39
March 27, 2018 City of Raleigh Neuse 72-inch Parallel Interceptor Condition Assessment and Rehabilitation Jim Perotti, PE CDM Smith Breanne Long, EI CORPUD

City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

March 27, 2018

City of Raleigh Neuse 72-inch Parallel Interceptor Condition

Assessment and Rehabilitation

Jim Perotti, PE CDM SmithBreanne Long, EI CORPUD

Page 2: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Presentation Outline

Interceptor History Inspection Approach Condition Data Results Data Evaluation

Page 3: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Neuse Parallel 72-inch Interceptors

Page 4: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

History

Transport 40 MGD South Interceptor - 1973 North Interceptor – 1998 Class III and IV RCP with a

coal-tar epoxy liner

Page 5: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

History

2014 Pole Camera Inspection Some sections installed in land

bridges (culverts laid in cut section, backfill, install pipe in cradles, minimum cover)

16-inch DIP Reclaimed water line installed between 72’s

Page 6: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Inspection Approach

Manned-entry• 4 man crew

‒ 2 men in pipe

Page 7: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Inspection Approach

Manned-entry• 4 man crew

‒ CCTV at entry MH

Page 8: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Inspection Approach

Manned-entry• 4 man crew

‒ Forced air at exit MH

Page 9: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Field Health and Safety Plan

Daily emails to project teamlocation/nature of work, weather outlook, status of lockout/tagout

Daily maps sent to Fire Dept • Work locations – road names,

manhole #s (address location not always available)

• Directions to nearest hospital

Page 10: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Field Health and Safety Plan

Doorhangers• 72 hours in

advance

Page 11: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Field Health and Safety Plan

Push Cart• 4 gas monitor, tools, 20

minute supply of air

CCTV monitoring WhatsApp

Page 12: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Inspection Approach - Manholes

Pre-screening of pipe conditions and debris levels

Page 13: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Inspection Approach - Pipes

Diameter laser measurements –at MH and every 25 feet

Pipe soundings every 10 feet Penetration tests

Page 14: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Bypassing Efforts

Walnut Creek PS

Page 15: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Bypassing Efforts

Battle Ridge

Page 16: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Bypassing Efforts

Battle Ridge

Page 17: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Hwy 50 Force Main

Page 18: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Bypassing Efforts

Hwy 50

Page 19: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Bypassing Efforts

Gravity Lines• 8-inch to 12-inch • Small trash pump with flexible hose • Allowed to enter 72

Page 20: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Condition Assessment Findings

Page 21: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Condition Assessment Findings

Modified PACP

Page 22: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Condition Assessment Findings

Page 23: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Effects from FM

Page 24: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Last 4000 feet of each section contained up to 12-inches of debris

Page 25: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Page 26: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Page 27: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Page 28: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Page 29: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Cleaning Efforts

Plant Influent Channel

Page 30: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Structural Evaluation

Pipe wall type assumptions• Type A for Class III and Type B for Class IV• 1-inch cover to reinforcement

Max burial depths for each section

Road crossings encased

Page 31: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Structural Evaluation

Page 32: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Structural Evaluation

Page 33: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install
Page 34: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Structural Evaluation

Page 35: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Rehabilitation Alternatives

Alternatives Pros ConsPotential Bypassing

Needs

Estimated Cost (based on 18,000')

Slipline (FRP) Little DisruptionInstalled in Ex. Flow

Reduced Capacity,Intermittent size

changesNone $600/LF

Open Cut (FRP)

Full CapacityFully Structural

Lengthy Disruption,Land Bridge & Major

Road X-ings

Full 72" bypass $700/LF

CIPP Little DisruptionMaintain Capacity

Not Fully Structural in all reaches,

On-site WetoutNone $1,100/LF

Page 36: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install

Breanne [email protected](919) 996-3732

Jim [email protected](919) 325-3542

Page 37: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install
Page 38: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install
Page 39: City of Raleigh Neuse 72-inch Parallel Interceptor ...€¦ · 2014 Pole Camera Inspection Some sections installed in land bridges (culverts laid in cut section, backfill, install