1
Role Value Part II Architectural Assistant Stonework, pre-cast concrete, brickwork & roof packages £13 million Design & Build contract Christ’s Lane, Cambridge Panter Hudspith Architects Zinc roofing 5C 5B C/L C/L C/L Singleply roofing membrane Zinc capping piece. Flat double lock welt joint to zinc capping Projecting bay to Christ's Pieces Zinc capping to stonework Aluminium soffit Flat double lock welt joint to zinc capping Overflow outlet to lower roof Singleply roofing membrane Singleply roofing membrane 05 07/19 07 07/47 04 07/19 04 07/19 03 07/39 04 07/39 05 07/39 06 07/39 02 07/47 RIBA workstages Description C - H September 2005 - September 2007 The Christs Lane scheme is a mixed use scheme which replaces an existing 1950’s shopping centre known as Bradwells Court. It consists of three levels of retail with 15 high specification residential units above. I started working on the project from RIBA Stage C working up the GA drawings and proceeding through detail design to seeing the project on site. My main area of involvement was in the preparation of the roof package which is a mixture of standing seam zinc (later changed to stainless steel) and single ply roofing membrane. The roof is one of the most complex areas of the building with 4 main roofs stepping back and intersecting at different angles. I developed the key 1:5 details which then fed back into all the 1:20 assembly drawings . I also worked to develop the secondary steelwork design for supporting gutters and extensions from the primary steelwork. Due to the complexity of the roofs we used 3D sketches to communicate junctions and locations of details to the design team and contractor. I also involved in the stonework, pre-cast concrete and brickwork packages. I developed a number of details and communicated design information to sub-contractors to enable the packages to be developed and constructed on site. The project has been well received by the client and all retail units were occupied when the building opened late 2007.

Christ’s Lane, Cambridge

  • Upload
    others

  • View
    8

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Christ’s Lane, Cambridge

Role

Value

Part II Architectural AssistantStonework, pre-cast concrete, brickwork & roof packages

£13 millionDesign & Build contract

Christ’s Lane,Cambridge

Panter Hudspith Architects

Zinc roofing

5C

5B

C/L

C/L

C/L

Singleply roofing membrane

Zinc capping piece.

Flat double lock welt joint to zinc capping

Projecting bay to Christ's Pieces

Zinc capping to stonework

Aluminium soffit

Flat double lock welt joint to zinc capping

Overflow outlet to lower roof

Singleply roofing membrane

Singleply roofing membrane

05

07/19

07

07/47

04

07/19

04

07/19

03

07/39

04

07/39

05

07/39

06

07/39

02

07/47

Line of roof

Concealed gutter

Upper roof beam

RHS stub support connections to S.Eng spec

PFC to box window

RHS stub support connections to S.Eng spec

Lower roof beam

Line of roof

5A 5B 5C 5D

01

04/118

01

04/118

01

07/45

CL

B18 pitched beam as set out on 04/119

Continuous 50 x 50 angle to S.Eng details

CL

Secondary steelwork to S.Eng details

CL

CL

Steelwork to S.Eng details

Unistrut support angle

CL

CL

5A5B

5C5D

Z purlins shown dotted

50x50x5 SHS @ 1m centres to S.Eng details. Slotted connection both ends

Centreline of beam set out on 07/30

Secondary steelwork to S.Eng details

01

07/39

02

07/39

Centreline of beam set out on 07/30

Centreline of beam set out on 07/30

05

07/19

Dwg.No.

DO NOT SCALE THIS DRAWING. CHECK ALL DIMENSIONS ON SITE. IF IN DOUBT ASK.

SCALE

PROJECT

DRAWING

All information contained in this drawing is sole copy right of Panter Hudspith Architects and is not to be reproduced without their permission.

Job.No.

Rev.CHECKED BY

DRAWN BY

REVISION BY

/

REVISION CHECKED BY

DATE

Email:

P A N T E R H U D S P I T H A R C H I T E C T S

Telephone: Fax:

AM

MW

AM

MW

1:5 @ A1 1:10 @ A3 21 Aug 06

Christ's Lane, Cambridge

3D sketches of roof & box windows

282

A

4-8, Emerson Street, London, SE1 9DU

020 7633 9425 020 7159 1045

[email protected]

07 52

REVISION DATEISSUE PURPOSE CHECKED DATE

1. Comments

2. Cost / buildability check

3. S/C tenders

4. Ordering

5. Construction

6. To enable others to design

7.

Main contractor:Client:

/ First Issue (by Fax)

Scale -

03

07/52

3D sketch of box window steelwork to upper roof NTS

21/08/06NOTES:

1, PRIMARY STEELWORK CONNECTIONS AND ALL SECONDARY STEELWORK TO BE CONFIRMED BY STRUCTURAL ENGINEER

A Details 2, 3, 4 & 5 added. 11/10/06

Scale -

02

07/52

3D sketch of box window and roof flashings to upper roof NTS

Scale -

04

07/52

3D sketch of steelwork to lower roof and projecting bay NTS

CLCentreline of beam set out on xx/xx

5C

5B

70x70mm tapered RSA stub connection

50x50x5mm RSA

Column

Column

Eaves roof beam

70x70x5mm SHS stub connections at 1m centres

100x190x10mm steel plate brackets @ 500 centres

150x100x10 steel angle

04

07/46

04

07/46

70x70x5mm SHS stub connections at 1m centres

100x190x10mm steel plate brackets @ 500 centres

150x100x10 steel angle

02

07/19

01

07/45

Box windowlocation

01

04/118

Rainscreen cladding

Box window

Zinc roof

Zinc roof edge

Zinc roof edge

Concealed gutter

Pressed aluminium fascia

04

07/46

03

07/19

01

07/45 5B

5C

01

04/118

02

07/19

06

07/19C/L

04

07/46

Scale -

01

07/52

3D sketch of box window steelwork to upper roof NTS

Scale -

05

07/52

3D sketch of lower roof and projecting bayNTS

RIBA workstages

Description

C - HSeptember 2005 - September 2007

The Christs Lane scheme is a mixed use scheme which replaces an existing 1950’s shopping centre known as Bradwells Court. It consists of three levels of retail with 15 high specification residential units above.

I started working on the project from RIBA Stage C working up the GA drawings and proceeding through detail design to seeing the project on site.

My main area of involvement was in the preparation of the roof package which is a mixture of standing seam zinc (later changed to stainless steel) and single ply roofing membrane. The roof is one of the most complex areas of the building with 4 main roofs stepping back and intersecting at different angles. I developed the key 1:5 details which then fed back into all the 1:20 assembly drawings . I also worked to develop the secondary steelwork design for supporting gutters and extensions from the primary steelwork. Due to the complexity of the roofs we used 3D sketches to communicate junctions and locations of details to the design team and contractor.

I also involved in the stonework, pre-cast concrete and brickwork packages. I developed a number of details and communicated design information to sub-contractors to enable the packages to be developed and constructed on site.

The project has been well received by the client and all retail units were occupied when the building opened late 2007.