Building Controls Upgrade - Construction Tyler Salisbury – AV-PMG August 10, 2021 Item No. 8e_supp Meeting Date: August 10, 2021

Building Controls Upgrade - Construction

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Building Controls Upgrade - Construction

Building Controls Upgrade - Construction

Tyler Salisbury – AV-PMGAugust 10, 2021

Item No. 8e_suppMeeting Date: August 10, 2021

Page 2: Building Controls Upgrade - Construction

Project Scope and Location

• Replace 107 obsolete control panels dispersed through the Airport.• Expand the dedicated fiber backbone and replace obsolete copper

backbone.

2

Page 3: Building Controls Upgrade - Construction

Building Controls Background

3

• HVAC Systems• Safety interlocks in

tenant/restaurant kitchens• Metering of usage for domestic

water, natural gas, and other utilities

• Automation and controls

Obsolete Panel New Panel

Space for Future expansions

Page 4: Building Controls Upgrade - Construction

Authorizations

4

Authorizations Project Authorization

Previous authorization $3,000,000

This request $6,901,000

Total authorized amount (Including this request) $9,901,000

Remaining to be authorized $0

Page 5: Building Controls Upgrade - Construction

Schedule• Design complete 2nd Quarter 2021• Construction Authorization 3rd Quarter 2021• Construction start 1st Quarter 2022• Substantial completion 1st Quarter 2023

5

Page 6: Building Controls Upgrade - Construction

We are here

Cone of Certainty

Page 7: Building Controls Upgrade - Construction

Risks and Operational Impacts

7

RISK DESCRIPTION PROBLEM IMPACT MITIGATION PLANRMM Additional time needed

to address any spot abatement required for the fiber routing.

Low Low Scheduling review with the selected contractor to allow for phasing and spot abatement work.

Commissioning cut overs Systems need to be taken offline in order to migrate the data points. This occurs one panel at a time limiting impact, for a short 4-to-6-hour period.

Low Low Follow shutdown request process and communicate in advance. This is a process that the Port is very experienced with.

Contractor Access There are a lot of rooms that need to be accessed for the panel and fiber work across many areas of the airport.

Low Medium Working with CM and Design teams in advance to develop a plan and access needs. The contractor will also be included once selected.

Page 8: Building Controls Upgrade - Construction

Questions