Upload
christopher-preece
View
154
Download
2
Tags:
Embed Size (px)
DESCRIPTION
BIM Awareness and Readiness
Citation preview
1
Royal Institution of Surveyors Malaysia
Building Information Modelling Awareness and Readiness Among Quantity Surveyors and Quantity Surveying Firms
Building Information Modelling Technical Committee Prepared by Dr. Kherun Nita binti Ali Sharifah Noraini Noreen binti Syed Ibrahim Al‐Jamalullail Tan Choon Boon March 2013
2
Building Information Modelling Technical Committee
Sr. Quek Jin Keat, Chair of BIM Technical Committee
Dr. Kherun Nita binti Ali, Universiti Teknologi Malaysia
Sharifah Noraini Noreen binti Syed Ibrahim Al‐Jamalullail, Perunding DMA Sdn. Bhd.
Tan Choon Boon, IJM Corporation Bhd.
Sr. Roznita binti Othman, Jabatan Kerja Raya
Dato’ Sr. Peter Tan Choon Hoo, Perunding Kos T & K Sdn. Bhd.
Sr. Chin Keh Liang, Perunding PCT Sdn. Bhd.
Sr. Mohamad Faiz bin Awang, JUBM Sdn. Bhd.
Sr. Mohd Ridzuan bin Lop Zainal Rashid, Perunding Kos T & K Sdn. Bhd.
Chin Wei Min, Perunding PCT Sdn. Bhd.
Suhaibah binti Mohd Ghazali, AQS Services Sdn. Bhd.
3
Table of Contents Building Information Modelling Technical Committee ................................................................................. 2
List of Figures ................................................................................................................................................ 5
List of Tables ................................................................................................................................................. 7
RESEARCH HIGHLIGHTS ................................................................................................................................. 8
EXECUTIVE SUMMARY .................................................................................................................................. 9
PART A: BUILDING INFORMATION MODELLING AWARENESS AMONG QUANTITY SURVEYORS ............... 14
1.0 Introduction ...................................................................................................................................... 14
2.0 Quantity Surveyors’ Profile ............................................................................................................... 14
3.0 Awareness Profile ............................................................................................................................. 18
3.1 Hardware and software application ........................................................................................ 18
3.2 Preference in types of drawing from architects ...................................................................... 19
3.3 E‐tendering experiences .......................................................................................................... 21
3.4 Knowledge on BIM ................................................................................................................... 22
3.5 Awareness on BIM programmes .............................................................................................. 25
3.6 Involvement in BIM projects .................................................................................................... 28
4.0 Level of awareness of Building Information Modeling (BIM) ........................................................... 30
4.1 Feasibility stage ........................................................................................................................ 30
4.2 Design stage ............................................................................................................................. 32
4.3 Construction stage ................................................................................................................... 34
4.4 In‐use and maintenance stage ................................................................................................. 36
4.5 Quantity surveyors’ task with the incorporation of BIM ......................................................... 37
5.0 Cross Tabulation Analysis .................................................................................................................. 39
5.1 Level of awareness vs gender .................................................................................................. 39
5.2 Level of awareness vs experience ............................................................................................ 43
5.3 Level of awareness vs registration ........................................................................................... 47
PART B: BUILDING INFORMATION MODELLING READINESS AMONG QUANTITY SURVEYING FIRMS ....... 51
6.0 Introduction ...................................................................................................................................... 51
7.0 Organisations’ profile ........................................................................................................................ 51
7.1 Designation .............................................................................................................................. 51
7.2 Years of establishment ............................................................................................................. 52
7.3 Number of employees ............................................................................................................. 53
4
7.4 Company turnover ................................................................................................................... 53
7.5 Management certification ....................................................................................................... 54
7.6 Access to computer and internet connection .......................................................................... 55
8.0 Readiness Profile ............................................................................................................................... 56
8.1 Information technology application in Malaysia ..................................................................... 56
8.2 Knowledge on BIM ................................................................................................................... 57
8.3 Participation in BIM program ................................................................................................... 58
8.4 Participation in BIM software training ..................................................................................... 59
8.5 Involvement in BIM Projects .................................................................................................... 60
9.0 Level of readiness among quantity surveying firms ......................................................................... 62
9.1 Technology aspect ................................................................................................................... 62
9.2 People aspect ........................................................................................................................... 64
9.3 Process aspect .......................................................................................................................... 66
9.4 Management aspect ................................................................................................................ 68
10.0 Cross tabulation analysis ................................................................................................................. 70
10.1 Level of readiness vs no. of staff ............................................................................................ 70
10.2 Level of readiness vs years of establishment ......................................................................... 74
5
List of Figures Figure 1: Respondent’s region of working .................................................................................................. 14
Figure 2: Respondent’s age ......................................................................................................................... 15
Figure 3: Respondent’s gender ................................................................................................................... 15
Figure 4: Respondent’s working experience ............................................................................................... 16
Figure 5: Respondent’s registration ............................................................................................................ 17
Figure 6: Respondent’s designation ............................................................................................................ 17
Figure 7: Software application .................................................................................................................... 18
Figure 8: Hardware application ................................................................................................................... 19
Figure 9: Preferences as to work on hardcopy or softcopy ........................................................................ 20
Figure 10: E‐Tendering experience ............................................................................................................. 21
Figure 11: Respondents’ knowledge on BIM .............................................................................................. 22
Figure 12: QS extinction with BIM existence .............................................................................................. 25
Figure 13: Awareness of BIM programmes ................................................................................................. 25
Figure 14: Participation in BIM programmes .............................................................................................. 26
Figure 15: Respondents’ sponsorship ......................................................................................................... 28
Figure 16: Respondent involvement in BIM projects ................................................................................. 28
Figure 17: BIM awareness at feasibility stage ............................................................................................. 32
Figure 18: BIM awareness at design stage .................................................................................................. 34
Figure 19: BIM awareness at construction stage ........................................................................................ 35
Figure 20: BIM awareness to in‐use and maintenance stage ..................................................................... 37
Figure 21: QS tasks with the incorporation of Building Information Modeling .......................................... 38
Figure 22: BIM awareness at feasibility stage vs gender ............................................................................ 39
Figure 23: BIM awareness at design stage vs gender ................................................................................. 40
Figure 24: BIM Awareness at Construction Stage vs Gender ..................................................................... 41
Figure 25: BIM awareness at in‐use and maintenance stage vs gender ..................................................... 42
Figure 26: BIM awareness at feasibility stage vs experience ...................................................................... 43
Figure 27: BIM awareness at design stage vs experience ........................................................................... 44
Figure 28: BIM awareness at construction stage vs experience ................................................................. 45
Figure 29: BIM awareness at in‐use and maintenance stage vs experience .............................................. 46
Figure 30: BIM awareness at feasibility stage vs QS registration ............................................................... 47
Figure 31: BIM awareness at design stage vs QS registration .................................................................... 48
6
Figure 32: BIM awareness at construction stage vs QS registration .......................................................... 49
Figure 33: BIM awareness at in‐use and maintenance stage vs QS registration ........................................ 50
Figure 34: Respondent’s designation .......................................................................................................... 52
Figure 35: Years of establishment .............................................................................................................. 52
Figure 36: Total number of employees ....................................................................................................... 53
Figure 37: Company turnover ..................................................................................................................... 54
Figure 38: Management certification ......................................................................................................... 54
Figure 39: Own computers and internet access ......................................................................................... 55
Figure 40: Information Technology (IT) application in Malaysia construction ........................................... 56
Figure 41: Information Technology (IT) application by QS in Malaysia ...................................................... 57
Figure 42: Staff participation in BIM programme ....................................................................................... 59
Figure 43: Staff participation in BIM software training .............................................................................. 60
Figure 44: Respondent’s involvement in BIM projects ............................................................................... 61
Figure 45: BIM readiness from the aspect of technology ........................................................................... 64
Figure 46: BIM readiness from the aspect of people .................................................................................. 66
Figure 47: BIM readiness from the aspect of process ................................................................................ 68
Figure 48: BIM readiness from the aspect of management ....................................................................... 70
Figure 49: Level of readiness vs number of staff from the aspect of technology ...................................... 70
Figure 50: Level of readiness vs number of staff from the aspect of people ............................................. 71
Figure 51: Level of readiness vs number of staff from the aspect of process ............................................ 72
Figure 52: Level of readiness vs number of staff from the aspect of management ................................... 73
Figure 53: Level of readiness vs number of years of establishment from the aspect of technology ......... 74
Figure 54: Level of readiness vs number of years of establishment from the aspect of people ................ 75
Figure 55: Level of readiness vs number of years of establishment from the aspect of process ............... 76
Figure 56: Level of readiness vs number of years of establishment from the aspect of management ..... 77
7
List of Tables Table 1: Reasons on type of drawing preferred by the quantity surveyors ............................................... 19
Table 2: Brief explanation about BIM knowledge ....................................................................................... 22
Table 3: BIM programmes title ................................................................................................................... 26
Table 4: BIM programmes title ................................................................................................................... 27
Table 5: BIM application in construction stages ......................................................................................... 29
Table 6: Problems experienced ................................................................................................................... 29
Table 7: Benefits experienced ..................................................................................................................... 30
Table 8: BIM awareness at feasibility stage ................................................................................................ 31
Table 9: BIM awareness at design stage ..................................................................................................... 32
Table 10: BIM awareness at construction stage ......................................................................................... 35
Table 11: BIM awareness at in‐use and maintenance stage ...................................................................... 36
Table 12: QS tasks with the incorporation of Building Information Modeling ........................................... 38
Table 13: Brief explanation about BIM knowledge..................................................................................... 58
Table 14: BIM programmes title ................................................................................................................. 59
Table 15: BIM software training ................................................................................................................. 60
Table 16: BIM application in construction stages ....................................................................................... 61
Table 17: Problems experienced ................................................................................................................. 61
Table 18: Benefits experienced ................................................................................................................... 62
Table 19: BIM readiness from the aspect of technology ............................................................................ 63
Table 20: BIM readiness from the aspect of people ................................................................................... 65
Table 21: BIM readiness from the aspect of process .................................................................................. 67
Table 22: BIM readiness from the aspect of management ........................................................................ 69
8
RESEARCH HIGHLIGHTS
• AIM to determine the level of awareness among
the quantity surveyors and the level of readiness among the quantity surveying firms towards Building Information Modelling (BIM)
• QUESTIONNAIRES were used as method of
data collection and descriptive statistics were adopted to analyse the data
• AWARENESS is exponentially growing though BIM is still at infancy rate
• READINESS level is high though some
concerned were raised in workforce training supports, legal and integration issues
• LIMITATION of the research lies on the
number of respondents which restricts the generalisation of the findings
• FURTHER data collection will be conducted to substantiate the interim findings of the survey
RESEA
RCH HIGHLIGHTS
9
EXECUTIVE SUMMARY
1. This report presents the interim findings of a survey to determine the level of awareness among
quantity surveyors and the level of readiness among quantity surveying firms towards the
Building Information Modeling (BIM). It is divided into two parts where Part A depicts the result
of the BIM awareness while Part B is for the firms’ BIM readiness.
2. The basis of the survey lies on its extensive literature reviews on the subject matter. Data
collection was conducted among quantity surveyors and quantity surveying firms’ owners by
means of questionnaire as the instrument. Data was then analyzed using descriptive statistics
where frequency and percentage were the analysis techniques used to present the findings.
Cross tabulation was used to present, summarize and visualize how the demographic
characteristics of quantity surveyors inter‐relate with measures of BIM awareness as well as
have a grasp of how firms’ size and years of establishment inter‐relate with measures of BIM
readiness.
3. Questionnaires were distributed to the target respondents during seminars and conferences
held between November 2012 and January 2013. Out of the total of 250 questionnaires
distributed to quantity surveyors during the seminars and conferences, 21.2% were useable for
the analysis. On the other hand, a total of 80 questionnaires were distributed to quantity
surveying firms’ owners but 22.5% were useable for analysis. The low number of participants
may not possibly represent the whole population of the profession, but it is an early indicator of
the awareness and readiness of the wider population.
4. The demographic analysis on the respondents for awareness survey shows that majority of
them has more than ten years of experiences in the industry (60%) with almost equal proportion
of female and male (53%:47%). The same proportion also revealed in age with 53% within the
age group of above 40 years old. In term of registration with the Board of Quantity Surveyors
Malaysia (BQSM), 49% of them are Registered QS as compared to Registered Graduate QS and
Non‐registered QS with the percentage of 38% and 13% respectively. The background of the
respondents shows that they have reasonable experiences in the industry and makes their
responses believable.
10
5. Looking at the awareness profiles of the survey, generally a fairly good level of skills and
knowledge in the information and technology (IT) hardware and software was clearly shown by
the respondents. However, majority of them prefer hardcopy drawings to softcopy due to
easiness in checking, visualizing and documentation purposes. Respondents who request for
softcopy praise how taking off could be done easily and in short period of time.
6. The respondents were asked a direct question of definition of BIM to which majority of them
correctly describe the fundamentals of BIM utility, i.e. integration, 3D models and collaboration.
This demonstrates the growing level of knowledge among them despite the fact that BIM is still
at infancy rate in Malaysia. Although one of them stated that BIM may replace QS’s
fundamental role which is the taking off, majority of them optimistically believe that BIM will
not bring QS profession to extinction.
7. At least for the past one year, BIM is being promoted through seminars or conference such as
QS International Convention, QS Principals Dialogue, BIM Conference and Exhibition and BIM
workshops which were organized by various organizations such as by CIDB, BQSM, RISM and
software vendors. However, many are still not aware of such programmes (50%:50%). And
among the aware group of respondents, only 29% participated in the programmes. The study
also shows that that the majority (63%) out of the percentage who attended the programme
were sponsored by their firms.
8. Only two respondents or 10% have involved in construction project that applied BIM. Although
the number is too low, it is inspiring to realize that QS has started getting involved in such kind
of projects. The QS were engaged at feasibility, design and construction stage. Despite the
benefits they experienced from the projects such as better visualization, faster taking off and
efficient coordination, problems in the implementation were also observed for example lack of
understanding and expertise in BIM, technical difficulties, non‐existence of standard BIM models
and resistance from various parties in the projects.
9. The study then delved into the level of awareness of BIM at different stages of a construction
lifecycle i.e. feasibility stage, design stage, construction stage and in‐use and maintenance stage.
Overall, the results show a considerably high level of awareness at all stages. In general, the
Aware status constitutes above 50% of the respondents in most of the items; while Somewhat
Aware comprises between 29%‐50% and the Not At All Aware is not more than 9%.
11
10. Three variables in the quantity surveyors’ profile were then selected for cross tabulation analysis
against all stages in the construction lifecycle. There are gender, years of experience and
registration with the BQSM. Females dominate the awareness level at Somewhat Aware and
Aware in all stages whereas the males form the majority of the Not At All Aware notion in the
study. As for years of experience versus construction stages, QSs with experience less than 10
years forms the majority in the Aware and Somewhat Aware level of awareness cross all stages.
The findings reveal a similar pattern in the cross tabulation for registration against construction
lifecycle which again the Aware and Somewhat Aware notion for Registered QS is taken over by
the Registered Graduate QS and Non Registered QS. Given the impression that Registered
Graduate and Non Registered QS are the same group of QS with less experience, this pattern is
not greatly astounding.
11. The questionnaires for BIM readiness among quantity surveying firms were responded by the
top management of the organizations either the principals, partners or directors. Majority of
the firms have long years in the industry having been established more than 11 years ago. In
term of size of the firms, it is categorized as small, medium and large depending on the number
of employees where small firms has less than 10 staff, medium is between 11 to 20 staff and
large means more than 20 staff. Small firms form 22% of the total respondents whereas
medium and large share an equal proportion of percentage which is 39% respectively. Most
firms reveal the company’s turnover of over RM 1 million for the year 2010 and 2011 with 67%
of the total respondents having obtained ISO quality certification. All firms stated that 100% of
their staff has access to their own computers and majority of them have 75% of their computers
connected to the internet.
12. In the readiness profiles of the firm, the respondents were asked of their perception of the level
of IT application the construction industry. More than half of the respondents rated the
industry as good or very good level in IT application. They also rated the same for QS level of IT
application. Just as the respondents for BIM awareness, the firms’ owners were asked of their
knowledge in BIM and similarly, most of them described quite correctly the fundamental of BIM.
13. The number of firms’ owners who had sponsored their staff to attend BIM related programmes
is a bit low (47%) though almost the number for those who have not sent any staff to any
programmes. This low number of participation is also reflected in the firms sponsoring staff to
attend BIM related software training which only 29% of them started exposing their staff to such
12
trainings. In addition, only 12% of the respondents have involved in constructions project that
involved BIM. Their involvement was particularly at the design and construction stage. Though
they appreciate the benefits that BIM brings into the construction process such as clear design
analysis at early stage that could prevent variation order during construction, at the same time
they recognize some issues surrounding the BIM implementation. For instance, the cost of the
software and training personnel for skills in BIM.
14. The respondents were then probed on their firms’ readiness from the aspects of technology,
people, process and management. The general findings for the first aspect reveal that the firms
are technologically ready to accept BIM in the construction industry where majority of the
respondents Moderately Agree or Agree to the notions. Most of them do realize that
integration is required for data and information sharing and thus, BIM could provide this feature
to enhance communication among parties. From the aspect of people, Quantity Surveying firms
are ready to accept BIM as long as there is sufficient training to guide them to the optimum
level. All of them agree to assist their workforce in re‐skilling and to capitalize on the rapidly
emerging technologies as it will help to improve and enhance the quality of works or end
product. The optimism among respondents continues at the aspect of process to which the
respondents are ready to accept the emerging new technology to improve and enhance their
quality of works provided that there are proper legal to overcome unwanted legal issues. Last
but not the least, from the management aspect, more than 80% or 13 respondents agree that
they have sufficient resources for research, development and training relating to BIM
implementation because they do have staff that are experienced in ICT adoption. Besides, they
are willing to support the necessary maintenance cost during BIM implementation and spend
additional time to familiarize with the software and enhance knowledge and experience about
BIM. Thus, the respondents are ready to adopt BIM in their firms to enhance the quality of
works.
15. In the cross tabulation analysis, two variables were selected against all aspects of readiness.
There are number of staff (firm size) and years of establishment. In term of size, large‐,
medium‐ and small‐sized firms have a balanced distribution of Moderately Agree and Agree
towards BIM across all aspects of readiness. As for years of establishment, it is clearly seen that
the older firms have more confidence in agreeing to the notions in all aspects of BIM readiness.
13
This depicts that they are more ready for the implementation of BIM in comparison to younger
firms.
16. The limitation of the survey lies on the number of respondents and the short period of time
used in gathering the data. Though the findings look positive, the result is not sufficed to
generalize the BIM awareness and readiness of QS profession as a whole. Further data
collection will be conducted and as to substantiate the interim findings of the survey.
14
PART A: BUILDING INFORMATION MODELLING AWARENESS AMONG QUANTITY SURVEYORS
1.0 Introduction
This chapter presents the findings and discussions of the survey. The chapter is divided into a
few sections i.e. the respondents profile; the respondents’ awareness profile; the respondents’ level of
awareness in feasibility stage, design stage, construction stage and in‐use and maintenance stage; and
finally the cross tabulation analysis.
A total of 250 questionnaires were distributed to the Quantity Surveyors during conferences and
seminars held between November 2012 and January 2013. The return rate is about 21.2% percent
which is 53 responded questionnaires with about 90%‐95% of validity. Bar charts, pie chart and tables
were used to present and summarise the findings.
2.0 Quantity Surveyors’ Profile
Figure 1 shows the state were respondents work within the construction industry. Fifty three
percent of the respondents are from Selangor, followed by thirty eight percent in Kuala Lumpur. Penang
and Johor recorded equal and least number of respondents (four percent). As this preliminary survey is
undertaken and distributed amongst seminar participants in Kuala Lumpur, it is expected that the
majority participants would be operating in Kuala Lumpur and Selangor Darul Ehsan.
Figure 1: Respondent’s region of working
4
38
4
53
0
10
20
30
40
50
Johor Kuala Lumpur Penang Selangor
Percen
tage
%
Fi
are from t
years old
percent re
responde
Fi
three pe
responde
gender. I
group of r
igure 2 shows
the category
and less than
espectively, w
nts are categ
igure 3 revea
rcent) and t
nts. This pr
n this survey
respondents
s the respond
41 years old
n 30 years old
with only one
orised as mat
ls the respon
the remainin
reliminary su
y, the differen
in term of ge
Less than
dents’ age. Fr
and above. T
d are almost
e percent diff
tured respon
Figure 2
ndents’ gende
ng percentag
rvey shows t
nce between
nder.
Figure 3: R
47%
30 years old 31
Male47%
om the pie ch
The percenta
the same, wh
erence. This
dents.
: Respondent’s
er, where alm
ge of forty
that QS prof
both genders
Respondent’s ge
27
26%
%
1 to 40 years old
Female53%
e%
hart, forty sev
ge of respond
hich is twenty
percentage i
age
most half of th
seven perce
fessions are
s is only six p
ender
7%
41 years old and
e
ven percent o
dent within t
y six percent
indicates that
he responden
ent are repr
not monopo
percent and it
d above
of the respon
he age of 31
and twenty s
t nearly half o
ts are female
resented by
olised by only
t is quite a ba
15
dents
to 40
seven
of the
e (fifty
male
y one
alance
16
Figure 4 reveals the respondents’ working experience in construction industry. Twenty one
percent of the respondents have less than 5 years of experience in construction industry, while nineteen
percent are in the category of 6 to 10 years and eleven percent of respondents have 11 to 15 years
experience. The remaining forty nine percent of the respondents are in the category of 16 years and
above working experience. This result is expected as most of the respondents are in the age of 41 years
old and above. This also illustrates that the respondents are well experienced respondents.
Figure 4: Respondent’s working experience
Figure 5 illustrates the respondents’ registration with the Board Of Quantity Surveying Malaysia
(BQSM) being the accredited professional body for quantity surveying profession in the Malaysia
construction industry. A total of forty nine percent are registered QS, followed by thirty eight percent of
registered graduate QS and a remaining of thirteen percent are non ‐ registered QS. This illustrates that
the QS respondents in this preliminary survey should be reliable and represents a good source of
Quantity Surveying professionals. The sample is able to show, preliminarily, what the current levels of
awareness of Building Information Modelling (BIM) are amongst registered QS and registered graduated
QS.
21 1911
49
0
10
20
30
40
50
Less than 5 years
6 to 10 years 11 to 15 years 16 years and above
Percen
tage
%
Fi
responde
followed w
A
Managing
percent re
This resul
QS (Senio
aware of t
igure 6 show
nts are Seni
with assistan
percentage
g Directors. S
epresents the
lt shows that
or QS, QS an
the existence
Percen
tage
%
ws the respon
ior Quantity
t Quantity Su
of seventeen
Six percent o
e Proprietor,
t, a total of fi
d assistant Q
e of Building I
Regi
2051015202530
Figure 5: Res
ndents’ desig
Surveyors,
urveyors repre
n percent are
of the respo
while the re
fty four perc
QS). Therefor
nformation M
Figure 6: Res
istered QS Re
6 9
spondent’s regis
nation in the
whilst twent
esenting six p
e Directors, f
ndents are t
maining thirt
ent from the
re, we could
Modelling (BIM
spondent’s desig
49%
38%
13%
egistered Gradua
1725
stration
e organisatio
ty three per
percent from
followed by
the Principal;
teen percent
e respondents
expect that
M) and its ap
gnation
%
ate QS Non‐re
5 23
n. Twenty fi
rcent are Qu
the responde
nine percent
; the least p
represents o
s are represe
most of the
plication in th
egistered QS
613
ive percent o
uantity Surve
ents.
t representin
percentage of
other designa
enting Profess
m would kno
he QS profess
17
of the
eyors,
ng the
f two
tions.
sional
ow or
sion.
18
3.0 Awareness Profile
3.1 Hardware and software application
Figure 7 shows how much the respondents rate their knowledge and application of desktop
software e.g. Microsoft Office Suite (Word, Excel, Power Point, Microsoft Outlook etc.) in quantity
surveying working environment. The result shows that forty three percent and thirty four percent of the
respondents rated good and very good respectively. Out of that, both percentages of eleven percent of
the respondents rated fair and excellent. With this result, it shows that the software application in
Malaysia’s construction industry is common and they apply it well in their works.
Figure 7: Software application
Figure 8 shows how the respondents rate the application of Information Technology (IT)
hardware (e.g. PC, laptop, tablet, smart phone etc.) in working in the industry. The result shows that
eighty one percent of the respondents rated good, very good and excellent. Out of that, forty five
percent are good, twenty six percent are very good; only a total of nine percent of respondents rated
excellent. A remaining nineteen percent rated fair and poor, with seventeen of the respondent rated
fair and only two percent rated poor. With this result, it shows that the application of IT hardware in
Malaysia’s construction industry is very well applied. By having this knowledge and applying it in
working may enable them to connect with the latest information in faster way, thus enhancing their
quality of works.
11
43
34
11
0
10
20
30
40
50
Fair Good Very Good Excellent
Percen
tage
%
19
Figure 8: Hardware application
3.2 Preference in types of drawing from architects
In this study, a question “When the architect give you drawings which are AutoCAD, are you
able to work on the softcopy or do you still request hardcopy from the architect for taking off
purposes?” was asked. The purpose is to know whether the respondents prefer to work with the
softcopy or still be using the hardcopy drawing for taking off purposes. 56% of them will request for
hardcopy form of drawings for taking off purposes (Figure 9). The reasons gathered are as follow:
Table 1: Reasons on type of drawing preferred by the quantity surveyors
Type of Drawing Answers
Work on the softcopy for taking
off purposes
Cad measure to take off quantities
Can work in the softcopy drawing but the hardcopy might used as checking and easy reference as the softcopy is limited on the full view
Estimate stage used softcopy, for BQ production used hardcopy
Hardcopy is still read although taking off is done from softcopy
It easier, more accurate and fast
More accurate and more easy to the quantity in short time
Easier & the quantity is more accurate, saving more time and reduce waste paper
Taking off using digitizer
Using softcopy is accurate given the scale set by the designer is correct
Will request hardcopy for checking and record purposes
Will still request hardcopy for checking / validate the softcopy
Because all drawings in AutoCAD format is same with hardcopy. It is easier
2
17
45
26
9
0
10
20
30
40
50
Poor Fair Good Very Good Excellent
Percen
tage
%
Wihartap
ll request rdcopy for aking off urposes
to measrule, calhard to
Easy refecompute
As need
At timesbe studi
Because
Companmanuall
Differen
Easy to ctake‐off
For docu
It is easy
Office PC
Softcopyamendmconfuse
Spread d
We have
We prinemploy rapid chdocume
Figure 9
H
ure using Autculator etc. Sunderstand d
erence, able ter screen is li
the hardcopy
s dimension ced
e don’t know A
ny does not usy
nt when done
check discrepelement whi
umentation p
y to refer hard
C technical is
y may be chament. At suchus
drawings bett
e no proper s
t using indepAutoCAD opeanges by Arcents
9: Preferences as
Hardcopy 56%
toCAD formatSave time in ddrawing in Au
to deduct errmited (14'' or
y for manual
could not be s
AutoCAD and
sing any takin
on softcopy,
pancy of the dich might not
purposes
dcopy and ta
sue
nged easily a there will be
ter than on sc
ystem to taki
endent printeerators. Hardh/Eng. has im
s to work on har
Softcopy 44%
t because dodoing measuretoCAD forma
ror/discrepanr 16'' only)
checking pro
seen when an
d do not insta
ng off softwar
difficult to p
drawings (bet drawn in the
king off will b
nd we are noe many versio
creen
ing off directl
er. We don’tcopy needed mplications to
rdcopy or softco
Work osoftcopoff pur
Will rehardcooff pur
n’t have/less ement/takingat rather than
ncy faster, the
ocess
n overall layou
all in QS deskt
re. Taking off
rint, better u
tween Archt. e drawing
be on softcop
ot informed oon of drawing
ly from softco
neither buy Afor evidentia
o QS when do
opy
on the py for taking rposes
quest opy for taking rposes
use of scale g off. But, quin hardcopy
e size of
ut plan needs
top
f is done
se hardcopy
and Eng) and
py
f the which may
opy
AutoCAD nor al purpose as ing contract
20
te
s to
d
Ta
hardcopy
softcopy
timely ma
AutoCAD/
can be do
yet, hardc
evidence.
hardcopy
3.3 Eten
A
whether t
tendering
F
experienc
experienc
QS in Mal
able 1 show
for AutoCAD
brings much
anner. But,
/ Revit progr
one. Neverth
copy drawing
There are
because of li
ndering expe
question “D
the responde
g facility desig
Figure 10 sh
ce or not. Fr
ced E‐Tenderi
aysia do not
ws the brief
D work takin
more benefi
doing taking
amme, thus
heless, from t
g is still in de
also respon
mited knowle
eriences
o you have a
ents are awa
gned for use b
hows the di
rom this pie
ing and only t
get good exp
explanation
ng off purpo
ts in doing ta
off by softc
it may take t
the response
mand by the
nses that sug
edge in AutoC
any E‐Tender
re about BIM
by Quantity S
istribution o
chart, a maj
thirty eight p
posure to e‐te
Figure 10: E
No62%
about the
ses. From t
aking off, as
opy might be
time in unde
e also it can b
e respondents
ggest that so
CAD.
ring experienc
M or not, as
urveyor and
of percentage
ority of sixty
percent had e
endering exer
‐Tendering expe
Y3
respondents’
these respon
it is easier, m
e difficult to
rstanding the
be said that e
s due to easy
ome taking o
ce” was aske
E‐Tendering
relates to BIM
e whether r
y two percent
xperienced E
rcises.
erience
Yes 8%
’ preference
ses, it is no
more accurat
QS who are
e format first
even though
y reference a
off are still d
ed in other to
is an efficien
M.
respondent
t of the resp
E‐Tendering.
of softcopy
doubt that
te and excelle
e not familiar
t before takin
softcopy is e
and can be ke
done manua
o get a rough
nt and transp
have E‐Tend
pondents hav
This indicate
21
y and
using
ent in
r with
ng off
easier,
ept as
lly by
h idea
parent
dering
ve not
s that
22
3.4 Knowledge on BIM
Figure 11 shows the distribution of percentage whether respondents know about BIM or do not
know about BIM. From this chart, more than half or sixty one percent of respondents have poor
knowledge of BIM; with forty two percent stating they don’t have much knowledge of BIM and nineteen
percent saying they do not know at all about BIM. Out of the total respondents, thirty four percent of
them have a fair knowledge about BIM, while four percent knows quite a lot about BIM and only two
percent stated they know a lot about BIM.
Figure 11: Respondents’ knowledge on BIM
In the questionnaire, respondents were asked to give a brief explanation about BIM based on
their knowledge or opinion. The responses was categorised into five categories, namely “cost”, “3D
modelling”, “managing construction information, integrate information, handling QS works and
managing building data”, “measurement tool” and “others”. The responses are as follow:
Table 2: Brief explanation about BIM knowledge
Categories of Answers Answers
Cost Costing and development of drawings combined to achieve desired result.
Facilitating communications, increasing productivity, reducing cost.
3D Modeling 3D taking off
BIM are model visualization, object with parameter which can use for
19
4234
4 20
10
20
30
40
Do not know at all
Not Much Fair Quite a lot A lot
Percen
tage
%
23
4D & 5D etc, collaboration among multidiscipline.
BIM is an integrated information model whereby can shared among the entire stakeholder efficiently.
Modeling based to help the construction process.
Software for QS to do taking off, provide 3D image for Qs to have better view & imagination to do measurement.
Using 3D model, integrated process of design, estimating & construction. Paper less, reduce discrepancies in design, and provide information centre to the construction player.
Using "polyline" in CAD software to come out 3D model & then transfer it to "BIM". Thereafter measurement will be done out.
Managing construction information, integrate information, handling
QS works and managing building data
A new tool of construction model for standardization.
An overall modeling that incorporate must of the information for a building construction and it's visualize.
BIM enables collaboration among designers, QS, client, consultants, etc. in project implementation that can reduce time and cost, and at the same time increase quality, productivity and efficiency.
BIM is a platform of collaboration between different parties to provide information about each tread for a more effective and economical construction.
BIM is professional software incorporating all in one task to complete a project.
BIM is single/one software that provides us all the information needed by enter some of information required.
BIM is a shared knowledge resource among the construction players.
BIM is a system which it can share the information among all the parties and the system must be unique.
Collective information among industry players.
For better integration from various professionals e.g. Architect, QS, Engineers.
Integration of information & knowledge by the construction industry team players to give a value added & cost effective on the project/to the client, i.e. clash identification.
Requires collaboration between construction professionals and early detailing for clash analysis/modeling during design, construction as well as facilities/maintenance management.
A model which integrates all information among the designers and cost estimations in 1 standard, given all coding, item, measurement etc are the same, in order to create a successful project with zero mistakes, etc in shorter time, lesser cost and increase the quality of the project.
Complete the entire task by software to make it more efficiency and
24
easily to catch up in a short period.
Measurement Tool
Using softcopy to measure the GFA as well the BQ ‐ AutoCAD format.
Method of quantification by computer from drawings.
Software that can do every measurement which may replace QS fundamental role i.e. taking off.
Others
On line Qs experience such as E‐Tendering & E‐Bidding
Networking within domestic / LAN.
Architect and engineers need to provide detailed design for clash analysis/modeling.
Table 2 shows the brief explanation about BIM knowledge by the respondents. From these
responses, it shows that the respondents do realise that BIM is not only function for costing but also can
convert 2D drawings into 3D models. Among the respondents some also stated that BIM can be
described as measurement tool for taking off. Apart from that, a majority of the respondents had an
opinion that BIM is used to manage construction information, integrate information, handling QS works
and managing building data. Thus, BIM can enhance the collaboration and communication among the
construction players.
A question “Do you think QS will be slowly extinct in the future with the existence of BIM?” was
asked in the questionnaire, in order to gage their opinion on the effects of BIM application towards QS
in the future.
Figure 12 shows the distribution of respondent opinion on the effects of BIM application
towards QS profession in the future. From this pie chart, a majority of seventy four percent of the
respondents is of the opinion that QS will not be extinct, while twenty six percent believe that QS will be
extinct with the existence of BIM. This shows the majority of the respondents have a positive opinion
regarding BIM and that BIM application will not bring negative effects to the QS profession in the future
and cause the QS profession to be extinct.
3.5 Awar
Fi
seminars,
is fair. Fif
percentag
though M
to enhanc
reness on BI
igure 13 show
conferences
fty percent of
ge also respo
Malaysia had a
ce the awaren
F
IM program
ws the distri
s or workshop
f respondents
nded that the
already set up
ness of BIM, t
F
igure 12: QS ext
mmes
bution of the
p. From this p
s replied that
ey are unawa
p road shows
the percentag
Figure 13: Awar
tinction with BIM
e respondent
pie chart, the
t they are awa
re of BIM pro
s about BIM a
ge of awaren
reness of BIM pr
74%
Yes N
50%
Yes N
M existence
ts awareness
level of awa
are of BIM pr
ogrammes. Th
and many pro
ess of BIM ar
rogrammes
26%
No
50%
No
s on BIM pro
reness amon
rogrammes, h
his can be con
ogrammes ha
re still yet at a
ogrammes su
g the respon
however, the
ncluded that,
ad been cond
a low rate.
25
uch as
dents
same
, even
ucted
Th
programm
Fi
seminars,
had parti
programm
in BIM are
Th
programm
he responden
mes (seminars
Programme
igure 14 sho
conferences
icipated in B
mes. This sho
e still very po
he responden
mes (seminars
nts who are a
s, conference
es Title
A
A
B
P
B
Q
Q
Q
ows the distr
s or workshop
BIM program
ws that, the
or even thou
F
nts whom had
s, conference
aware of the B
es or worksho
Table 3: B
AGM
Awareness BIM
BIM Awarene
Product Launc
Building Inform
QS Conferenc
QSIC 2012
QS Principals'
ribution of re
p. From this
mmes, while
level of QS p
gh various pr
igure 14: Partici
d participated
es or worksho
71%
BIM program
op) as specifie
IM programmes
M (CREAM)
ss for JKR Sta
ch ‐ Glodon
mation Mode
e 2012
Dialogue
espondents’
pie chart, on
majority of
articipation i
rogrammes h
ipation in BIM p
d in BIM prog
op) they atten
29%
Yes No
mes had also
ed in the Tabl
s title
ff (PROKOM J
eling Confere
participation
nly twenty ni
them has n
n any progra
ad been orga
programmes
grammes had
nded as speci
%
o stated the ti
le 3 below.
JKR)
nce & Exhibit
n in BIM pro
ne percent o
ever particip
mmes as to a
anized.
stated the tit
fied in the Ta
tle of the BIM
tion
ogrammes su
of the respon
pated in any
acquire know
tle of the BIM
able 4 below.
26
M
ch as
dents
y BIM
wledge
M
27
Table 4: BIM programmes title
Programmes Title
AGM
Awareness BIM (CREAM)
BIM Awareness for JKR Staff (PROKOM JKR)
Product Launch ‐ Glodon
Building Information Modeling Conference & Exhibition
QS Conference 2012
QSIC 2012
QS Principals' Dialogue
Building Smart Singapore
Lake Constance Germany 5D Conference
Workshop by Cost X
PAQS 2010, PAQS 2011, PAQS 2012
As for the respondents that attended and participated in BIM programmers, the question “Did
you attend such seminars/conference/workshop at your own accord or sponsored by your firm?” was
asked. This is to obtain information of whether the BIM participation is due to instructions from the
firm or because of own self‐awareness.
Figure 15 shows the distribution of respondents’ sponsorship, either they had participated in the
BIM programmes (seminars/conference/workshop) at their own accord or been sponsored by firm.
Sixty three percent of the respondents were sponsored by the firm to participate in such BIM
programmes, while only thirty seven of them participated in the BIM programmes at their own accord.
This results show that the awareness of BIM in firm are higher than awareness as an individual by
twenty six percent. Nevertheless, more awareness programmes of BIM should be organized as there is
no doubt that BIM do bring improvement in the quality of construction project.
3.6 Invol
A
questionn
Fi
all of the
BIM, whil
of the re
applicatio
lvement in B
question “H
naire, to know
igure 16 show
respondents
e only ten pe
espondents h
on of BIM in c
Percen
tage
%
BIM projects
Have you eve
w how many r
ws the distrib
s (ninety perc
ercent of them
have never e
onstruction p
Figur
0
20
40
60
80
A
Figure 15: Re
s
er been invo
respondents
bution of resp
cent) have ne
m involved ha
experienced
projects in Ma
re 16: Responde
37
At my own acco
90%
spondents’ spon
lved in any
have had han
pondents’ han
ever been inv
ands on in pr
in projects
alaysia are sti
nt involvement
ord
Yes No
nsorship
projects that
nds on experi
nds on involv
volved in any
rojects that u
that apply B
ill very low.
in BIM projects
63
Sponsored by
10%
t use BIM?”
ence in hand
vement in BIM
construction
se BIM. This
BIM and it a
s
y my firm
was asked i
ling BIM proj
M project. A
n projects tha
s shows that,
also indicate
28
n the
ects.
Almost
at use
most
s the
29
Next, the respondents who had been involved in the BIM projects were asked more about BIM
application in construction stages, the problems faced and the benefit gains from applying BIM in the
projects.
Table 5: BIM application in construction stages
BIM Application in Construction Stages Design
Construction
Feasibility
Table 5 shows the stages that BIM was being used in the construction project that the
respondents had been involved in. From these responses, it shows that BIM had been applied in three
stages of construction, which are design stage, construction stage and feasibility stage. None of the
respondents had any experience using BIM in the maintenance stage.
Table 6: Problems experienced
Problems
Understanding of BIM concept among fresh grade, and expertise for implementing BIM
Not much experience in BIM
Internet Connections
Lack of training for the designers, PC technical issues (not compatible), no standard library for taking off purposes (using 3D Model), no standard input/measures to create info in the Revit Family/Components for the purpose of taking off
Limited within LAN
Non‐standard object parameters, step learning curve for the 5D BIM software, resistant from internal & external parties, lack of knowledge sharing among governments & industry player, and no standard BIM modeling, QTO & BQ standard imposed by government/authorities
30
Table 6 shows the problems experienced by the respondents during the course of the project
that uses BIM application. From these responses, it shows that the respondents had a difficulty in
understanding BIM concept, have limitations on knowledge of BIM software, and also faces technical
problems such as poor internet connections and limited access.
Table 7: Benefits experienced
Benefits
No information lost, able to visualize the end result, and changing 3D at the same time changes 2D
Increase in technological experience and paperless technology
Time saving in measurement, object visualization, and close detection reduce revoke
With the clash detection, the coordination meeting becomes more efficient and much easier for the designers to facilitate the whole design process
Table 7 shows the benefit experienced by the respondents during the course of the project that
uses BIM application. From these responses, it shows that the respondents agreed that BIM helps to
visualize the projects in 3D, taking off is done much faster, and increases the technology experience.
One of the response also said that the coordination meeting becomes more efficient and much easier
for the designers to facilitate the whole design process, thus, this enhances the collaboration and
communication between the construction player’s team
4.0 Level of awareness of Building Information Modeling (BIM)
4.1 Feasibility stage
Figure 17 and Table 8 shows the BIM awareness at feasibility stage. From the figure above, we
can notice that less than 7% of respondents (which means that only 2 to 3 respondents) are not aware
about the function of BIM during feasibility stage. Approximately 93% or 44 to 45 out of a total of 47
revealed they are aware about the true function of BIM during this stage. In addition to that, we can
see that more than 70% or 29 to 31 respondents are aware that BIM is able to project a model of the
project during this stage as to provide a better visualisation to all parties involved. This would able the
31
clients and designers to make any changes onto the model of which cost implication could be analysed
automatically.
Table 8: BIM awareness at feasibility stage
Not at all aware
Somewhat aware
Aware Total
Percent
(Frequency) Percent
(Frequency) Percent
(Frequency) Percent
(Frequency)
1
A brief design or model can be projected at early stage
MODEAS 4.26 (2) 34.04 (16) 61.70 (29) 100.00 (47)
2 Pre‐estimation can be identified within a shorter period
PRESHO 4.26 (2) 31.91( 15) 63.83 (30) 100.00 (47)
3 Any changes in the design will give effect to the pre‐estimate
CHADPR 6.38 (3) 29.79 (14) 63.83 (30) 100.00 (47)
4 Forming a better integration between designers and client
INTDECL 4.26 (2) 29.79 (14) 65.96 (31) 100.00 (47)
5
Client are able to make a better decision with the projected design or model
BETDEC 4.26 (2) 31.91( 15) 63.83 (30) 100.00 (47)
MODEAS PRESHO CHADPR INTDECL BETDEC
Not at all aware 4.26 4.26 6.38 4.26 4.26
Somewhat Aware 34.04 31.91 29.79 29.79 31.91
Aware 61.70 63.83 63.83 65.96 63.83
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Valid percentage ( %
)
32
Figure 17: BIM awareness at feasibility stage
4.2 Design stage
Figure 18 and Table 9 shows the BIM awareness at design stage. The percentage of bar chart
fluctuates, but in general more than 80% of respondents are aware about the usage of BIM during
design stage. Out of 12 questions, converting 2D drawings into 3D models score the highest under the
Not at all aware category, which is a 17.3% or 8 respondents. This might be due to the confusion where
respondents think that BIM can alter 2D paper drawings into 3D model. But the actual function is that
designers will need to design the construction model and input the information into it to make it an nD
model. Under the Aware category, serving as an information centre to provide better communication
among construction team members score the highest among the 12 questions, which is a 69.5% or 32
respondents. This is one of the major functions of BIM where the model itself contains a lot of
information regarding the proposed project, so that every members involved can easily understand the
requirement of that particular project. Other than that, the Not at all aware category only scored about
2% to 7% or 1 to 3 respondents. This clearly shows that BIM’s functions in design stage are well known
among Quantity Surveyors.
Table 9: BIM awareness at design stage
Not at all aware
Somewhat aware
Aware Total
Valid
Percent Valid
Percent Valid
Percent Valid
Percent
1 It converts 2D drawings into 3D models
CO2DND 17.39 (8) 30.43 (14) 52.17 (24) 100.00 (46)
2
It serves as an information centre to provide better communication among construction team members
INFOCEN 2.17 (1) 28.26 (13) 69.57 (32) 100.00 (46)
3
It is a platform that links all the data from different software such as AutoCAD, Tekla, Vico and etc.
LINDIFS 4.35 (2) 50 (23) 45.65 (21) 100.00 (46)
4 It reduces discrepancies between architect and engineer drawings
REDIAE 2.13 (1) 40.43 (19) 57.4 (27) 100.00 (47)
33
5 It reduces discrepancies between drawings and bill of quantities
REDRAB 4.35 (2) 45.65 (21) 50 (23) 100.00 (46)
6 It detects clashes between structures and ducting for services
DETCLA 2.27 (1) 40.91 (18) 56.82 (25) 100.00 (44)
7
Provide information such as building’s natural lighting system, building’s components and etc. For example, the door carries information about its fire rating, construction, glazing and also information about suppliers
INFNAT 4.26 (2) 48.94 46.81 (22) 100.00 (47)
8 It can automatically quantify every element and generate Bills of Quantities
AUTQUG 6.38 (3) 48.94 (23) 44.68 (21) 100.00 (47)
9 It increases the accuracy of the quantification for every item
INCACC 4.26 (2) 40.43 (19) 55.32 (26) 100.00 (47)
10 It provides auto quantification with zero miss counting or zero double counting
ZEMISC 6.38 (3) 46.81 (22) 46.81 (22) 100.00 (47)
11 It is able to cut short the duration of tendering by eliminating the taking off process
CUTDUR 6.38 (3) 31.91 (15) 61.70 (29) 100.00 (47)
12 Heading towards paperless technology by storing records in digital form
STORDIG 4.26 (2) 31.91 (15) 63.83 (30) 100.00 (47)
34
Figure 18: BIM awareness at design stage
4.3 Construction stage
Figure 19 and Table 10 reveals the BIM awareness at construction stage. Out of 46 respondents,
almost 90% of them fall in the category of Somewhat Aware and Aware that BIM can improve the
process of construction industry during the construction stage. The maximum and minimum
percentages for Not At All Aware category are 8.70% and 2.17% respectively. There are 4 respondents
that noted they are not aware that application of BIM is able to reduce construction wastage and
shorten construction period, 3 respondents recorded not aware that BIM is able to reduce variation
orders, reduces the probabilities of extension of time due to variation orders and disputes, ease the
project management procedures by following up project activities, cost and time schedule and reduces
dispute due to discrepancies. Only one respondent indicated not aware that BIM have a higher
tendency to meet the clients’ requirements.
From the findings, it can be summed up that Quantity Surveyors are quite aware of the function
and ability of BIM to ease and enhance the process of construction industry during the construction
CO2DND
INFOCEN
LINDIFS
REDIAE
REDRAB
DETCLA
INFNAT
AUTQUG
INCACC
ZEMISC
CUTDUR
STORDIG
Not at all aware 17.3 2.17 4.35 2.13 4.35 2.27 4.26 6.38 4.26 6.38 6.38 4.26
Somewhat aware 30.4 28.2 50.0 40.4 45.6 40.9 48.9 48.9 40.4 46.8 31.9 31.9
Aware 52.1 69.5 45.6 57.4 50.0 56.8 46.8 44.6 55.3 46.8 61.7 63.8
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
Valid percentage (%
)
35
stage. Only minor groups of Quantity Surveyor are not aware about the power of BIM. The finding
proof that BIM is getting stronger, more people get to know about the power of BIM.
Table 10: BIM awareness at construction stage
Not at all aware
Somewhat aware
Aware Total
Valid
Percent Valid
Percent Valid
Percent Valid
Percent
1 Able to reduce construction wastage
REDWAS 8.70 (4) 41.30 (19) 50 (23) 100 (46)
2 Able to shorten the construction period
SHOCOP 8.70 (4) 50 (23) 41.30 (19) 100 (46)
3 Able to reduce variation orders
REDVO 6.52 (3) 41.30 (19) 52.17 100 (46)
4
It reduces the probabilities of extension of time due to variation orders and disputes
REDEOT 6.52 (3) 43.48 (20) 50 (23) 100 (46)
5
It is able to ease the project management procedures by following up project activities, cost and time schedule
FOLOSHE 6.52 (3) 47.83 (22) 45.65 (21) 100 (46)
6 It reduces dispute due to discrepancies
REDISCR 6.52 (3) 47.83 (22) 45.65 (21) 100 (46)
7 The end product able to meet clients’ requirements
ENDCRE 2.17 (1) 47.83 (22) 50 (23) 100 (46)
Figure 19: BIM awareness at construction stage
REDWAS SHOCOP REDVO REDEOTFOLOSH
EREDISCR ENDCRE
Not at all aware 8.70 8.70 6.52 6.52 6.52 6.52 2.17
Somewhat aware 41.30 50.00 41.30 43.48 47.83 47.83 47.83
Aware 50.00 41.30 52.17 50.00 45.65 45.65 50.00
0.00
10.00
20.00
30.00
40.00
50.00
60.00
Vaid Pe
rcen
tage
(%)
36
4.4 Inuse and maintenance stage
Figure 20 and Table 11 reveals the BIM awareness to In‐use and maintenance stage. We can see
that about 90% and above of respondents are aware about the function of BIM in the In‐use and
Maintenance stage, whereas only 4.35% to 8.89% of respondents fall in the Not At All Aware category.
There are only 2 respondents who are not aware that BIM is able to store historical data as references
for new projects, obtain pre‐estimation on maintenance cost and retrieve the building data for
renovation and replacement purposes. Besides that, 3 respondents are not aware that with the
application of BIM, maintenance can be done at the correct timing and spot and 4 respondents are not
aware that BIM is able to reduce the energy wastage based on the energy reading provided.
From the bar chart, we can see that Quantity Surveyors know that BIM is not only about 3D
designing, whereas BIM is able to create a whole picture of the project which is nD model. They know
that data from BIM can be use for maintenance purposes or even renovation purposes. The readings
depicts that the knowledge of Quantity Surveyors towards BIM is no longer limited to measuring or
designing a project. Instead, BIM is a platform that carries a lot of information regarding the project.
Table 11: BIM awareness at in‐use and maintenance stage
Not at all aware
Somewhat aware
Aware Total
Valid
Percent Valid
Percent Valid
Percent Valid
Percent
1 It is able to store historical data as references for new projects
STOHISD 4.35 (2) 34.78 (16) 60.87 (28) 100 (46)
2 Able to obtain pre‐estimation on maintenance cost
PRESMAC 4.44 (2) 44.44 (20) 51.11 (23) 100 (45)
3
Able to reduce the energy wastage based on the energy reading provided by BIM
REDENER 8.89 (4) 42.22 (19) 48.89 (22) 100 (45)
4 Maintenance can be done at the correct timing and spot
CORTIMS 6.67 (3) 40 (18) 53.33 (24) 100 (45)
5
Able to retrieve the building data for renovation and replacement purposes
RETDAT 4.35 (2) 47.83 (22) 47.83 (22) 100 (46)
37
Figure 20: BIM awareness to in‐use and maintenance stage
4.5 Quantity surveyors’ task with the incorporation of BIM
Figure 21 and Table 12 illustrates the QS tasks with the incorporation of Building Information
Modeling. Out of the total of 48 respondents, 100% of the respondents fall in the category of
Somewhat Aware and Aware, which means that none of the respondents is not aware that the QS tasks
mentioned are still needed even with the incorporation of BIM. From the figure above, we can see that
the percentages are quite evenly distributed among these 9 questions. Ranging from 64.58% to 81.25%
or 31 to 39 respondents out of 48 is totally aware about these issues. From the figure, the result depicts
that QS are aware that the existence of BIM is not a threat to QS profession, instead BIM will ease and
improve the quality and professionalism of QS works.
STOHISD PRESMAC REDENER CORTIMS RETDAT
Not at all aware 4.35 4.44 8.89 6.67 4.35
Somewhat aware 34.78 44.44 42.22 40.00 47.83
Aware 60.87 51.11 48.89 53.33 47.83
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Valid Percentage (%
)
38
FESTUD
COESPL
PRECON
PRETEND
CALTEND
EVATEND
INTEVAL
INTECER
FINACC
Not at all aware 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Somewhat aware 35.42 27.08 27.08 18.75 22.92 20.83 27.08 25.00 20.83
Aware 64.58 72.92 72.92 81.25 77.08 79.17 72.92 75.00 79.17
0.0010.0020.0030.0040.0050.0060.0070.0080.0090.00
Valid Percentage (%
)
Table 12: QS tasks with the incorporation of Building Information Modeling
Not at all aware
Somewhat aware
Aware Total
Valid
Percent Valid
Percent Valid
Percent Valid Percent
1 QS is still needed to carry out feasibility study
FESTUD 0 (0) 35.42 (17) 64.58 (31) 100.00 (48)
2 QS is still needed to prepare cost estimate and cost plan for new projects
COESPL 0 (0) 27.08 (13) 72.92 (35) 100.00 (48)
3
QS is still needed for contractual task such as preparing condition of contract
PRECON 0 (0) 27.08 (13) 72.92 (35) 100.00 (48)
4
QS is still needed for documentation in preparing tender document
PRETEND 0 (0) 18.75 (9) 81.25 (39) 100.00 (48)
5 QS is still needed to call for tenders
CALTEND 0 (0) 22.9 (11) 77.08 (37) 100.00 (48)
6 QS is still needed to evaluate tenders
EVATEND 0 (0) 20.83 (10) 79.17 (38) 100.00 (48)
7 QS is still needed to carry out interim valuation
INTEVAL 0 (0) 27.08 (13) 72.92 (35) 100.00 (48)
8 QS is still needed to prepare interim certificate
INTECER 0 (0) 25 (12) 75 (36) 100.00 (48)
9 QS is still needed to prepare of final account
FINACC 0 (0) 20.83 (10) 79.17 (38) 100.00 (48)
Figure 21: QS tasks with the incorporation of Building Information Modeling
39
5.0 Cross Tabulation Analysis
5.1 Level of awareness vs gender
Feasibility Stage
Figure 22: BIM awareness at feasibility stage vs gender
Figure 22 illustrates the BIM Awareness at Feasibility Stage against gender. From the figure
shown, the awareness towards BIM in the feasibility stage by female gender is the highest compared to
the male, with an average of sixty percent to seventy five percent awareness. Both female and male
gender had the same percentage of awareness in ‘pre‐estimation can be identified within a shorter
period’ with sixty four percent. From the figure also, it can be seen that there are percentage of male
gender that are Not At All Aware of BIM in feasibility stage compared to none by the female.
F M F M F M
Not at all aware Somewhat aware Aware
MODEAS 0 9 36 32 64 59
PRESHO 0 9 36 27 64 64
CHADPR 0 14 28 32 72 55
INTDECL 0 9 28 32 72 59
BETDEC 0 9 28 36 72 55
0
20
40
60
80
100
Valid Percentage (%
)
40
Design Stage
Figure 23: BIM awareness at design stage vs gender
Figure 23 shows the BIM awareness at Design Stage vs gender. As in the feasibility stage, the
female gender again showed a great response in design stage compared to the male. The percentage of
Not At All Aware for female group also none except for, only thirteen percent of female which Not At All
Aware that BIM can converts 2D drawings into 3D models.
F M F M F M
Not at all aware Somewhat aware Aware
CO2DND 13 23 21 41 67 36
INFOCEN 0 5 21 36 79 59
LINDIFS 0 9 46 55 54 36
REDIAE 0 5 44 36 56 59
REDRAB 0 9 50 41 50 50
DETCLA 0 5 43 38 57 57
INFNAT 0 9 52 45 48 45
AUTQUG 0 14 60 36 40 50
INCACC 0 9 44 36 56 55
ZEMISC 0 14 60 32 40 55
CUTDUR 0 14 36 27 64 59
STORDIG 0 9 24 41 76 50
0
20
40
60
80
100
Valid Percentage (%
)
41
Construction Stage
Figure 24: BIM Awareness at Construction Stage vs Gender
Figure 24 shows the BIM awareness at Construction Stage against gender. For this particular
stage, both gender had the same level of awareness. Although the Not At All Aware percentage of male
are higher than the female, the percentage of Aware and Somewhat Aware are almost in the same
range for both male and female gender.
F M F M F M
Not at all aware Somewhat aware Aware
REDWAS 4 14 42 41 54 45
SHOCOP 4 14 54 45 42 41
REDVO 4 9 46 36 50 55
REDEOT 0 14 50 36 50 50
FOLOSHE 0 14 54 41 46 45
REDISCR 0 14 54 41 46 45
ENDCRE 0 5 50 45 50 50
0
20
40
60
80
100
Valid Percentage (%
)
42
Inuse and maintenance stage
Figure 25: BIM awareness at in‐use and maintenance stage vs gender
Figure 25 reveals the BIM awareness at In‐Use and Maintenance Stage against gender. The
highest percentage of Aware is from the female, while the Somewhat Aware is higher among males. The
male also showed a small percentage of Not At All Aware status. In overall, although female gender did
show higher percentage of BIM awareness compared to male, the awareness at In‐Use and
Maintenance stage is still low as the percentage of awareness are in the average of fifty percent.
F M F M F M
Not at all aware Somewhat aware Aware
STOHISD 0 9 29 41 71 50
PRESMAC 0 9 43 45 57 45
REDENER 4 14 35 50 61 36
CORTIMS 0 14 39 41 61 45
RETDAT 0 9 46 50 54 41
0
20
40
60
80
100
Valid Percentage (%
)
43
5.2 Level of awareness vs experience
Feasibility Stage
Figure 26: BIM awareness at feasibility stage vs experience
Figure 26 reveals the BIM awareness at Feasibility Stage against experience. From the figure,
the awareness level is high across all groups of respondents except for the group with 11 to 15 years of
experience, with an average of twenty percent only. The awareness of the group with more than 16
years experience, 6 to 11 years experience and below 5 years experience shows more than fifty percent
that they are aware of BIM in implementation in feasibility stage. Nonetheless, the only groups that are
fully agree by hundred percent on the statement that BIM is forming a better integration between
designers and client is the group that have below 5 years of experience.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Not at all aware Somewhat aware Aware
MODEAS 0 0 40 0 18 40 40 38 82 60 20 62
PRESHO 0 0 40 0 27 40 40 29 73 60 20 71
CHADPR 0 10 40 0 18 40 40 29 82 50 20 71
INTDECL 0 0 40 0 0 40 40 38 100 60 20 62
BETDEC 0 0 40 0 27 30 40 33 73 70 20 67
0
20
40
60
80
100
Valid Percentage (%
)
44
Design Stage
Figure 27: BIM awareness at design stage vs experience
Figure 27 shows the BIM awareness at Design Stage versus experience. The Aware percentage
shows the highest in overall compare to Somewhat Aware and Not At All Aware. In the Aware
percentage, every group of the respondents shows a good percentage of awareness with the range of
fifty percent to eighty percent. This result is excluding the group of 11 to 15 years of experiences where
the Aware percentage of them are only in range of twenty to forty percent.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Not at all aware Somewhat aware Aware
CO2DND 9 11 40 19 36 11 40 33 55 78 20 48
INFOCEN 0 0 20 0 18 22 40 33 82 78 40 67
LINDIFS 0 0 20 5 55 33 60 52 45 67 20 43
REDIAE 0 0 20 0 45 44 40 36 55 56 40 64
REDRAB 0 0 20 5 36 44 60 48 64 56 20 48
DETCLA 0 0 20 0 50 38 40 38 50 63 40 62
INFNAT 0 11 20 0 45 33 40 59 55 56 40 41
AUTQUG 0 11 20 5 45 44 60 50 55 44 20 45
INCACC 0 0 20 5 36 33 60 41 64 67 20 55
ZEMISC 0 0 20 9 64 44 60 36 36 56 20 55
CUTDUR 0 0 20 9 18 44 60 27 82 56 20 64
STORDIG 0 0 20 5 27 22 60 32 73 78 20 64
0
20
40
60
80
100
Valid Percentage (%
)
45
Construction Stage
Figure 28: BIM awareness at construction stage vs experience
Figure 28 reveals the BIM awareness at Construction Stage against experience. In overall, the
level of awareness in this stage is quite poor, as the range of Aware and Somewhat Aware percentages
are within twenty percent to sixty percent only. For the Not At All Aware, the respondents with 11 to 15
years of experience shows the highest percentage, while respondents with more than 16 years of
experience has the least percentage, and none for below 5 years of experience nor the respondents with
6 to 10 years of experience.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Not at all aware Somewhat aware Aware
REDWAS 0 0 60 5 45 38 20 45 55 63 20 50
SHOCOP 0 0 60 5 55 38 20 59 45 63 20 36
REDVO 0 0 60 0 55 38 20 41 45 63 20 59
REDEOT 0 0 40 5 45 38 40 45 55 63 20 50
FOLOSHE 0 0 40 5 45 50 40 50 55 50 20 45
REDISCR 0 0 40 5 45 50 40 50 55 50 20 45
ENDCRE 0 0 20 0 36 38 60 55 64 63 20 45
0
20
40
60
80
100
Valid Percentage (%
)
46
Inuse and Maintenance Stage
Figure 29: BIM awareness at in‐use and maintenance stage vs experience
Figure 29 reveals the BIM awareness at In‐Use and Maintenance Stage versus experience. In
overall, the level of awareness in this stage is quite poor, as the range of Aware and Somewhat Aware
percentages are within twenty percent to seventy five percent only. For Not At All Aware, the
respondents with 11 to 15 years of experience shows the highest percentage, followed by the
respondents with 6 to 10 years experience, while respondents with more than 16 years of experience
showed a very least percentage, and none for below 5 years of experience.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Not at all aware Somewhat aware Aware
STOHISD 0 13 20 0 36 13 40 41 64 75 40 59
PRESMAC 0 13 20 0 36 38 40 52 64 50 40 48
REDENER 0 13 40 5 45 38 20 48 55 50 40 48
CORTIMS 0 13 20 5 36 25 40 48 64 63 40 48
RETDAT 0 13 20 0 55 38 40 50 45 50 40 50
0
20
40
60
80
100
Valid Percentage (%
)
47
5.3 Level of awareness vs registration
Feasibility Stage
Figure 30: BIM awareness at feasibility stage vs QS registration
Figure 30 illustrates the BIM Awareness at Feasibility Stage versus the QS Registration. From the
figure shown, the awareness of Non‐registered QS towards BIM in the feasibility stage is the highest
compared to the Registered Graduate QS and the Registered QS. In overall, every group of respondents
is aware of the role of BIM at the feasibility stage by more than fifty percent. They are aware and
concerned that BIM are a brief design or model that can be projected at early stage, pre‐estimation can
be identified within a shorter period, and any changes in the design will have effect on the pre‐
estimation. They are also aware that BIM is forming a better integration between designers and client,
thus client are able to make a better decision with the projected design or model.
Reg. QSReg.
Grad. QSNon Reg.
QSReg. QS
Reg. Grad. QS
Non Reg. QS
Reg. QSReg.
Grad. QSNon Reg.
QS
Not at all aware Somewhat aware Aware
MODEAS 4 6 0 39 39 0 57 56 100
PRESHO 4 6 0 35 39 0 61 56 100
CHADPR 9 6 0 30 33 17 61 61 83
INTDECL 4 6 0 39 28 0 57 67 100
BETDEC 4 6 0 39 28 17 57 67 83
0
20
40
60
80
100
Valid percentage (%
)
48
Design Stage
Figure 31: BIM awareness at design stage vs QS registration
Figure 31 illustrates the BIM awareness at Design Stage versus the QS registration. In overall,
the Non‐registered QS had shown a great awareness towards BIM at design stage compared to the
Registered Graduate QS and the Registered QS. The Aware percentage by the Non‐registered QS are the
highest among other groups with the range of eighty percent to hundred percent. The percentage of
Non‐ registered QS that Somewhat Aware is also very low and none in Not At All Aware. This shows that
the Non‐registered QS had more knowledge and concern about the BIM implementation in the
construction industry compared to the Registered Graduate QS and the Registered QS.
Reg. QSReg.
Grad. QSNon Reg.
QSReg. QS
Reg. Grad. QS
Non Reg. QS
Reg. QSReg.
Grad. QSNon Reg.
QS
Not at all aware Somewhat aware Aware
CO2DND 22 18 0 35 29 17 43 53 83
INFOCEN 0 6 0 39 24 0 61 71 100
LINDIFS 4 6 0 61 53 0 35 41 100
REDIAE 0 6 0 39 50 17 61 44 83
REDRAB 4 6 0 52 47 17 43 47 83
DETCLA 0 6 0 41 47 20 59 47 80
INFNAT 4 6 0 52 61 0 43 33 100
AUTQUG 9 6 0 48 67 0 43 28 100
INCACC 4 6 0 43 50 0 52 44 100
ZEMISC 9 6 0 39 67 17 52 28 83
CUTDUR 9 6 0 35 39 0 57 56 100
STORDIG 4 6 0 43 22 17 52 72 83
0
20
40
60
80
100
Valid Percentage (%
)
49
Construction Stage
Figure 32: BIM awareness at construction stage vs QS registration
Figure 32 reveals the BIM awareness at Construction Stage against QS registration. Similar to
Design stage, the Non‐registered QS again had the highest percentage in BIM awareness at Construction
stage, compared to other groups of respondent. While the percentage of awareness for Registered
Graduate QS and the Registered QS are almost the same.
Reg. QSReg.
Grad. QSNon Reg.
QSReg. QS
Reg. Grad. QS
Non Reg. QS
Reg. QSReg.
Grad. QSNon Reg.
QS
Not at all aware Somewhat aware Aware
REDWAS 9 12 0 48 41 17 43 47 83
SHOCOP 9 12 0 57 59 0 35 29 100
REDVO 4 12 0 39 53 17 57 35 83
REDEOT 9 6 0 43 59 0 48 35 100
FOLOSHE 9 6 0 48 65 0 43 29 100
REDISCR 9 6 0 48 59 17 43 35 83
ENDCRE 0 6 0 57 53 0 43 41 100
0
20
40
60
80
100
Valid Percentage (%
)
50
Inuse and Maintenance Stage
Figure 33: BIM awareness at in‐use and maintenance stage vs QS registration
Figure 33 shows the BIM awareness at In‐Use and Maintenance Stage against QS registration.
The result of Aware percentage for Non‐registered QS is again higher than Registered Graduate QS and
Registered QS. Despite the low percentage of awareness for Registered Graduate QS and Registered QS
in Aware and Somewhat Aware, both groups also showed small percentage in Not At All Aware, while
none for Non‐registered QS.
Reg. QSReg.
Grad. QSNon Reg.
QSReg. QS
Reg. Grad. QS
Non Reg. QS
Reg. QSReg.
Grad. QSNon Reg.
QS
Not at all aware Somewhat aware Aware
STOHISD 4 6 0 43 35 0 52 59 100
PRESMAC 4 6 0 48 56 0 48 38 100
REDENER 9 13 0 43 44 33 48 44 67
CORTIMS 9 6 0 43 50 0 48 44 100
RETDAT 4 6 0 48 59 17 48 35 83
0
20
40
60
80
100
Valid Percentage (%
)
51
PART B: BUILDING INFORMATION MODELLING READINESS AMONG QUANTITY SURVEYING FIRMS
6.0 Introduction
This chapter presents the interim findings and discussions of the survey. It is divided into a few
sections i.e. the organisations’ profile; the organisations’ readiness profile; the organisations’ level of
readiness in the aspect of technology, people, process and management; and finally the cross tabulation
analysis.
A total of 80 questionnaires were distributed to the firms’ owners during conferences and
seminars held between November 2012 and January 2013. The return rate is about 22.5% percent or 18
responded questionnaires with about 90%‐95% of validity. Bar charts, pie chart and tables were used to
present and summarise the findings.
7.0 Organisations’ profile
7.1 Designation
Figure 34 shows the respondents’ designation in the organisation. Thirty five percent of the
respondents are Directors, followed by Managing Director and Partner with percentage of (eighteen
percent). Principal and Senior Quantity Surveyors represents twelve percent each, while the remaining
six percent are other designations. This result shows that, a total of eighty two percent from the
respondents are represent by the upper level of an organisation which include Director, Managing
Director Partner and Principal. It expected that the persons that manage a firm should be most to
known the existence of Building Information Modelling (BIM) as this application can enhance the quality
of works and help the firm to deliver a project in way better.
52
Figure 34: Respondent’s designation
7.2 Years of establishment
Figure 35 shows the period of years the respondents company have in operation. 53% percent
of the respondent’s firm had been established for more than 15 years, while firms that had been
established in less than 5 years and between 6 to 10 years had equal percentage (18%). The least was
firms established between 11 to 15 years (18%). This illustrates that majority of the respondents
represent organisations which are well experienced in the industry.
Figure 35: Years of establishment
1218 18
35
126
0
10
20
30
40
Principal Partner Managing Director
Director Senior Quantity Surveyor
Others
Percen
tage
%
18 1812
53
0
10
20
30
40
50
60
less than 5 years
6 to 10 years 11 to 15years more than 15years
Percen
tage
%
7.3 Numb
Fi
of the res
having 11
By this re
(represen
sized firm
firms, wh
7.4 Comp
Fi
million rin
two perce
million w
companie
percent.
ber of empl
igure 36 show
spondent ha
1 to 20 emplo
esult, we can
nt by less than
m (represent b
ich makes the
pany turnov
igure 37 reve
nggit. In 2010
ent of them h
were sixty se
es with turnov
oyees
ws the respon
d less than 1
oyees. Only tw
n see that, th
n 10 employe
by more than
e findings som
ver
eals the resp
0, fifty eight
had turnover
even percent
ver below 1 m
le
ndents’ total
10 employee
wenty two pe
he responden
ees), medium‐
n 20 employe
mewhat inclu
Figure 36: Tot
pondents’ com
percent of t
below 1 milli
t, representin
million were
39%
ess than 10
employees in
s and the sa
ercent of the
nts had fulfill
‐sized firm (re
es). Thus, th
sive.
tal number of em
mpany turno
he responde
on. While in
ng an increa
thirty three p
39%
22%
11 to 20
n the firm org
me percenta
respondents
ed all three
epresent by 1
he findings of
mployees
over in 2010
nts had turno
2011, compa
ase of nine
percent, whic
%
more than 20
ganisation. T
age also fall i
s had more th
categories of
11 to 20 emp
f this survey c
and 2011 be
over above 1
anies that had
percent. On
ch represent
Thirty nine pe
in the catego
han 20 emplo
f firms; smal
loyees), and
covered all ty
elow and abo
1 million and
d turnover ab
the other
a decrease of
53
ercent
ory of
oyees.
l firm
large‐
ype of
ove 1
forty
bove 1
hand,
f nine
7.5 Mana
Fi
from firm
percent w
quality of
of the pro
responde
construct
agement cer
igure 38 show
m with an ISO
were from firm
f the products
oducts or effe
nt used the I
ion industry.
Percen
tage
%
rtification
ws the respon
O managemen
ms without IS
s manufactur
ectiveness of
SO managem
58
0
10
20
30
40
50
60
70
Figure 37
ndents’ firm m
nt certificate
SO managem
red or service
the services.
ment in delive
Figure 38: Ma
8
42
2010
With IS
: Company turn
management
(sixty seven
ment certificat
es provided an
. From this re
ery their prod
anagement cert
67
33
2011
67%
33%
SO Withou
nover
certification
percent), w
tion. The cer
nd assure the
esult, it indic
uct and servi
tification
Ab
Be
ut ISO
. Half of the
hile the rema
rtifications fr
e public regar
ates that mo
ices, thus it is
bove 1 million
elow 1 million
respondents
aining thirty
om ISO signif
rding the relia
re than half o
s good sign fo
54
were
three
fy the
ability
of the
or our
55
7.6 Access to computer and internet connection
A question “How many percent of the staff in your firm have access to their own computer? And
“How many percent of computers in your company have access to the internet?” were asked. The
essence of the question is that internet has made information available in a quick and easy manner,
publicly accessible and within easy reach. It enhances communications and social networking, through
owning own computer with an internet access might helps to produce a better quality of product.
Figure 39 shows the distribution of computer ownership and internet access among the staff in
the organisation. Hundred percent of the respondents said that more than seventy five percent of their
staff had their own computer, while seventy eight percent of the respondents also reported that more
than 75 percent of their computers had an internet access. However, the result also shows six percent
of the respondents reported 25 percent to 50 percent of their computers had an internet access, and
the remaining seventeen percent of the respondents indicated that less than 25 percent of their
computer has internet access.
Figure 39: Own computers and internet access
100
17
6
78
0
20
40
60
80
100
<25% 25%‐50% >75%
Percen
tage
%
Staff had access to own computer
Computer with internet access
56
8.0 Readiness Profile
8.1 Information technology application in Malaysia
Figure 40 shows how the respondents rate the application of Information Technology (IT) in
Malaysia construction industry vis‐a‐vis the following scales: Construction industry recently has used
latest information technologies to enhance the performance of worker; increase the productivity and
improve safety; and information technology also plays important role to avoid and mitigate the conflict
and dispute between owner and contractor. The result indicates more than half of the respondent (sixty
one percent) agreed that IT in Malaysia construction industry is either good or very good. The result also
shows that thirty three percent of the respondents rated IT application in Malaysia construction industry
fair while only six percent said is poor.
Figure 40: Information Technology (IT) application in Malaysia construction
Figure 41 shows how the respondents rate the application of Information Technology (IT) by
Quantity Surveyor in Malaysia construction industry. Based on the result, more than half of the
respondents (seventy eight percent) agreed that IT in Malaysia construction industry is good or very
good. The result also shows that seventeen percent of the respondents rated it fair and only six percent
of the respondents is of the notion that application of Information Technology (IT) by Quantity Surveyor
in Malaysia construction industry is poor.
6
33
44
17
0
10
20
30
40
50
Poor Fair Good Very Good
Percen
tage
%
57
Figure 41: Information Technology (IT) application by QS in Malaysia
8.2 Knowledge on BIM
In the survey, respondents were asked to give a brief explanation about BIM based on their
knowledge or opinion. The responses were categories into four categories, namely “3D modelling”,
“managing construction information and integrate information”, “measurement tool” and “others”.
Table 13 shows the brief explanation about BIM knowledge by the respondents. From these
responses, it shows that the respondents do realise that BIM makes 3D modelling analysis clear, makes
visualization of buildings information in 3D models. The respondents also stated that BIM can be
described as measurement tool for taking off purposes, calculating GFA and preparing BQ. Apart from
that, a majority of the respondents had an opinion that BIM play roles as collective information among
industry players.
6
17
50
28
0
10
20
30
40
50
Poor Fair Good Very Good
Percen
tage
%
58
Table 13: Brief explanation about BIM knowledge
Categories of Answers Answers
3D Modeling
3D modeling, clear analysis
An overall modeling that incorporate most of the information for a buildings which is visualize
Collaborative software for clear analysis among 3D modeling during feasible/estimate stage as well as construction; and facilities maintenance after completion
Managing Construction Information and
Integrate Information Collective information among industry player
Measurement Tool
BQ measurement
Knowledge more related to measurement using CAD software
A model software of the various elements of a construction project, where the user can use to extract quantity & lost (the two mere elements among others) for quick production of BQ
Quantification for soft drawings
Softcopy drawings to be used for the purpose of calculating GFA, BQ preparation
Others Use the computer/project software in helping to complete the task
8.3 Participation in BIM program
A question “Have you ever sent your staff to any seminars/conferences/workshop on BIM?” was
asked in order to get the respondents’ feedback about the BIM awareness.
Figure 42 reveals the distribution of respondents’ staff participation in BIM programme. The
percentage of the result is quite close. Forty seven percent of the respondents had sent their staff for
BIM programmes such as seminars, conferences or workshop. And the remaining fifty three percent had
never sent their staff to participate in any BIM programmes. It can therefore be inferred that, even
Malaysia had already set up road shows about BIM and many programmes conducted to enhance the
awareness of BIM, the response from the construction players, precisely the Quantity Surveyor is still
not good enough. Respondents which had sent their staff BIM programmes also stated the title of the
BIM programmes (seminars, conferences or workshop) as specified in the Table 14 below.
R
programm
8.4 Parti
Fo
software?
Fi
training. F
attend or
send their
espondents
mes (seminars
BIM Progr
icipation in
or further an
?” was asked
igure 43 sho
From this pie
r participate
r staff to atte
Figu
whom had s
s, conference
rammes Title
BIM softwar
nalysis, a que
in the questio
ows the distr
e chart, only t
in BIM relate
end or particip
ure 42: Staff par
sent their st
es or worksho
Table 14: B
re training
estion “Have
onnaire.
ibution of re
twenty nine
ed software t
pated in any B
rticipation in BIM
aff BIM prog
op) as specifie
BIM programme
BIM seminars
Introduction
RISM Program
Product Laun
Seminar by C
e you ever se
espondents’ s
percent of th
training, whil
BIM related s
53%
Yes N
M programme
grammes had
ed in the Tabl
es title
s / software lau
to BIM related
mmes
nch ‐ Glodon
ost X
ent your sta
staff particip
he responden
le a majority
software train
47%
No
d stated the
le 14 below.
unch, training
d measuremen
ff for trainin
ation in BIM
nts that had m
of seventy o
ning.
e title of the
t (taking off)
ng on BIM re
M related soft
make their st
one percent
59
e BIM
elated
tware
taff to
never
R
the title o
8.5 Invol
To
involved i
involveme
involved i
involved i
that appli
very low.
N
applicatio
projects.
espondents’
of the BIM pro
lvement in B
o know the r
in any projec
ent in BIM p
in any project
in BIM projec
es BIM and it
ext, the resp
on in construc
Figure
whom sent t
ogrammes as
BIM Software
BIM Projects
espondents e
cts that use B
project. Alm
ts that use B
cts. This show
t also indicate
ondents who
ction stages,
e 43: Staff partic
their staff to
specified in t
Table 15: B
training
s
experience in
BIM?” was as
ost all of th
IM. Only the
ws that, most
es the applic
om had been
the problems
71%
cipation in BIM s
participate i
the Table 15 b
BIM software tra
Training for G
New IT ‐ Auto
n handling BIM
sked. Figure
e responden
e remaining tw
t of the respo
cation of BIM
involved in t
s faced and t
29%
Yes No
software trainin
n BIM relate
below.
aining
Glodon
oCAD
M projects, a
44 shows th
ts (eighty eig
welve percen
ondents neve
in constructi
he BIM proje
the benefit ga
%
ng
d software t
question “Ha
he distributio
ght percent)
nt of the resp
er been exper
on projects in
ect were aske
ained from a
raining had s
ave you ever
on of respond
have never
pondents had
rienced in pro
n Malaysia ar
d more abou
pplying BIM i
60
stated
been
dents’
been
been
ojects
re still
t BIM
in the
Ta
responde
construct
that BIM a
Ta
that used
new softw
the respo
able 16 show
nts had bee
ion which are
also might be
able 17 show
BIM applicat
ware and to p
ndent that th
P
Figure
ws the stage
n involved in
e design stag
e applied in th
Tab
BIM
ws the proble
tion. Their re
provide a tra
he software is
Problems
e 44: Responden
es that BIM
n. The resu
ge and constr
he maintenan
ble 16: BIM appl
M Application
Co
ms experienc
esponses show
ined staff for
s not as good
Table 17: P
Expens
New so
To acqu
Softwa
nt’s involvemen
was being u
lt shows tha
ruction stage
nce stage or in
ication in const
n in Construct
Design
onstruction
ced by the re
w that the fir
r that particu
as expected.
Problems experi
sive software
oftware need
uire / train st
re not as goo
88%
Yes No
t in BIM project
used in the
at BIM had b
. None of th
n feasibility st
ruction stages
tion Stages
espondents d
rms had a diff
ular software
.
enced
learning curv
aff
od as expecte
12%
ts
construction
been applied
he responden
tage.
uring the cou
ficulty allocat
. There is als
ve
d.
n project tha
in two stag
nts had an op
urse of the p
ting budget t
o an opinion
61
at the
ges of
pinion
roject
o buy
from
62
Table 18 below the benefit experienced by the respondents during the course of the project
that used BIM application. The result shows that the respondent agreed that BIM provides detailed
design which involves architect, M&E and engineers at early stage and helps to provide clear analysis,
whereby problems such as design matters can be sorted out earlier. Thus a considerable amount of
variation orders during construction can be prevented from occurring.
Table 18: Benefits experienced
Benefits
Detailed design involving architect, M&E and engineers at early stage and/or clear analysis sorts out design matters earlier and prevent considerable amount of VO's during construction.
9.0 Level of readiness among quantity surveying firms
9.1 Technology aspect
Figure 45 and Table 19 show the BIM readiness from the aspect of technology. In general, we
can notice that majority of the respondents moderately agree that our technology is ready to integrate
BIM in the construction industry. There are 23.53% or 4 respondents who disagree that they outsource
or appoint in‐house staff to be an IT manager for their company. This might be because there are still
some minor Quantity Surveying firms which do not focus much on IT and process their works manually.
Under moderate the first two questions recorded 64.71% (11 respondents) and 70.59% (12
respondents) respectively. The implication is that the current system we are using now is not well
integrated among the parties involved, but respondents did know that this feature is needed for data
and information sharing. For the rest, approximately 50% or more than 8 respondents do agree that we
are ready for the change.
63
Table 19: BIM readiness from the aspect of technology
Disagree Moderate Agree Total
Percent (Frequency)
Percent (Frequency)
Percent (Frequency)
Percent (Frequency)
1
We use collaborative system to record all transactions during a project and all the information required (i.e. integrated project delivery)
COLSYS 17.65 (3) 64.71 (11) 17.65 (3) 100.00 (17)
2
We use integrated system to enables all the data needed by any of the participants interlinked.
INTSYS 11.76 (2) 70.59 (12) 17.65 (3) 100.00 (17)
3
We adopt ICT to improve communication, closer relationships, and overcome the geographical problem.
ADOSIT 5.88 (1) 17.65 (3) 76.47 (13) 100.00 (17)
4
We have adequate information technology infrastructure in place and available to the people in the company.
ADEQIN 5.88 (1) 41.18 (7) 52.94 (9) 100.00 (17)
5
We do focus on ICT skills development and/or employing ICT experts (i.e. either outsourcing or appointing in‐house staff to be an IT Manager etc).
SKIDEV 23.53 (4) 47.06 (8) 29.41 (5) 100.00 (17)
6
We have the basic internet requirements to go online, such as modem, service provider etc.
BASREQ 0.00 (0) 11.76 (2) 88.24 (15) 100.00 (17)
7
We will install the necessary software that meets the minimum requirements to run the BIM software.
WILINS 5.88 (1) 23.53 (4) 70.59 (12) 100.00 (17)
8
We have sufficient hardware with minimum requirements to run the BIM software.
SUFHAR 17.65 (3) 35.29 (6) 47.06 (8) 100.00 (17)
64
Figure 45: BIM readiness from the aspect of technology
9.2 People aspect
Figure 46 and Table 20 show the BIM readiness from the aspect of people. From the figure, we
can see those employees are not familiar with BIM, they might know the function and how powerful
BIM are, but they have not come across with the platform and do not have the chance to experience it
by themselves. This problem can be overcome by proper training or seminars on using BIM. On top of
that, we notice that the firms are ready to provide specific training and available resources to employees
in implementing BIM, 100% or 17 respondents fall in the category of Moderate and Agree. We can say
that the employers can see the future of BIM and they are ready to provide trainings to their employees
to push them to the next level. Besides, 0% or none of the respondents disagree to assist their
workforce in re‐skilling and to capitalize on the rapidly emerging technologies. The rapidly emerging
technologies really change our lifestyle, it helps to improve and enhance the quality of our works or end
product. From the aspect of people, Quantity Surveying firms are ready to accept BIM as long as there is
sufficient training to guide them to the optimum level.
COLSYS INTSYS ADOSIT ADEQIN SKIDEV BASREQ WILINSSUFHA
R
Disagree 17.65 11.76 5.88 5.88 23.53 0.00 5.88 17.65
Moderate 64.71 70.59 17.65 41.18 47.06 11.76 23.53 35.29
Agree 17.65 17.65 76.47 52.94 29.41 88.24 70.59 47.06
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
100.00
Valid Percentage (%
)
65
Table 20: BIM readiness from the aspect of people
Disagree Moderate Agree Total
Percent
(Frequency) Percent
(Frequency) Percent
(Frequency) Percent
(Frequency)
1
Our employees are ‘ready’ or have the correct skills and the right attitude to use the BIM software when it is introduced in our organization.
EMPREA 23.53 (4) 47.06 (8) 29.41 (5) 100.00 (17)
2
We are willing to adopt innovative approaches, using proven technologies, tools and practices.
INOTEC 11.76 (2) 23.53 (4) 64.71 (11) 100.00 (17)
3
Our employees are willing to change their way of work to avoid work inefficiency, disorganization, low morale, and no motivation when introducing BIM in our organization.
CHAGWA 17.65 (3) 35.29 (6) 47.06 (8) 100.00 (17)
4
Our firm will provide specific training and available resources to employees in implementing BIM.
TRARES 5.88 (1) 23.53 (4) 70.59 (12) 100.00 (17)
5
Our firm will provide technical assistance to our employees in implementing BIM.
TECASS 0.00 (0) 35.29 (6) 64.71 (11) 100.00 (17)
6 Our firm has the employees with prior experience in collaborative environments.
EXPCOL 23.53 (4) 52.94 (9) 23.53 (4) 100.00 (17)
7
We are confident in dealing with the education and training requirements of potential BIM users within our organization.
DEATRA 5.88 (1) 52.94 (9) 41.18 (7) 100.00 (17)
8
We will assist our workforce in re‐skilling and to capitalize on the rapidly emerging technologies.
WOFRES 0.00 (0) 47.06 (8) 52.94 (9) 100.00 (17)
9 Our employees are familiar with the BIM.
FAMBIM 58.82 (10) 29.41 (5) 11.76 (2) 100.00 (17)
66
Figure 46: BIM readiness from the aspect of people
9.3 Process aspect
Figure 47 and Table 21 show the BIM readiness from the aspect of process. Generally,
respondents moderately agree that we are ready to accept BIM except for question number 4, 5 and 6
where the score of agree are 81.25% or 13 respondents, 56.25% or 9 respondents and 81.25% or 13
respondents respectively. This showing that they believe BIM standard models will help QS in the
measurement process, confident that the BIM system will provide adequate security for exchange of
information or documents throughout the process and they believe that BIM process can help them to
be better Quantity Surveyor. Finding from question number 7, 8, 9 and 10 shows that respondents are
quite disagree that Malaysia have any proper legal terms to accommodate BIM in the construction
industry. The result ranging from 31.25% to 37.50% or 5 to 6 respondents out of 16 respondents
disagree with those statements. From the aspect of process, respondents are ready to accept the
emerging new technology to improve and enhance their quality of works provided that there are proper
legal systems to overcome unwanted legal issues.
EMPREA
INOTECCHAGWA
TRARES TECASS EXPCOLDEATR
AWOFRE
SFAMBIM
Disagree 23.53 11.76 17.65 5.88 0.00 23.53 5.88 0.00 58.82
Moderate 47.06 23.53 35.29 23.53 35.29 52.94 52.94 47.06 29.41
Agree 29.41 64.71 47.06 70.59 64.71 23.53 41.18 52.94 11.76
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
Valid Percentage (%
)
67
Table 21: BIM readiness from the aspect of process
Disagree Moderate Agree Total
Percent
(Frequency) Percent
(Frequency) Percent
(Frequency) Percent
(Frequency)
1
We do not have problem in absorbing information systems (IS) and ICT into our work practices.
NPRABS 31.25 (5) 37.50 (6) 31.25 (5) 100.00 (16)
2
We allow technology to be slowly absorbed into the current organizational business processes when implementing new technology into current processes.
TSLOAB 18.75 (3) 50.00 (8) 31.25 (5) 100.00 (16)
3
We will conduct a self‐evaluation within the organization before the implementation of BIM.
SELEVA 12.50 (2) 43.75 (7) 43.75 (7) 100.00 (16)
4 We believe that standard models will help QS in the measurement process
STAMOD 6.25 (1) 12.50 (2) 81.25 (13) 100.00 (16)
5
We are confident that the BIM system will provide adequate security for exchange of information or documents throughout the process.
ADESEC 12.50 (2) 31.25 (5) 56.25 (9) 100.00 (16)
6 We believe that BIM process can help us to be a better QS
BETTQS 6.25 (1) 12.50 (2) 81.25 (13) 100.00 (16)
7
We are confident that there is sufficient law and regulation to protect our rights when using the BIM software.
PRORIG 43.75 (7) 18.75 (3) 37.50 (6) 100.00 (16)
8
We believe that BIM process is compatible with the current legal status regarding electronic transmissions
LEGSTA 37.50 (6) 25.00 (4) 37.50 (6) 100.00 (16)
9 We believe that BIM software does meet current evidentiary requirements legally.
EVIREQ 37.50 (6) 31.25 (5) 31.25 (5) 100.00 (16)
10
We believe that appropriate legal policies and processes are developed to deal with any problem incur by BIM.
LEGPOL 37.50 (6) 31.25 (5) 31.25 (5) 100.00 (16)
68
Figure 47: BIM readiness from the aspect of process
9.4 Management aspect
Figure 48 and Table 22 shows the BIM readiness from the aspect of management. The first five
questions show that 100% or all the respondents (16 respondents) either moderately or totally agree
that from the aspect of management, they are ready to use BIM. With their proper organization
hierarchical structures, they are able to introduce BIM into their company after planning and evaluation
on their capability to implement it. They believe that ICT investment can help them to increase their
business performance or revenue, thus they prefer to learn how BIM may be used to effectively re‐
engineer the processes rather than continue with the conventional or traditional methods. On top of
that, more than 80% or 13 respondents agree that they have sufficient resources for research,
development and training relating to BIM implementation because they do have staff that are
experience in ICT adoption. Besides, they are willing to support the necessary maintenance cost during
BIM implementation and spent additional time to familiarizing ourselves with the software due to lack
of experience about BIM. Thus, from the findings we notice that from the aspect of management,
respondents are ready to adopt BIM in their firms to enhance the quality of works.
NPRABS
TSLOAB
SELEVA
STAMOD
ADESEC
BETTQS
PRORIG
LEGSTA
EVIREQ
LEGPOL
Disagree 31.25 18.75 12.50 6.25 12.50 6.25 43.75 37.50 37.50 37.50
Moderate 37.50 50.00 43.75 12.50 31.25 12.50 18.75 25.00 31.25 31.25
Agree 31.25 31.25 43.75 81.25 56.25 81.25 37.50 37.50 31.25 31.25
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
Valid Percentage (%
)
69
Table 22: BIM readiness from the aspect of management
Disagree Moderate Agree Total
Percent (Frequency)
Percent (Frequency)
Percent (Frequency)
Percent (Frequency)
1 We believe that BIM can help increase our business performance or revenue.
INCPER 0.00 (0) 43.75 (7) 56.25 (9) 100.00 (16)
2 Our organization hierarchical structures will be able to support BIM implementation.
OHIESU 0.00 (0) 50.00 (8) 50.00 (8) 100.00 (16)
3
We will introduce BIM into our company after planning and evaluation on our capability to implement it.
PLAEVA 0.00 (0) 37.50 (6) 62.50 (10) 100.00 (16)
4 We are aware that technology can help in making ICT investment decisions.
INVDEC 0.00 (0) 25.00 (4) 75.00 (12) 100.00 (16)
5
We prefer to learn how BIM may be used to effectively re‐engineer the processes rather than continue with the conventional/traditional methods.
REGPRO 0.00 (0) 18.75 (3) 81.25 (13) 100.00 (16)
6
Our senior managers are experience in ICT adoption when introducing BIM into our organization.
SMEXAD 18.75 (3) 62.50 (10) 18.75 (3) 100.00 (16)
7
We have sufficient resources for research, development and training relating to BIM implementation.
SUFRES 18.75 (3) 68.75 (11) 12.50 (2) 100.00 (16)
8
We are willing to spent additional time to familiarizing ourselves with the software due to lack of experience about BIM.
SPADTI 6.25 (1) 43.75 (7) 50.00 (8) 100.00 (16)
9 We are willing to support the necessary maintenance cost during BIM implementation.
SUMACO 6.25 (1) 62.50 (10) 31.25 (5) 100.00 (16)
10
We are able to quantify and measure the actual cost of creating and distributing information electronically.
QUANCO 0.00 (0) 68.75 (11) 31.25 (5) 100.00 (16)
11
We are able to conduct cost assessment in order to judge or appraise whether using the BIM process is financially viable.
COSASS 12.50 (2) 43.75 (7) 43.75 (7) 100.00 (16)
70
Figure 48: BIM readiness from the aspect of management
10.0 Cross tabulation analysis
10.1 Level of readiness vs no. of staff
Technology
Figure 49: Level of readiness vs number of staff from the aspect of technology
INCPER
OHIESU
PLAEVA
INVDEC
REGPRO
SMEXAD
SUFRES
SPADTI
SUMACO
QUANCO
COSASS
Disagree 0.00 0.00 0.00 0.00 0.00 18.75 18.75 6.25 6.25 0.00 12.50
Moderate 43.75 50.00 37.50 25.00 18.75 62.50 68.75 43.75 62.50 68.75 43.75
Agree 56.25 50.00 62.50 75.00 81.25 18.75 12.50 50.00 31.25 31.25 43.75
0.0010.0020.0030.0040.0050.0060.0070.0080.0090.00
Valid Percentage (%
)
≤ 10 11‐20 >20 ≤ 10 11‐20 >20 ≤ 10 11‐20 >20
Disagree Moderate Agree
COLSYS 0 14 0 100 57 75 0 29 25
INTSYS 0 0 0 100 71 75 0 29 25
ADOSIT 0 0 0 17 43 0 83 57 100
ADEQIN 0 0 0 33 71 25 67 29 75
SKIDEV 0 14 0 67 71 50 33 14 50
BASREQ 0 0 0 0 29 0 100 71 100
WILINS 0 0 0 17 57 0 83 43 100
SUFHAR 0 0 0 67 57 25 33 43 75
020406080
100
Valid Percentage (%
)
71
Figure 49 illustrates the level of readiness versus number of staff from the aspect of technology.
From the figure shown, firm which had more than 20 staffs had the highest percentage of readiness
towards BIM in the aspect of technology. They are hundred percent agreed that they had use
collaborative system to record all transactions during a project and all the information required, have
the basic internet requirements to go online, and they will install the necessary software that meets the
minimum requirements to run the BIM software. Meanwhile, none of the firm with more than 20 staffs
and the firm which had below than 10 staffs showed any disagree percentage.
People
Figure 50: Level of readiness vs number of staff from the aspect of people
Figure 50 reveals the level of readiness against the number of staff from the aspect of people.
From the figure shown, the percentage of moderate and agree among all the respondents group are
quite good. Again, the firms with more than 20 staffs agreed with a high percentage. However, there
≤ 10 11‐20 >20 ≤ 10 11‐20 >20 ≤ 10 11‐20 >20
Disagree Moderate Agree
EMPREA 0 0 0 67 86 50 33 14 50
INOTEC 0 0 0 50 43 0 50 57 100
CHAGWA 17 0 0 50 71 0 33 29 100
TRARES 0 0 0 17 43 25 83 57 75
TECASS 0 0 0 33 57 0 67 43 100
EXPCOL 0 0 0 83 71 75 17 29 25
DEATRA 0 0 0 33 71 75 67 29 25
WOFRES 0 0 0 50 57 25 50 43 75
FAMBIM 17 14 0 67 71 100 17 14 0
0
20
40
60
80
100
Valid Percentage (%
)
72
were overwhelming hundred percent moderate response to the statement ‘Our employees are familiar
with the BIM’. While, with the same statement, the group of 11 to 20 staffs and the group of below 10
staffs agreed that their employees are familiar with BIM but with a low percentage of seventeen
percent and fourteen percent respectively.
Process
Figure 51: Level of readiness vs number of staff from the aspect of process
Figure 51 illustrates the level of readiness against the number of staff from the aspect of
process. From the figure shown, the firms with below than 10 staffs agreed with a higher percentage
than the firms with more than 20 staffs. Nevertheless, firms with more than 20 staffs disagree by an
average of twenty five percent with the statement ‘We do not have problem in absorbing information
systems (IS) and ICT into our work practices’, ‘We are confident that there is sufficient law and
regulation to protect our rights when using the BIM software’, and ‘We believe that BIM process is
compatible with the current legal status regarding electronic transmissions’, while none of the other
respondent group are disagree.
≤ 10 11‐20 >20 ≤ 10 11‐20 >20 ≤ 10 11‐20 >20
Disagree Moderate Agree
NPRABS 0 0 25 80 57 50 20 43 25
TSLOAB 0 0 0 60 71 75 40 29 25
SELEVA 0 0 0 60 71 25 40 29 75
STAMOD 0 0 0 0 29 25 100 71 75
ADESEC 0 0 0 20 57 50 80 43 50
BETTQS 0 0 0 0 43 0 100 57 100
PRORIG 0 0 25 40 71 50 60 29 25
LEGSTA 0 0 25 40 71 50 60 29 25
EVIREQ 0 0 0 60 71 75 40 29 25
LEGPOL 0 0 0 40 86 75 60 14 25
0
20
40
60
80
100
Valid Percentage (%
)
73
Management
Figure 52: Level of readiness vs number of staff from the aspect of management
Figure 52 depicts the level of readiness versus number of staff from the aspect of management.
From the figure shown, the firms with more than 20 staffs agreed with more than fifty percent, except
they only twenty five percent agree that ‘Our senior managers are experience in ICT adoption when
introducing BIM into our organization’ and none for ‘We have sufficient resources for research,
development and training relating to BIM implementation’. Nevertheless, none of the respondent are
disagree.
≤ 10 11‐20 >20 ≤ 10 11‐20 >20 ≤ 10 11‐20 >20
Disagree Moderate Agree
INCPER 0 0 0 60 43 25 40 57 75
OHIESU 0 0 0 60 57 25 40 43 75
PLAEVA 0 0 0 40 43 25 60 57 75
INVDEC 0 0 0 20 29 25 80 71 75
REGPRO 0 0 0 20 29 0 80 71 100
SMEXAD 0 0 0 80 86 75 20 14 25
SUFRES 0 0 0 80 86 100 20 14 0
SPADTI 0 0 0 80 43 25 20 57 75
SUMACO 0 0 0 60 86 50 40 14 50
QUANCO 0 0 0 80 71 50 20 29 50
COSASS 0 0 0 60 71 25 40 29 75
0
20
40
60
80
100
120
Valid Percentage (%
)
74
10.2 Level of readiness vs years of establishment
Technology
Figure 53: Level of readiness vs number of years of establishment from the aspect of technology
Figure 53 shows the Level of Readiness vs Years of Establishment from the Aspect of
Technology. From the figure shown, the respondent with 6 to 10 years of establishment had a fair
moderate percentage in the range of fifty percent to hundred percent. Meanwhile, the group of
respondents with 11 to 15 years of establishment had also shown a fair moderate percentage in the
range of fifty percent to hundred percent, except none for the statement ‘We do focus on ICT skills
development and/or employing ICT experts’. In overall, none of all the groups disagree, excluding for
the group more than 16 years of establishment, with eleven percent on the statement of ‘We use
collaborative system to record all transactions during a project and all the information required ‘ and
‘We do focus on ICT skills development and/or employing ICT experts’.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Disagree Moderate Agree
COLSYS 0 0 0 11 100 100 50 78 0 0 50 11
INTSYS 0 0 0 0 100 100 50 89 0 0 50 11
ADOSIT 0 0 0 0 33 50 0 22 67 50 100 78
ADEQIN 0 0 0 0 100 50 50 33 0 50 50 67
SKIDEV 0 0 0 11 100 50 100 44 0 50 0 44
BASREQ 0 0 0 0 0 50 0 11 100 50 100 89
WILINS 0 0 0 0 67 50 0 22 33 50 100 78
SUFHAR 0 0 0 0 67 50 50 56 33 50 50 44
0
20
40
60
80
100
Valid Percentage (%
)
75
People
Figure 54: Level of readiness vs number of years of establishment from the aspect of people
Figure 54 illustrates the Level of Readiness vs Years of Establishment from the Aspect of People.
From the figure shown, the respondent with 11 to 15 years of establishment had shown a fairly agree
percentage in the range of fifty percent to hundred percent, except none for the statement of ‘Our
employees are familiar with the BIM’. While the group of respondents within 6 to 10 years of
establishment also shown a fair moderate percentage in the range of fifty percent to hundred percent.
Overall, none of all the groups disagree except for the group from more than 16 years of establishment
and the group from 11 to 15 years of establishment, recording eleven percent and fifty percent
respectively with the same statement of ‘Our employees are familiar with the BIM’.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Disagree Moderate Agree
EMPREA 0 0 0 0 100 100 50 56 0 0 50 44
INOTEC 0 0 0 0 67 50 50 22 33 50 50 78
CHAGWA 33 0 0 0 67 50 50 33 0 50 50 67
TRARES 0 0 0 0 33 50 0 33 67 50 100 67
TECASS 0 0 0 0 67 50 0 22 33 50 100 78
EXPCOL 0 0 0 0 67 100 50 78 33 0 50 22
DEATRA 0 0 0 0 33 50 50 67 67 50 50 33
WOFRES 0 0 0 0 33 50 50 44 67 50 50 56
FAMBIM 0 0 50 11 100 100 50 67 0 0 0 22
0
20
40
60
80
100
Valid Percentage (%
)
76
Process
Figure 55: Level of readiness vs number of years of establishment from the aspect of process
Figure 55 depicts the Level of Readiness vs Years of Establishment from the Aspect of Process.
From the figure shown, again, the respondent with 11 to 15 years of establishment showed a fairly
agree percentage in the range of fifty percent to hundred percent, while the group within 6 to 10 years
of establishment also indicated a fairly moderate percentage in the same range percentage. Overall,
none of the groups disagree except for the group within more than 16 years of establishment by
thirteen percent with the same statement ‘We are confident that there is sufficient law and regulation
to protect our rights when using the BIM software’ and ‘We believe that BIM process is compatible with
the current legal status regarding electronic transmissions’.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Disagree Moderate Agree
NPRABS 0 0 0 13 67 100 50 63 33 0 50 25
TSLOAB 0 0 0 0 67 50 50 75 33 50 50 25
SELEVA 0 0 0 0 67 100 50 38 33 0 50 63
STAMOD 0 0 0 0 0 50 0 13 100 50 100 88
ADESEC 0 0 0 0 0 50 50 50 100 50 50 50
BETTQS 0 0 0 0 33 50 0 13 67 50 100 88
PRORIG 0 0 0 13 67 50 0 75 33 50 100 13
LEGSTA 0 0 0 13 33 50 50 75 67 50 50 13
EVIREQ 0 0 0 0 33 100 50 88 67 0 50 13
LEGPOL 0 0 0 0 33 100 0 88 67 0 100 13
0
20
40
60
80
100
Valid Percentage (%
)
77
Management
Figure 56: Level of readiness vs number of years of establishment from the aspect of management
Figure 56 reveals the Level of Readiness vs Years of Establishment from the aspect of
management. From the figure shown, most of the respondents’ groups fall within moderate
percentage. The group within 6 to 10 years of establishment recorded hundred percent moderate
agreements to almost every statement, except for the statement ‘We are aware that technology can
help in making ICT investment decisions’ with fifty percent agreement. Nevertheless, none of the
respondent group disagreed in this management aspect.
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
≤ 5 yrs6‐10 yrs
11‐15 yrs
≥ 16 yrs
Disagree Moderate Agree
INCPER 0 0 0 0 0 100 50 50 100 0 50 50
OHIESU 0 0 0 0 67 100 50 38 33 0 50 63
PLAEVA 0 0 0 0 33 100 50 25 67 0 50 75
INVDEC 0 0 0 0 0 50 50 25 100 50 50 75
REGPRO 0 0 0 0 0 100 0 13 100 0 100 88
SMEXAD 0 0 0 0 100 100 100 63 0 0 0 38
SUFRES 0 0 0 0 100 100 100 75 0 0 0 25
SPADTI 0 0 0 0 1 1 1 0 0 0 1 1
SUMACO 0 0 0 0 67 100 50 63 33 0 50 38
QUANCO 0 0 0 0 67 100 50 63 33 0 50 38
COSASS 0 0 0 0 33 100 50 50 67 0 50 50
0
20
40
60
80
100
Valid Percentage (%
)