19
SESSION I2: RENEWABLE ENERGY & ECONOMIC CHANGE IMPACTS THIRTY FIVE YEARS OF RENEWABLE ENERGY PROJECT EXPERIENCE AT FORT HUACHUCA, ARIZONA 1 OCTOBER 2015 BILL STEIN, CEM, CEP, CSDP, CMVP, CEA, REP, CDSM U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION ENGINEERING RESEARCH LABORATORY

Bill Stein 2015 WEEC presentation 35 Yrs RE proj exp at Fort Huachuca 1 Oct 15

Embed Size (px)

Citation preview

SESSION I2: RENEWABLE ENERGY & ECONOMIC CHANGE IMPACTS

THIRTY FIVE YEARS OF RENEWABLE ENERGY PROJECT EXPERIENCE AT FORT HUACHUCA, ARIZONA

1 OCTOBER 2015 BILL STEIN, CEM, CEP, CSDP, CMVP, CEA, REP, CDSM

U.S. ARMY CORPS OF ENGINEERS CONSTRUCTION ENGINEERING RESEARCH LABORATORY

2000 SF UNGLAZED INDOOR POOL SOLAR SYSTEM - 1980

900 SF SOLAR DOMESTIC HOT WATER - 1981

1000 SF SOLAR ATTIC SYSTEM - 2002

2300 SF TRANSPIRED AIR SOLAR SYSTEMS- 2001

SOLAR AIR PANEL SYSTEM - 2009

DAYLIGHTING – 1998

5 KW GRID CONNECTED PV SYSTEM - 1982

W. FACING GRID CONNECTED PV SYSTEM – 1998 AND 2015

30 KW BUILDING INTEGRATED PHOTOVOLTAIC (BIPV) - 2009

42.8 KW TRUCK SHED MOUNTED PHOTOVOLTAIC - 2009

13.6 MW (A/C) PHOTOVOLTAIC SYSTEM - JAN 2015

10 KW DISH/STIRLING SOLAR THERMAL ELECTRIC GENERATOR - 1996

DISH/STIRLING SOLAR THERMAL ELECTRIC GENERATOR -2010??

10 KW WIND TURBINE - 2002

1 MW WIND TURBINE – SEPT 2011 TO FEB 2013

50 KW ORGANIC RANKIN CYCLE SOLAR THERMAL ELECTRIC GENERATOR AT THE SOUTH CENTRAL PLANT – 2010

1.7 MILLION BTU WOOD CHIP BOILER AT THE WEST CENTRAL HEATING AND COOLING PLANT – 2010

BUILDING STRONG®

Thank You!!

Questions?? My contact information

►Bill Stein ►[email protected] ►217-373-4470 or 520-456-1377