14
CERN EL Group Summary J Devine S Infante

CERN EL Group SummaryCERN Electrical Network • HV/MV: 400kV, 66kV, 18kV, 3.3kV distribution • LV: 230/400V 50Hz throughout • DC: 48V network for critical systems

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • CERN EL Group Summary

    J Devine

    S Infante

  • Summary

    • Structure of EN-EL group at CERN

    • Structure of the CERN electrical network

    • Operating & installation restrictions

    • Principal items of equipment we use

    • Some more ‘exotic’ items…

  • Organisation Chart

  • Main Activities

    • Control Cabling & Optical Fibers

    • Computing and Documentation

    • Control• High Voltage• Low Voltage• Network Operations

  • CERN Electrical Network

    • HV/MV: 400kV, 66kV, 18kV, 3.3kV distribution• LV: 230/400V 50Hz throughout• DC: 48V network for critical systems• Diesel generators for continuity and life safety• Variety of equipment of all types and ages

  • High Voltage Section

    • 400kV Supply from EDF• 132kV Supply from SIG• 66kV Distribution for LHC• 18kV Distribution for SPS/Admin• 3.3kV Distribution for Life Safety & Cryogenics• Over 100 Substations• Over 500Km of underground cables

  • Low Voltage Section

    • Major Projects: New build and refurbishment• Minor Projects: According to user needs• Everything from transformers > lights & sockets• Majority of equipment is purchased through a

    standing contract (3 year duration), including installation labour

    • Special items (cables, connectors, things unique to CERN) purchased & supplied directly

  • Low Voltage Section

    • Typical equipment we use:– LV Switchboard & distribution boards– Cables & Containment– Socket outlet strips– Lighting– UPS– 48V DC production equipment– Custom chassis, emergency stop, 48V

    distribution

  • Control Section

    • Supervision of CERN Electrical Network, from 400kV to 400V, via an industrial SCADA/DMS system (200,000 ana/dig data points)

    • RTU’s, industrial computers acting as data concentrators, are installed in all main substations, surface and underground.

    • Several thousands of electrical equipment, from transformers, to protection relays, to I/O units and switchboard measurement readers are monitored via different field bus and communication protocols

  • Control Section

    IEC870-5-101/104

  • Control Section

    • Permanent changes/upgrades of the whole control infrastructure follow the network renovation projects

    • Main components are purchased through a standing Contract (RTU’s, DAU’s). End foreseen in 2013

    • Data Engineering performed via the standing Contract or via a Software Support for Industrial Control interdepartmental Contract (3 year duration)

  • Control Section

    • Several hundreds of PLC’s managing network switchover in case of outages or LV power distribution control. Programming is normally outsourced.

    • Pilot project for IEC-61850 standard implementation for inter-tripping/interlocking signals within substation

  • Questions?

    CERN EL Group SummarySummaryOrganisation ChartMain ActivitiesCERN Electrical NetworkHigh Voltage SectionSlide Number 7Low Voltage SectionLow Voltage SectionControl SectionControl SectionControl SectionControl SectionQuestions?