Upload
ngotuong
View
216
Download
0
Embed Size (px)
Citation preview
ROBUST PROJECT
CIDAUT WP5 - Computational Mechanics B5 - Temporary Vertical Concrete Safety Barrier MAIN REPORT Volume 1 of 1
November 2005 Doc. No.: ROBUST-5-011a – Rev 0
Main Report
286-2-1-no-en
Report title:
WP5 - Computational Mechanics B5 Concrete Barrier
Client:
CIDAUT
Doc. no.:
ROBUST-5-011a
Project no.:
202.813023 / ROBUST-GRD1-2002-70021
Reporter(s):
J García
Abstract:
The Robust Project aims to improve scientific and technical knowledge on the main issues still open in the new European standards on the road restraint system EN1317. The knowledge acquired will form the basis of updated standards for EN 1317 and lead to more advanced road restraint systems and improve road-users safety. This report is part of the deliverables from Work Package 5 – Computational Mechanics. This report documents the simulations performed on the B5 temporary vertical concrete safety barrier. The simulations were performed by CIDAUT.
Keywords:
Restricted
Internal
Free distribution
Ref. allowed
Rev. no. Date Prepared by Checked by Approved by Reason for revision
0 22/5/6 J Garcia Public release
ROBUST project Page i
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
CONTENTS
1 INTRODUCTION..................................................................................................1
2 SUMMARY AND CONCLUSIONS .......................................................................2 2.1 Summary..............................................................................................................2 2.2 Conclusions .........................................................................................................2
3 BARRIER – B5 VS GEOMETRO FOR THE ANALYSIS OF OUTPUT SIGNALS. 3 3.1 General ................................................................................................................3 3.2 Additional data .....................................................................................................3 3.3 Input data.............................................................................................................4 3.3.1 Test item ..............................................................................................................4 3.3.2 Test procedure.....................................................................................................4 3.3.3 Analysis data........................................................................................................5 3.4 Analysis results ....................................................................................................7
4 BARRIER – B5 VS GEOMETRO. BASELINE MODEL.......................................15 4.1 General ..............................................................................................................15 4.2 Additional data ...................................................................................................15 4.3 Input data...........................................................................................................15 4.3.1 Test item ............................................................................................................15 4.3.2 Test procedure...................................................................................................16 4.3.3 Analysis data......................................................................................................16 4.4 Analysis results ..................................................................................................18
5 BARRIER – B5 VS GEOMETRO, VARIATION OF FRICTION COEFFICIENT...25 5.1 General ..............................................................................................................25 5.2 Additional data ...................................................................................................25 5.3 Input data...........................................................................................................25 5.3.1 Test item ............................................................................................................25 5.3.2 Test procedure...................................................................................................26 5.3.3 Analysis data......................................................................................................26 5.4 Analysis results ..................................................................................................28
6 BARRIER – B5 VS GEOMETRO. VARIATION OF KINETIC ENERGY..............35 6.1 General ..............................................................................................................35 6.2 Additional data ...................................................................................................35 6.3 Input data...........................................................................................................35 6.3.1 Test item ............................................................................................................35 6.3.2 Test procedure...................................................................................................36 6.3.3 Analysis data......................................................................................................36 6.4 Analysis results ..................................................................................................38
7 BARRIER – B5 VS GEOMETRO., LS-DYNA SIMULATION...............................46 7.1 General ..............................................................................................................46 7.2 Additional data ...................................................................................................46 7.3 Input data...........................................................................................................46 7.3.1 Test item ............................................................................................................46 7.3.2 Test procedure...................................................................................................47 7.3.3 Analysis data......................................................................................................47 7.4 Analysis results ..................................................................................................49
8 REFERENCES...................................................................................................56
ROBUST project Page 1
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
1 INTRODUCTION
Within ROBUST project WP5, CIDAUT carried out simulations of a vehicle, impacting a vertical concrete barrier. The impact conditions were according to EN1317 – Part 2 specifications for TB11 crash test, with an initial speed of 100 km/h and an angle of 20 degrees. The vehicle used for the test simulations was a version of the Geometro model specifically adapted for PAM-CRASH simulation code. The objectives of the WP5 project are:
• Evaluation and enhancement of the use of computational mechanics to complement experimental activity
• Criteria and procedures for the validation of computational mechanics results through comparison with test results
• Reconstruction of real life accidents
• Identification of activity needed for further enhancement of the use of computational mechanics
The simulations reported are focused on the first objective. The topics addressed include the data output and post-processing procedure. This report documents the simulations performed on the B5 temporary vertical concrete safety barrier.
ROBUST project Page 2
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
2 SUMMARY AND CONCLUSIONS
2.1 Summary
The following simulations have been performed for the B5 barrier
Case Barrier Test Name id. Chapter
1 B5 Concrete TB11 B5-MetroPAM-TB11 output signals
Chapter 3
2 B5 Concrete TB11 B5-MetroPAM-TB11 Chapter 4
3 B5 Concrete TB11 B5-MetroPAM-TB11 modified friction
Chapter 5
4 B5 Concrete TB11 B5-MetroPAM-TB11 modified kinetic energy
Chapter 6
5 B5 Concrete TB11 GeoMetro LS-DYNA Chapter 7
The main results are summarised inTable 2-1 below.
Table 2-1 Results from simulations with the B5 temporary vertical concrete safety barrier
Case ASI THIV [km/h]
PHD [g]
Working Width [mm]
Exit speed [km/h]
Exit angle [deg]
Trajectory Detailed description
1 1.67 28.2 22.2 450 90.4 5.0 OK Chapter 3
2 1.71 29.4 20.8 450 83.7 3.7 OK Chapter 4
3.1 1.68 28.4 22.6 450 86.4 4.4 OK Chapter 5
3.2 1.66 28.0 24.2 450 89.6 4.9 OK Chapter 5
4.1 1.71 28.7 21.7 450 91.4 5.2 OK Chapter 6
4.2 1.75 29.3 21.2 450 93.2 5.3 OK Chapter 6
4.3 1.81 30.2 20.6 450 96.1 5.2 OK Chapter 6
5 1.73 31.2 19.2 450 75.6 5.5 OK Chapter 7
2.2 Conclusions
Simulation results, in terms of acceleration and velocity time histories, are representative of the behaviour of TB11 test vehicle in crash test. The post-processing of the results has additional requirements in terms of output process and data filtering in order to obtain adequate calculation of the severity indices.
ROBUST project Page 3
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
3 BARRIER – B5 VS GEOMETRO, ANALYSIS OF OUTPUT SIGNALS.
3.1 General
In this stage, a complete set of simulations were performed in order to determine the most suitable way to obtain, store and process outputs from the simulation program so that a reliable assessment could be made. The results obtained using the finally chosen parameters are the ones included in this chapter. For additional information, refer to document ROBUST-5-011b.
The barrier used in the simulation represented the ‘Temporary Vertical Concrete Safety Barrier’ (B5) used in Round Robin Testing. The vehicle model was a light passenger vehicle, developed by CIDAUT for simulation with the PAM-CRASHTM code. This vehicle model has the same overall geometry as the Geometro model which was supplied as part of the project, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle.
The simulation scenario consisted of the vehicle impacting the barrier with an initial speed of 100 km/h and an angle of 20 degrees.
The characteristics specific to this simulation are:
� The barrier was modelled as a rigid body, rigidly fixed in space, and represented by shell elements that reproduced its outer surface
� Friction between the vehicle and the barrier was set to 0.
� Friction between the ground and the tyres was set to 0.6
3.2 Additional data
The following data and files supplement the result presentation of the simulation as presented in this chapter.
Excel worksheet file:
Rawdata file: B5-metroPAM-c1.zip
Animations:
- front view B5-c1_front.avi
- side view B5-c1_side.avi
- top view B5-c1_top.avi
-perspective B5-c1_iso.avi
ROBUST project Page 4
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
3.3 Input data
3.3.1 Test item
Test item: Temporary vertical concrete safety barrier (B5)
Vehicle: Geometro
Drawings: From Marshalls
3.3.2 Test procedure
1) Test type – TB11
Impact speed: 100 km/h
Impact angle: 20 degrees
Impact point: About 3.2 metres from the beginning of the VRS
Spinning wheels: No
Inertial vehicle test mass: 874 kg
2) VRS model
Barrier type: Temporary Vertical Concrete Safety Barrier (B5)
Number of posts: None
Spacing: None
Total length: 11 m
Element formulation/type: Shell elements.
Connection/Joints: None
Foundation: None. Complete barrier fixed in space
End anchoring: NA
Soil (type and formulation): NA
Roadway: Modelled as rigid wall
3) Vehicle model
Light passenger vehicle, developed by CIDAUT for simulation with PAM-CRASHTM. Same overall geometry as the Geometro model, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle. Validation report available.
ROBUST project Page 5
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
3.3.3 Analysis data
Timestep: Between 2 and 3 E-06
Precision: Single
Friction barrier/vehicle (static coefficient): 0
Friction barrier/vehicle (dynamic coefficient) 0
Friction wheel/ground (static coefficient) 0.6
Friction wheel/ground (dynamic coefficient) 0.6
Accelerometer location (mounting block) Coincident with vehicle cog: Distance 16 mm in Y-direction, less than 1 mm in X and Z directions.
Sampling rate
Friction other:
1.0 E-4 for THP
NA
ROBUST project Page 6
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.1 Model description.
Temporary Vertical Concrete Safety Barrier (B5) Computer model, VRS for roads
Model description Nodes Shell elements Spot welds Materials
15462 14516 NA 1 Other
The concrete barrier was modelled with dimensions 0.8m height, 0.45m depth and 11m length. In order to reproduce the perfectly rigid behaviour intended in crash tests, it was modelled as a rigid body with all degrees of freedom fixed. Contact with friction was modelled between the vehicle and the concrete barrier. To take into account this interaction, shell elements were used.
Table 3.2 Material characteristic.
Vehicle restraint system Part E-Module [MPa] Density [kg/m3] Yield Stress [MPa] Ultimate Stress
[MPa] Failure Strain [-] Comments
B5 Concrete barrier
NA NA - - - Elastic
Strain Rate Stress vs. strain values
NA NA
ROBUST project Page 7
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
3.4 Analysis results
1) VRS
Maximum global dynamic deflection: 0 mm
Working width: 450 mm
Maximum global permanent deflection: 0 mm
Length of contact: 3.31m approximately
Major parts fractured or detached: No
Description of damage to test items: No
Ground anchorage’s meets design levels: NA
Plot of test items: Table 4.3 - Table 4.6
2) Vehicle
Exit speed: 90.4 km/h
Exit angle: 5.0 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
ROBUST project Page 8
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
3) General description of vehicle trajectory:
The vehicle hits the VRS at a velocity of 100 km/h and at an angle of 20 degrees. The vehicle leaves the VRS at an angle of 3.7 degrees. The trajectory is good in the simulation.
Vehicle damage TAD: NA
Vehicle damage VDI: NA
Vehicle cockpit def. index VCDI: NA
Major parts of vehicle detached: No
Plots of the vehicle: Table 4.7
4) Assessment of the impact severity
Impact severity for this model was assessed through three different procedures for data processing.
Post-processing procedure Accelerometer and rotation data, sampled at 10 KHz, input into TRAP as raw data
Acceleration severity index, ASI: 1.67
Acceleration graphs: Yes
THIV: 28.3 km/h
Time of flight: 73.2 ms
Post-impact head deceleration, PHD: 26.2 g
Flail space: 0.6 x 0.3 m
Post-processing procedure Data sampled at 10 KHz, then processed to have a constant time interval of 10 KHz, and input into TRAP as raw data
Acceleration severity index, ASI: 1.67
Acceleration graphs: Yes
THIV: 28.2 km/h
Time of flight: 73.2 ms
Post-impact head deceleration, PHD: 22.2 g
Flail space: 0.6 x 0.3 m
Post-processing procedure Data sampled 10 KHz, processed to have a constant time interval of 10 KHz, filtered CFC180, and finally input into TRAP
Acceleration severity index, ASI: 1.67
Acceleration graphs: Yes
THIV: 28.2 km/h
Time of flight: 73.2 ms
Post-impact head deceleration, PHD: 22.2 g
Flail space: 0.6 x 0.3 m
ROBUST project Page 9
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
5) General statement
From the results above, it can be concluded that the crash protection system fulfils the requirements of the CEN standard with the exception of the severity indices.
The comparison of the values obtained from the different post-processing led to the adoption of the output parameters for the subsequent simulations.
ROBUST project Page 10
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.3 Vehicle - Front view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 11
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.4 Vehicle – Side view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 12
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.5 Vehicle - Top view
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 13
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.6 Vehicle – Iso View
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 14
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 3.7 Vehicle damage.
Top view Bottom view
Side view Side view
View View
ROBUST project Page 15
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
4 BARRIER – B5 VS GEOMETRO. BASELINE MODEL
4.1 General
The barrier used in the simulation represented the ‘Temporary Vertical Concrete Safety Barrier’ (B5) used in Round Robin Testing. The vehicle model was a light passenger vehicle, developed by CIDAUT for simulation with the PAM-CRASHTM code. This vehicle model has the same overall geometry as the Geometro model which was supplied as part of the project, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle.
The simulation scenario consisted of the vehicle impacting the barrier with an initial speed of 100 km/h and an angle of 20 degrees.
The characteristics specific to this simulation were the ones deemed to provide a better agreement with the experimental crash test. They are:
� The barrier was modelled as a rigid body, rigidly fixed in space, and represented by shell elements that reproduced its outer surface
� Friction between the vehicle and the barrier was set to 0.3.
� Friction between the ground and the tyres was set to 0.6
4.2 Additional data
The following data and files supplement the result presentation of the simulation as presented in this chapter.
Excel worksheet file:
Rawdata file: B5-metroPAM-c2.zip
Animations:
- front view B5-c2_front.avi
- side view B5-c2_side.avi
- top view B5-c2_top.avi
-perspective B5-c2_iso.avi
4.3 Input data
4.3.1 Test item
Test item: Temporary vertical concrete safety barrier (B5)
Vehicle: Geometro
Drawings: From Marshalls
ROBUST project Page 16
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
4.3.2 Test procedure
4) Test type – TB11
Impact speed: 100 km/h
Impact angle: 20 degrees
Impact point: About 3.2 metres from the beginning of the VRS
Spinning wheels: No
Inertial vehicle test mass: 874 kg
5) VRS model
Barrier type: Temporary Vertical Concrete Safety Barrier (B5)
Number of posts: None
Spacing: None
Total length: 11 m
Element formulation/type: Shell elements.
Connection/Joints: None
Foundation: None. Complete barrier fixed in space
End anchoring: NA
Soil (type and formulation): NA
Roadway: Modelled as rigid wall
6) Vehicle model
Light passenger vehicle, developed by CIDAUT for simulation with PAM-CRASHTM.
4.3.3 Analysis data
Timestep: Between 2 and 3 E-06
Precision: Single
Friction barrier/vehicle (static coefficient): 0.3
Friction barrier/vehicle (dynamic coefficient) 0.3
Friction wheel/ground (static coefficient) 0.6
Friction wheel/ground (dynamic coefficient) 0.6
Accelerometer location (mounting block) Coincident with vehicle cog
Sampling rate
Friction other:
1.0 E-4 for THP
NA
ROBUST project Page 17
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.1 Model description.
Temporary Vertical Concrete Safety Barrier (B5) Computer model, VRS for roads
Model description Nodes Shell elements Spot welds Materials
15462 14516 NA 1 Other
The concrete barrier was modelled with dimensions 0.8m height, 0.45m depth and 11m length. In order to reproduce the perfectly rigid behaviour intended in crash tests, it was modelled as a rigid body with all degrees of freedom fixed. Contact with friction was modelled between the vehicle and the concrete barrier. To take into account this interaction, shell elements were used.
Table 4.2 Material characteristic.
Vehicle restraint system Part E-Module [MPa] Density [kg/m3] Yield Stress [MPa] Ultimate Stress
[MPa] Failure Strain [-] Comments
B5 Concrete barrier
NA NA - - - Elastic
Strain Rate Stress vs. strain values
NA NA
ROBUST project Page 18
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
4.4 Analysis results
6) VRS
Maximum global dynamic deflection: 0 mm
Working width: 450 mm
Maximum global permanent deflection: 0 mm
Length of contact: 3.31m approximately
Major parts fractured or detached: No
Description of damage to test items: No
Ground anchorage’s meets design levels: NA
Plot of test items: Table 4.3 - Table 4.6
7) Vehicle
Exit speed: 83.7 km/h
Exit angle: 3.7 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
ROBUST project Page 19
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
8) General description of vehicle trajectory:
The vehicle hits the VRS at a velocity of 100 km/h and at an angle of 20 degrees. The vehicle leaves the VRS at an angle of 3.7 degrees. The trajectory is good in the simulation. It is essentially similar to the one reported in case 1, but with a larger change of velocity due to the friction coefficient.
Vehicle damage TAD: NA
Vehicle damage VDI: NA
Vehicle cockpit def. index VCDI: NA
Major parts of vehicle detached: No
Plots of the vehicle: Table 4.7
9) Assessment of the impact severity
Post-processing procedure Accelerometer and rotation data, sampled at 10 KHz, CFC180, input into TRAP
Acceleration severity index, ASI: 1.71
Acceleration graphs: Yes
THIV: 29.4 km/h
Time of flight: 73.6 ms
Post-impact head deceleration, PHD: 20.8 g
Flail space: 0.6 x 0.3 m
10) General statement
From the results above, it can be concluded that the crash protection system fulfils the requirements of the CEN standard with the exception of the severity indices.
ROBUST project Page 20
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.3 Vehicle - Front view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 21
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.4 Vehicle – Side view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 22
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.5 Vehicle - Top view
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 23
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.6 Vehicle – Iso View
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 24
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 4.7 Vehicle damage.
Top view Bottom view
Side view Side view
View View
ROBUST project Page 25
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
5 BARRIER – B5 VS GEOMETRO, VARIATION OF FRICTION COEFFICIENT
5.1 General
The barrier used in the simulation represented the ‘Temporary Vertical Concrete Safety Barrier’ (B5) used in Round Robin Testing. The vehicle model was a light passenger vehicle, developed by CIDAUT for simulation with the PAM-CRASHTM code. This vehicle model has the same overall geometry as the Geometro model which was supplied as part of the project, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle.
The simulation scenario consisted of the vehicle impacting the barrier with an initial speed of 100 km/h and an angle of 20 degrees.
Once that the barrier and vehicle model were checked, simulation case 3 analyses the effect of variations in friction coefficient.
The characteristics specific to this simulation are:
� The barrier was modelled as a rigid body, rigidly fixed in space, and represented by shell elements that reproduced its outer surface
� Friction between the vehicle and the barrier was set to 0.15 and 0, from the initial value of 0.3.
� Friction between the ground and the tyres was set to 0.6
5.2 Additional data
The following data and files supplement the result presentation of the simulation as presented in this chapter.
Excel worksheet file:
Rawdata file: B5-metroPAM-c3.zip
Animations:
- front view B5-c3_front.avi
- side view B5-c3_side.avi
- top view B5-c3_top.avi
-perspective B5-c3_iso.avi
5.3 Input data
5.3.1 Test item
Test item: Temporary vertical concrete safety barrier (B5)
Vehicle: Geometro
Drawings: From Marshalls
ROBUST project Page 26
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
5.3.2 Test procedure
7) Test type – TB11
Impact speed: 100 km/h
Impact angle: 20 degrees
Impact point: About 3.2 metres from the beginning of the VRS
Spinning wheels: No
Inertial vehicle test mass: 874 kg
8) VRS model
Barrier type: Temporary Vertical Concrete Safety Barrier (B5)
Number of posts: None
Spacing: None
Total length: 11 m
Element formulation/type: Shell elements.
Connection/Joints: None
Foundation: None. Complete barrier fixed in space
End anchoring: NA
Soil (type and formulation): NA
Roadway: Modelled as rigid wall
9) Vehicle model
Light passenger vehicle, developed by CIDAUT for simulation with PAM-CRASHTM.
5.3.3 Analysis data
Timestep: Between 2 and 3 E-06
Precision: Single
Friction barrier/vehicle (static coefficient): 0.15, 0
Friction barrier/vehicle (dynamic coefficient) 0.15, 0
Friction wheel/ground (static coefficient) 0.6
Friction wheel/ground (dynamic coefficient) 0.6
Accelerometer location (mounting block) Coincident with vehicle cog
Sampling rate
Friction other:
1.0 E-4 for THP
NA
ROBUST project Page 27
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.1 Model description.
Temporary Vertical Concrete Safety Barrier (B5) Computer model, VRS for roads
Model description Nodes Shell elements Spot welds Materials
15462 14516 NA 1 Other
The concrete barrier was modelled with dimensions 0.8m height, 0.45m depth and 11m length. In order to reproduce the perfectly rigid behaviour intended in crash tests, it was modelled as a rigid body with all degrees of freedom fixed. Contact with friction was modelled between the vehicle and the concrete barrier. To take into account this interaction, shell elements were used.
Table 5.2 Material characteristic – Steel and plastic sections.
Vehicle restraint system Part E-Module [MPa] Density [kg/m3] Yield Stress [MPa] Ultimate Stress
[MPa] Failure Strain [-] Comments
B5 Concrete barrier
NA NA - - - Elastic
Strain Rate Stress vs. strain values
NA NA
ROBUST project Page 28
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
5.4 Analysis results
11) VRS
Maximum global dynamic deflection: 0 mm
Working width: 450 mm
Maximum global permanent deflection: 0 mm
Length of contact: 3.31m approximately
Major parts fractured or detached: No
Description of damage to test items: No
Ground anchorage’s meets design levels: NA
Plot of test items: Table 4.3 - Table 4.6
12) Vehicle
Case 3.1. Friction coefficient 0.15
Exit speed: 86.4 km/h
Exit angle: 4.4 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
Case 3.2. Friction coefficient 0.
Exit speed: 89.6 km/h
Exit angle: 4.9 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
ROBUST project Page 29
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
13) General description of vehicle trajectory:
The vehicle hits the VRS at a velocity of 100 km/h and at an angle of 20 degrees. The vehicle leaves the VRS at an angle of 3.7 degrees. The trajectory is good in the simulation. Only a slight difference in the exit trajectory appear between case 3.1 and 3.2, and between them and case 2.
Vehicle damage TAD: NA
Vehicle damage VDI: NA
Vehicle cockpit def. index VCDI: NA
Major parts of vehicle detached: No
Plots of the vehicle: Table 4.7
14) Assessment of the impact severity
Impact severity for this model was assessed for cases 3.1 and 3.2.
Case 3.2. Friction coefficient 0.15
Post-processing procedure
Accelerometer and rotation data, sampled at 10 KHz, CFC180, input into TRAP
Acceleration severity index, ASI: 1.68
Acceleration graphs: Yes
THIV: 28.4 km/h
Time of flight: 73.5 ms
Post-impact head deceleration, PHD: 22.6 g
Flail space: 0.6 x 0.3 m
Case 3.2. Friction coefficient 0.
Post-processing procedure
Accelerometer and rotation data, sampled at 10 KHz, CFC180, input into TRAP
Acceleration severity index, ASI: 1.68
Acceleration graphs: Yes
THIV: 28.0 km/h
Time of flight: 73.5 ms
Post-impact head deceleration, PHD: 24.2 g
Flail space: 0.6 x 0.3 m
15) General statement
From the results above, it can be concluded that the crash protection system fulfils the requirements of the CEN standard with the exception of the severity indices.
ROBUST project Page 30
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.3 Vehicle - Front view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 31
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.4 Vehicle – Side view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 32
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.5 Vehicle - Top view
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
Time 0.336 Time 0.384
Compared trajectories: case 3.1 (blue), 3.2 (red) and 2 (green)
ROBUST project Page 33
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.6 Vehicle – Iso View
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 34
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 5.7 Vehicle damage.
Top view Bottom view
Side view Side view
View View
ROBUST project Page 35
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
6 BARRIER – B5 VS GEOMETRO. VARIATION OF KINETIC ENERGY
6.1 General
The barrier used in the simulation represented the ‘Temporary Vertical Concrete Safety Barrier’ (B5) used in Round Robin Testing. The vehicle model was a light passenger vehicle, developed by CIDAUT for simulation with the PAM-CRASHTM code. This vehicle model has the same overall geometry as the Geometro model which was supplied as part of the project, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle.
The simulation scenario consisted of the vehicle impacting the barrier with an angle of 20 degrees, and increased values for initial speed (102, 104, 107 km/h) and increased total vehicle mass (964 kg).
The characteristics specific to this simulation are:
� The barrier was modelled as a rigid body, rigidly fixed in space, and represented by shell elements that reproduced its outer surface
� Friction between the vehicle and the barrier was set to 0.3.
� Friction between the ground and the tyres was set to 0.6
6.2 Additional data
The following data and files supplement the result presentation of the simulation as presented in this chapter.
Excel worksheet file:
Rawdata file: B5-metroPAM-c4.zip
Animations:
- front view B5-c4_front.avi
- side view B5-c4_side.avi
- top view B5-c4_top.avi
-perspective B5-c4_iso.avi
6.3 Input data
6.3.1 Test item
Test item: Temporary vertical concrete safety barrier (B5)
Vehicle: Geometro
Drawings: From Marshalls
ROBUST project Page 36
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
6.3.2 Test procedure
10) Test type – TB11
Impact speed: 102, 104, 107 km/h
Impact angle: 20 degrees
Impact point: About 3.2 metres from the beginning of the VRS
Spinning wheels: No
Inertial vehicle test mass: 964 kg
11) VRS model
Barrier type: Temporary Vertical Concrete Safety Barrier (B5)
Number of posts: None
Spacing: None
Total length: 11 m
Element formulation/type: Shell elements.
Connection/Joints: None
Foundation: None. Complete barrier fixed in space
End anchoring: NA
Soil (type and formulation): NA
Roadway: Modelled as rigid wall
12) Vehicle model
Light passenger vehicle, developed by CIDAUT for simulation with PAM-CRASHTM.
6.3.3 Analysis data
Timestep: Between 2 and 3 E-06
Precision: Single
Friction barrier/vehicle (static coefficient): 0.3
Friction barrier/vehicle (dynamic coefficient) 0.3
Friction wheel/ground (static coefficient) 0.6
Friction wheel/ground (dynamic coefficient) 0.6
Accelerometer location (mounting block) Coincident with vehicle cog
Sampling rate
Friction other:
1.0 E-4 for THP
NA
ROBUST project Page 37
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.1 Model description.
Temporary Vertical Concrete Safety Barrier (B5) Computer model, VRS for roads
Model description Nodes Shell elements Spot welds Materials
15462 14516 NA 1 Other
The concrete barrier was modelled with dimensions 0.8m height, 0.45m depth and 11m length. In order to reproduce the perfectly rigid behaviour intended in crash tests, it was modelled as a rigid body with all degrees of freedom fixed. Contact with friction was modelled between the vehicle and the concrete barrier. To take into account this interaction, shell elements were used.
Table 6.2 Material characteristic.
Vehicle restraint system Part E-Module [MPa] Density [kg/m3] Yield Stress [MPa] Ultimate Stress
[MPa] Failure Strain [-] Comments
B5 Concrete barrier
NA NA - - - Elastic
Strain Rate Stress vs. strain values
NA NA
ROBUST project Page 38
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
6.4 Analysis results
16) VRS
Maximum global dynamic deflection: 0 mm
Working width: 450 mm
Maximum global permanent deflection: 0 mm
Length of contact: 3.31m approximately
Major parts fractured or detached: No
Description of damage to test items: No
Ground anchorage’s meets design levels: NA
Plot of test items: Table 4.3 - Table 4.6
17) Vehicle
Exit speed: 83.7 km/h
Exit angle: 3.7 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
ROBUST project Page 39
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
18) General description of vehicle trajectory:
The vehicle hits the VRS at a velocity of 100 km/h and at an angle of 20 degrees. The vehicle leaves the VRS at an angle of 3.7 degrees. The trajectory is good in the simulation.
Vehicle damage TAD: NA
Vehicle damage VDI: NA
Vehicle cockpit def. index VCDI: NA
Major parts of vehicle detached: No
Plots of the vehicle: Table 4.7
19) Assessment of the impact severity
Impact severity for this model was assessed for the three different cases.
Case 4.1. 102 km/h
Post-processing procedure Sampled 10 KHz, CFC180, TRAP
Acceleration severity index, ASI: 1.71
Acceleration graphs: Yes
THIV: 28.7 km/h
Time of flight: 73.1 ms
Post-impact head deceleration, PHD: 21.7 g
Flail space: 0.6 x 0.3 m
Case 4.1. 104 km/h
Post-processing procedure Sampled 10 KHz, CFC180, TRAP
Acceleration severity index, ASI: 1.75
Acceleration graphs: Yes
THIV: 29.3 km/h
Time of flight: 72.0 ms
Post-impact head deceleration, PHD: 21.2 g
Flail space: 0.6 x 0.3 m
Case 4.1. 107 km/h
Post-processing procedure Sampled 10 KHz, CFC180, TRAP
Acceleration severity index, ASI: 1.81
Acceleration graphs: Yes
THIV: 30.2 km/h
Time of flight: 70.4 ms
Post-impact head deceleration, PHD: 20.6 g
Flail space: 0.6 x 0.3 m
ROBUST project Page 40
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
20) General statement
From the results above, it can be concluded that the crash protection system fulfils the requirements of the CEN standard with the exception of the severity indices.
ROBUST project Page 41
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.3 Vehicle - Front view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 42
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.4 Vehicle – Side view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 43
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.5 Vehicle - Top view
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.200
Differences in cog trajectories (represented: case 4.3, black; case 4.2 red; case 4.1 blue; case 2 green) and vehicle damages are nearly negligible.
ROBUST project Page 44
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.6 Vehicle – Iso View
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 45
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 6.7 Vehicle damage.
Top view Bottom view
Side view Side view
View View
ROBUST project Page 46
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
7 BARRIER – B5 VS GEOMETRO., LS-DYNA SIMULATION
7.1 General
The barrier used in the simulation represented the ‘Temporary Vertical Concrete Safety Barrier’ (B5) used in Round Robin Testing. The vehicle model was the a LS-DYNA TB11 model. It was based on the Geometro model supplied as part of the project. Then some modifications were applied, in order to study the possibility to tune the model for a better agreement with test vehicles. The vehicle model complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle.
The simulation scenario consisted of the vehicle impacting the barrier with an initial speed of 100 km/h and an angle of 20 degrees.
The characteristics specific to this simulation are:
� The barrier was modelled as a rigid body, rigidly fixed in space, and represented by shell elements that reproduced its outer surface
� Friction between the vehicle and the barrier was set to 0.3.
� Friction between the ground and the tyres was set to 0.6
7.2 Additional data
The following data and files supplement the result presentation of the simulation as presented in this chapter.
Excel worksheet file:
Rawdata file: B5-metroc5.zip
Animations:
- front view B5-c5_front.avi
- side view B5-c5_side.avi
- top view B5-c5_top.avi
-perspective B5-c5_iso.avi
7.3 Input data
7.3.1 Test item
Test item: Temporary vertical concrete safety barrier (B5)
Vehicle: Geometro
Drawings: From Marshalls
ROBUST project Page 47
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
7.3.2 Test procedure
13) Test type – TB11
Impact speed: 100 km/h
Impact angle: 20 degrees
Impact point: About 3.2 metres from the beginning of the VRS
Spinning wheels: No
Inertial vehicle test mass: 874 kg
14) VRS model
Barrier type: Temporary Vertical Concrete Safety Barrier (B5)
Number of posts: None
Spacing: None
Total length: 11 m
Element formulation/type: Shell elements.
Connection/Joints: None
Foundation: None. Complete barrier fixed in space
End anchoring: NA
Soil (type and formulation): NA
Roadway: Modelled as rigid wall
15) Vehicle model
Light passenger vehicle, developed by CIDAUT for simulation with PAM-CRASHTM. Same overall geometry as the Geometro model, and complies with the vehicle characteristics specified by EN1317 for 900-kg vehicle. Validation report available.
7.3.3 Analysis data
Timestep: Between 2 and 3 E-06
Precision: Single
Friction barrier/vehicle (static coefficient): 0.2
Friction barrier/vehicle (dynamic coefficient) 0.2
Friction wheel/ground (static coefficient) 0.7
Friction wheel/ground (dynamic coefficient) 0.7
Accelerometer location (mounting block)
Sampling rate
Friction other:
1.0 E-5
NA
ROBUST project Page 48
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.1 Model description.
Temporary Vertical Concrete Safety Barrier (B5) Computer model, VRS for roads
Model description Nodes Shell elements Spot welds Materials
15462 14516 NA 1 Other
The concrete barrier was modelled with dimensions 0.8m height. In order to reproduce the perfectly rigid behaviour intended in crash tests, it was modelled as a rigid body with all degrees of freedom fixed. Contact with friction was modelled between the vehicle and the concrete barrier. To take into account this interaction, shell elements were used.
Table 7.2 Material characteristic.
Vehicle restraint system Part E-Module [MPa] Density [kg/m3] Yield Stress [MPa] Ultimate Stress
[MPa] Failure Strain [-] Comments
B5 Concrete barrier
NA NA - - - Elastic
Strain Rate Stress vs. strain values
NA NA
ROBUST project Page 49
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
7.4 Analysis results
21) VRS
Maximum global dynamic deflection: 0 mm
Working width: 450 mm
Maximum global permanent deflection: 0 mm
Length of contact: 3.3m approximately
Major parts fractured or detached: No
Description of damage to test items: No
Ground anchorage’s meets design levels: NA
Plot of test items: Table 4.3 - Table 4.6
22) Vehicle
Exit speed: 75.6 km/h
Exit angle: 5.5 degrees
Rebound distance: NA
Vehicle breaches barrier: No
Vehicle passes over the barrier: No
Vehicle within CEN “box”: Simulation was not run for a long enough period to make the assessment. Though, shallow exit angle indicates it most probably complies
Vehicle rolls over after impact: No
Damage to test vehicle: Table 4.7
ROBUST project Page 50
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
23) General description of vehicle trajectory:
The vehicle hits the VRS at a velocity of 100 km/h and at an angle of 20 degrees. The vehicle leaves the VRS at an angle of 3.7 degrees. The trajectory is good in the simulation.
Vehicle damage TAD: NA
Vehicle damage VDI: NA
Vehicle cockpit def. index VCDI: NA
Major parts of vehicle detached: No
Plots of the vehicle: Table 4.7
24) Assessment of the impact severity
Impact severity for this model was assessed through three different procedures for data processing.
Post-processing procedure Accelerometer and rotation data, sampled at 10 KHz, input into TRAP as raw data
Acceleration severity index, ASI: 1.73
Acceleration graphs: Yes
THIV: 31.2 km/h
Time of flight: Ms
Post-impact head deceleration, PHD: 19.2 g
Flail space: 0.6 x 0.3 m
25) General statement
From the results above, it can be concluded that the crash protection system fulfils the requirements of the CEN standard with the exception of the severity indices.
ROBUST project Page 51
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.3 Vehicle - Front view.
Time 0.00 Time 0.040
Time 0.100 Time 0.140
Time 0.200 Time 0.240
ROBUST project Page 52
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.4 Vehicle – Side view.
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 53
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.5 Vehicle - Top view
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 54
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.6 Vehicle – Iso View
Time 0.00 Time 0.048
Time 0.096 Time 0.144
Time 0.192 Time 0.240
ROBUST project Page 55
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
Table 7.7 Vehicle damage.
Top view Bottom view
Side view Side view
View View
ROBUST project Page 56
CIDAUT ROBUST-5-011a – Rev 0
WP5 - Computational Mechanics B5 Concrete Barrier MAIN REPORT
8 REFERENCES
Ref. 1 EN 1317-1: Road restraint systems – Part 1: Terminology and general criteria for test methods. European Committee for Standardization, April 1998.
Ref. 2 EN 1317-2: Road restraint systems – Part 2: Performance classes, impact test acceptance criteria and test methods for safety barriers. European Committee for Standardization, April 1998