge-associates.co.uk

0930 Metronet Rail Neasden Depot Train Simulator Building

Provision of a new building at the Depot to house Train Driver Simulation equipment for training purposes.

Fire Strategy

0842 Morgan Est Cooling the Tube – Ventilation Shaft works

Preparation of fire strategies to suit the increased ventilation requirements of ventilation shafts at Drayton Park, Coburg Street and Tynmouth Road

Fire Strategy

0821 Metronet Rail Northumberland Park Depot Escape Lighting

New escape lighting system for the main sheds within the Depot, including new UPS system.

Electrical

0838 TfL Paddington Station New Switchroom for CBS supplies

Provision of a new switchroom to allow for an increased service head for new CBS advertising panel supplies

Fire Strategy

0835 Metronet Rail Bond Street entrance canopy New canopy at the Oxford Street entrance to the station Fire Strategy

0830 Metronet Rail Victoria Line Upgrade – Single point of failure

Electrical design to overcome single point of failure identified on the new SER supplies

Electrical

0906 Metronet Rail Acton Training Centre – Building AC20 Fire Strategy

Re-fit of an existing building to provide a Signalling training facility

Fire Strategy

0843 Metronet Rail Ruislip Depot Train Simulator Building

Provision of a new building at the Depot to house Train Driver Simulation equipment for training purposes.

Fire Strategy

0907 Metronet Rail Kings Cross, Brixton and Tottenham Hale – Victoria Line Platform Humps

Installation of platform humps on the Victoria Line Platforms for step free access to the trains

Fire Strategy

0816 Tube Lines Secondment of a Mechanical Engineer to Tube Lines office

Various projects by our Engineer working in Tube Lines Westferry office including station mods at Oval, Clapham Common, Stanmore and Edgware Road

Mechanical

0814 Metronet Rail Victoria Line Back Up Control Facility

Mechanical and Fire designs in relation to back up Facility areas at Northumberland Park Depot and Blackhorse Road station for the Victoria Line

Mechanical and Fire

0750 Metronet Rail Victoria Line – New OPO System

Electrical design in relation to the new OPO system at all of the Victoria Line stations (16no)

Electrical

0749 Network Rail Waterloo Station Design of new platform 20 (change of use from Waterloo International Platform to domestic platform) plus refurbishment of Platform 19

Electrical and Mechanical

Page 33: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 33 of 44

www.beveridge-associates.co.uk

0746/0417 TMA / Metronet Rail Shepherd's Bush Station Design of the AGW and PPP projects that were implemented and the BGW scheme that was not. Fully integrated design between the three projects, undertaken in a way that allowed the station to remain open (it closed following this due to time constraints)

Mechanical, Electrical and Fire

0745 Metronet Rail Earls Court Control Room – environmental conditions

Renewal of Ventilation and Air Conditioning within the Control Room

Mechanical

0738 AMEC Silver Link Stations (London Overground)

Site survey and outline fire strategy information in relation to work at 14no Silverlink (London Overground) stations

Fire

0723 Metronet Rail Parsons Green Train Crew Accommodation

New staff accommodation for train crew within the staff building on the platform

Electrical and Mechanical

0719 Metronet Rail Victoria Line Upgrade – UPS Hydrogen Testing

Investigative report into the possibility of hydrogen discharge from UPS batteries installed within the Victoria Line Upgrade, and recommendations to overcome any issue found

Electrical

0715 Metronet Rail Warwick Avenue Station Supervisors office

Electrical, Mechanical and Fire works in relation to the relocation of the supervisor’s office

Electrical, Mechanical and Fire

0707 Metronet Rail Victoria Station Phased works to remove asbestos from the station Fire Strategy

0650 Metronet Rail Hainault Depot Train Simulator Building

Provision of a new building at the Depot to house Train Driver Simulation equipment for training purposes

Fire Strategy

0649 Metronet Rail Victoria Line Upgrade MDA Installation at 4no stations Fire Strategy

0646 Network Rail Willesden Depot Provision of a new 'Fuel Farm' within the Depot to improve existing unsatisfactory environmental conditions

Electrical and Mechanical

0645 Network Rail Wembley Depot Provision of a new 'Fuel Farm' within the Depot to improve existing unsatisfactory environmental conditions

Electrical and Mechanical

0644 Metronet Rail White City Station Document Review of handover documentation Electrical and Mechanical

0642 Morgan Est Notting Hill Gate Station Station Modernisation Fire Strategy

0641 Morgan Est Buckhurst Hill Station Station Modernisation Fire Strategy

0639 Morgan Est Marble Arch Station Station Modernisation Fire Strategy

Page 34: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 34 of 44

www.beveridge-associates.co.uk

0637 Morgan Est Marble Arch Station Station Modernisation and congestion relief - Design of all services in relation to the modernisation and for the relocation of the staff accommodation at Ticket Hall level for congestion relief purposes

Electrical, Mechanical and Fire

0633 Iceberg Air Cond High Street Kensington New air conditioning scheme for station supervisor’s office Mechanical

0632 Metronet Northumberland Park Depot Feasibility Report into options for a complete Point Heater replacement and design of preferred option

Electrical

0627 Metronet Rail Victoria Line Upgrade HVAC design work in relation to power supplies to SERs for three stations

Electrical

0623 Metronet Rail Waterloo & City Line Installation of platform humps on the Victoria Line Platforms for step free access to the trains

Fire Strategy

0614 Metronet Rail Bank Station – DLR Smoke Ventilation

Design for replacement of Smoke Ventilation fans to allow for the DLR Tunnel Ventilation Improvements

Electrical and Mechanical

0613 Iceberg Air Cond Chancery Lane Station Toilet Ventilation Scheme Mechanical

0611 Metronet Rail Ruislip Depot – Escape Lighting

Design of new escape lighting system for the main sheds within the Depot, including new UPS system

Electrical

0609 Iceberg Air Cond Paddington Station Ticket office

New Air Conditioning for ticket office Mechanical

0608 Balfour Beatty / Metronet Rail Waterloo & City Line (Closure) Input into fire engineering issues associated with the W&C Kline closure, as well as a non-compliance report for Waterloo Depot

Fire

0605 Metronet Rail Earls Court Station – Roof replacement works

Temporary Crash Deck and roof replacement works Fire Strategy

Fire Strategy

0602 Tube Lines Fire Alarm Design of cable arrangement to conceal fire alarm cabling at Caledonian Road and Turnpike Lane stations

Electrical

0531 Tube Lines CMS Preparation of a Designers Guide to Cable Management for use by Tube Line designers on Station modernisation works

Electrical

0529 Tube Lines South Kentish Town (Disused) Station

Electrical design in relation to temporary lighting and electrical supplies at a Dis-used station for major P-Way works

Electrical

0519 Metronet Rail Stonebridge Park Depot Lighting Survey / Report for the replacement of all the work at the Depot and outline design works to enable budget costs and programmes to be ascertained

Electrical

Page 35: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 35 of 44

www.beveridge-associates.co.uk

0514 Amey Rail Acton Training Centre Incoming services connections associated with new modular accommodation for training purposes

Electrical and Mechanical

0513 Metronet Rail Euston Station Design of electrical supplies to 2Nr. Compressor Sets Electrical

0503 TMA Bank Station Services input in relation to optioneering assessment for Bank Masterplan project

Electrical and Mechanical

0458 Amey Rail Hainault Depot Air conditioning for the security hut Mechanical

0449 Amey Rail Newbury Park Station Toilets refurbishment Mechanical

0446 Metronet Rail Rickmansworth Depot Walkway Lighting for pathway between station and Depot Electrical

0433 Tube Lines Jubilee, Northern and Piccadilly Lines

Emergency and escape route lighting surveys at 44no Section 12 stations

Electrical

309 Metronet Rail Templar House Condition Survey and report of building servers within the building. Watching brief over Design and Build Contractor in relation to the fit out for Metronet Rail

Electrical, Mechanical and Fire

0413 Metronet Rail Victoria Line Upgrade Design of fire services and preparation of Fire Strategies for 16no Signal Equipment Rooms and UPS rooms related to the Victoria Line Upgrade project

Fire

0357 Metronet Rail Ashfield House Electrical Services design in relation to the fitting out of the 3rd and 4th floor for office use

Electrical

0226 Infraco JNP Holloway Road Station Electrical design to stage C/D for Station Modernisation Electrical

0212 Infraco JNP Asset Condition Report Electrical and mechanical asset condition update in relation to the annual asset condition report across the Tube Lines network

Electrical and Mechanical

0205 Infraco BCV Lancaster Gate Station Electrical design to stage C/D for Station Modernisation Electrical

0204 Infraco BCV Elephant & Castle Station Electrical design to stage C/D for Station Modernisation Electrical

0148 Infraco BCV Wanstead Station Temporary & Permanent Lighting Electrical

0146 Infraco SSL Train Crew Accommodation Works

Upgrading of staff facilities at Rickmansworth/Baker Street/Parsons Green/Edgware Road/Neasden/Barking & Upminster

M & E & B

0113 Infraco BCV Bakerloo and Victoria Line Water Surveys and preparation of as existing drawings for 8no stations

Mechanical

Page 36: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 36 of 44

www.beveridge-associates.co.uk

0104 Infraco BCV Marble Arch/Roding Valley/Chigwell Stations

Electrical design to stage E for Station Modernisation Electrical and Mechanical

0050 YJL / Infraco JNP Wembley Park New air conditioning system for the Train Crew Accommodation building

Mechanical

0041 Railtrack Southern Zone Clapham Junction Depot – new lighting installation for external walkways and miscellaneous works to the electrical installation within the Depot

Electrical and Mechanical

0038 London Underground/Pascel/Watson

Knightsbridge Station & Sloane Street Ticket Hall

Congestion Relief Project – electrical design work in relation to the lighting and CMS installations

Electrical

0029 Railtrack/Watts Southern Zone Strawberry Hill Depot – renewal of electrical and mechanical systems

Electrical and Mechanical

9601 Bovis / London Underground Works to Listed Stations Electrical and mechanical design works, in particular relating to cable management and lighting works at 21no listed stations

Electrical and Mechanical

9504 (A) London Underground Hangar Lane & Perivale Stations

Lighting scheme site survey and detailed design Electrical

9956 Railtrack Hastings/Ramsgate/Selhurst Depots

Technical Audit/Advice Electrical and Mechanical

9955 Railtrack Southern Zone Depots Electrical Testing Works Electrical

9954 Railtrack/Watts Hornsey Depot Miscellaneous works in relation to electrical and mechanical systems

Electrical

9953 Railtrack/Watts Woodham Ferrers Station Lighting design to existing station Electrical and Mechanical

9952 Railtrack Ramsgate Depot Water services renewal Mechanical

9931 Railtrack Paddington Station Station Regeneration Project Electrical and Mechanical

9915 London Underground / Lovell District Line Depots Cable Calculations Electrical

9904 Railtrack Bletchley Depot Rewire of main staff accommodation and office building. Renewal of water services

Electrical and Mechanical

9902 London Underground Knightsbridge Ventilation design for escalator machine chamber Mechanical

9866 London Underground 366 Grays Inn Road Office refurbishment Electrical and Mechanical

Page 37: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 37 of 44

www.beveridge-associates.co.uk

9829 Virgin Rail Willesden Depot Electrical and ventilation works in relation to new Depot equipment

Electrical and Mechanical

9819 Railtrack Various stations Station Regeneration Project – electrical and mechanical upgrade works to 68no stations – London North and East Anglia.

Electrical

9814 London Underground Ashfield House and Morden Station

Kitchen Refurbishments Electrical and Mechanical

9748 Railtrack London South Region Selhurst Depot Electrical and Mechanical Upgrade works Electrical and Mechanical

9746 Railtrack London North Region Depots electrical and mechanical upgrade works at 5no Depots

Electrical and Mechanical

9739 Railtrack Norwich Relocation of GTRM Facilities Electrical

9714 Railtrack London North Region – Station Regeneration

Station Regeneration Project – electrical and mechanical upgrade works to 27no stations – London East and Essex

Electrical

9621 Railtrack London North Region – Station Regeneration

Station Regeneration Project - electrical and mechanical upgrade works to 7no stations and 3no Depots - London East, Essex and East Anglia

Electrical

9603 London Underground Review standards Review/Revise Mechanical Standards Mechanical

9601 London Underground 21 Listed Stations (Bovis) Survey, Design and Implementation of M&E&F Services Electrical, Mechanical and Fire

9518 London Underground Gt Portland Street Station Survey and Design of new Mechanical Services Mechanical

9506 London Underground Several Stations Escalator Machine Rooms Survey and Reports Electrical

9504 London Underground Several Surface Stations Fire Safety Project Site Survey and Design Fire

9421 London Underground Various Depots Site Supervision of upgrade works to Close-Outs Electrical

9420 London Underground Turnpike Lane Station Station Modernisation and Upgrade - Design and Site Supervision

Electrical

9416 London Underground Several Stations Emergency Exit Signs-Site Supervision and Design and Implementation

Electrical

9408 London Underground Notting Hill Gate Station Switchroom Modernisation-Site Supervision and Project Management

Electrical

9306 London Underground Several Stations Exit/Emergency Signs - Site Supervision Electrical

9304 London Underground Several Stations Phase 2 Escalator Machine Chamber Surveys/Repairs Electrical

9303 London Underground Several Stations Site Survey, Design and Implementation of new Exit and Electrical

Page 38: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 38 of 44

www.beveridge-associates.co.uk

emergency signs

9302 London Underground Various Depots Site Survey, Design and implementation of new security systems

Electrical

9301 London Underground Harrow-on-the-Hill Station Site Survey and Design-Upgrade of Electrical Services Electrical

9233 London Underground 73No. Stations Exit and General Signage - Site Survey & Design Electrical Supplies

Electrical

9232 London Underground Several Stations Contract Implementation Electrical

9231 London Underground Rickmansworth Station Staff Accommodation Upgrade – Site Survey and Design Electrical

9230 London Underground Baker Street Station Signals Block Upgrade-Site Survey and Design Electrical

9229 London Underground Brixton Station Staff Accommodation Upgrade – Site Survey and Design Electrical

9228 London Underground Highbury & Islington Station Staff Accommodation Upgrade – Site Survey and Design Electrical

9227 London Underground Upminster Station Staff Accommodation Upgrade – Site Survey and Design Electrical

9226 London Underground Central Line – All Above Ground Stations

Site Surveys & Design of New Lighting & Power Electrical

9224 London Underground Several Stations Escalator Machine Room Surveys Electrical

9222 London Underground Several Stations – Staff Accommodation Upgrade Project

Surveys and Electrical Design and Site Supervision of Installation

Electrical

9215 London Underground Several Stations – Ticket Collection Boxes

Surveys and Design Power Supplies Electrical

9211 London Underground Several Stations Platform Invert Surveys Electrical

9058 London Underground Several Stations – Section 12 – Compartmentation

Survey and Fire Damper Design Electrical and Fire

9021 London Underground 7No. Stations Replacement of Lighting over Escalators Electrical

9020 London Underground Several Stations-Section 12 Communication Equipment Rooms

Survey and Power Design Electrical

8970 London Underground Marylebone Station Survey and Lighting Improvements Electrical

Page 39: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 39 of 44

www.beveridge-associates.co.uk

APPENDIX C

ISO9001 CERTIFICATE

ACE CERTIFICATE

LINK-UP CERTIFICATE

CONSTRUCTION LINE CERTIFICATE

Page 40: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 40 of 44

www.beveridge-associates.co.uk

Page 41: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 41 of 44

www.beveridge-associates.co.uk

Page 42: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 42 of 44

www.beveridge-associates.co.uk

Page 43: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 43 of 44

www.beveridge-associates.co.uk

Page 44: BEVERIDGE ASSOCIATES PARTNERSHIP LIMITED - RAILbeveridge-associates.co.uk/PDF-statements/Beveridge... · 2019. 1. 2. · 2.0 SCOPE OF SERVICE ... fire engineering designs. Bank Station

Page 44 of 44

www.beveridge-associates.co.uk