8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
1/13
Biogas Capture
From
Palm Oil Mill Effluent
ForPower Generation
Prepared ByIr Wong Keng Chew
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
2/13
Conventional Practice of Treating
Palm Oil Mill Effluent (POME)
a) The POME is put into anaerobic ponds.
b) Problembiogas is evolved from the anaerobic ponds.
c) Biogasconsists mainly of methane and carbon dioxide, with small
amounts of hydrogen sulphide, water vapour and other gases.
Methane and carbon dioxide are the main green house gases that
contribute to global warming, with methane being 21 times more
potent than carbon dioxide. By harvesting the biogas for fuel, we
are not only utilizing a renewable source of energy but also
helping to alleviate the global warming effect.
Anaerobic Pond
Pome Influent Pipe Pome Effluent Pipe
Biogas (Mainly methane)
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
3/13
New Practice To Treat POME
a) The Biogas is extracted and retained instead of beingreleased freely into the atmosphere.
b) Biogas can be extracted and retained by two different
methods, viz:-
i. Lagoon Digester
ii. Tank Digester
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
4/13
Lagoon Digester
The lagoon digester is
installed by covering theexisting anaerobic pond with
HDPE sheet. The biogas is
retained below this cover
and part of the volume is
recirculated by blowers to
agitate the POME to speed
up the anaerobic digestion.
Pome Influent
PipePome Effluent Pipe
Biogas
To scrubber
HDPE
Cover
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
5/13
Tank Digester System
The tank digester uses a
cylindrical tank to contain thePOME for anaerobic digestion to
biogas. Blowers are also installed
to agitate and recirculate the
POME for even digestion and to
speed up the process.
Biogas evolved is held in a
gas holder, before further
processing (i.e sending to the H2S
scrubber).
Gas HolderAgitator
Pump
Biogas
Tank Digester
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
6/13
Comparison Between Lagoon Digester
And Tank Digester
Lagoon Digester Tank Digester
a) Cost Lesser cost
-Because the flexible HDPE can
be installed over the pond,
thus saving the cost for a
separate biogas (buffer) holder.
Higher cost
-Because of the need of new
tank and a buffer holder.
b) Time to construct Lesserconstruction time Longerconstruction time
c) Productivity Less biogas produced(16m3 of biogas/T of POME)
Longer digestion time
(30days)
More biogas produced
(28m3 of biogas/T of POME)
Shorter digestion time
(15 days average)
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
7/13
Biogas Processing & Power Generation
After the digester,
the biogas stillcontains various
impurities; mainly
moisture and H2S.
H2S is removed by a
bioscrubber and the
moisture by cooling
and condensation.
The processed
biogas is fed finally
to the gas engine
alternator whereelectricity is
generated.
Bio Scrubber
From
Digester
DryerGas Engine
Generator
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
8/13
H2S can be
removed by
biological means; by
passing the biogas
containing H2S
through a mediumwhich has microbes
growing in it. These
microbes feed on
H2S and thus
purifies the biogas.
Biogas Out
Biogas In
Bioscrubber
Bioscrubber
(Vertical Type)
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
9/13
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
10/13
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
11/13
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
12/13
8/11/2019 Biogas Capture From Palm Oil Mill Effluent for Power Generation on 27.3.2014 (for MR CHIN)
13/13
THANK YOU