Conductor Stringing

Embed Size (px)

Citation preview

  • 7/27/2019 Conductor Stringing

    1/42

    Conductor Stringing

    Safe Practice Guide

    ihsa.ca

  • 7/27/2019 Conductor Stringing

    2/42

    1

    Infrastructure Health & Safety Association

    Safe Practice Guide

    Conductor Stringing

    Foreword

    This Guide designates the practices that should be

    followed by the member firms of the Infrastructure

    Health & Safety Association (IHSA) when involved in

    conductor stringing operations. This Guide is not

    designed as a training manual, but contains informa-

    tion, best practices and general recommendations

    deemed appropriate to perform a job in a responsibleand safe manner.

    The contents of this Safe Practice Guide, including all

    advice, recommendations and procedures, are

    provided as a service by the Infrastructure Health &

    Safety Association. No representation of any kind is

    made to any persons whatsoever with regard to the

    accuracy, completeness or sufficiency of the informa-

    tion contained herein. Any and all use of or reliance on

    this Safe Practice Guide and the information containedherein is solely and entirely at the user's risk. The user

    also acknowledges that the safe practices described

    herein may not satisfy all requirements of Ontario law.

    The Infrastructure Health & Safety Association wishes

    to express its appreciation to those who assisted in

    the preparation of this Guide.

    All rights reserved. This publication may not be reproduced,

    in whole or in part, without the express written permission of

    the copyright owner.

    12/05

  • 7/27/2019 Conductor Stringing

    3/42

    2

    TABLE OF CONTENTS

    Introduction 4Purpose 4

    SECTION I

    GENERAL

    100 Safe Execution of Work 6

    101 Competent Personnel 6

    102 Job Planning Tailboard Talks 6

    103 Communication and Teamwork 7

    104 Suitable Equipment Work Methods 7

    105 Utility Work Protection Code 7

    106 Work Area Protection 8

    107 Protective Cover-up Devices 8

    SECTION II

    STRINGING PROCEDURES

    200 Personal Protection 10

    201 Initial Preparation 10

    202 Preparation for Work 11

  • 7/27/2019 Conductor Stringing

    4/42

    3

    SECTION III

    TEMPORARY GROUNDING

    AND BARRICADING OF EQUIPMENT

    300 General Precautions 14

    301 Procedures for Setting Up

    Ground Gradient Mats 15

    302 Procedure for Setting Up Stringing Equipment 17

    303 Procedure for Setting Up Barriers 17

    304 Procedure for Grounding/Bonding During

    Stringing Operations 18

    SECTION IV

    CONVENTIONAL STRINGINGMETHODS

    400 General 28

    401 Tension Brake Devices 28

    402 Pulling Devices 30

    403 Miscellaneous Equipment 31

    404 Removing Old Conductor 34

    SECTION V

    TENSION STRINGING METHODS

    500 General 38

    501 Miscellaneous Equipment 38

    502 Pulling Ropes 39

  • 7/27/2019 Conductor Stringing

    5/42

    4

    INTRODUCTION

    Conductor stringing operations date back to the

    beginning of the electric power era. However, theoriginal stringing methods used in the past no longer

    provide the safe work zone required by current regula-

    tory agencies and management philosophies. The

    ever-increasing presence of obstacles such as

    telecommunications plant, other power lines, roads,

    highways and railroad right of ways have made it

    necessary to use different methods of conductor

    stringing in order to avoid unnecessary risk or interfer-

    ence from these obstacles. More modern types of

    conductor stringing equipment have been developed,

    and many complex stringing jobs have been com-

    pleted safely using this equipment.

    PURPOSE

    This Safe Practice Guide has been compiled to

    familiarize utility and telecommunications personnel,

    and their contractors, with various conductor stringing

    methods, safe work practices, and the equipmentnecessary to undertake a stringing operation in a safe

    manner.

  • 7/27/2019 Conductor Stringing

    6/42

    5

    SECTION I

    GENERAL

    100 SAFE EXECUTION OF WORK

    101 COMPETENT PERSONNEL

    102 JOB PLANNING TAILBOARD TALKS

    103 COMMUNICATION AND TEAMWORK

    104 APPROPRIATE EQUIPMENT WORK METHODS

    105 UTILITY WORK PROTECTION CODE

    106 WORK AREA PROTECTION

    107 PROTECTIVE COVER-UP DEVICES

  • 7/27/2019 Conductor Stringing

    7/42

    6

    SECTION I

    GENERAL

    100 SAFE EXECUTION OF WORK

    The safe execution of a conductor stringing operation

    requires:

    - competent personnel

    - proper, detailed job planning

    - approved work methods

    - effective communication and teamwork

    - well maintained, appropriate equipment

    101 COMPETENT PERSONNEL

    Only competent personnel, or personnel in training

    under the direct supervision of a competent person

    should engage in conductor stringing operations.

    102 JOB PLANNING TAILBOARD TALKS

    As in all other phases of utility and telecommunica-tions work, job planning is of the utmost importance so

    that the work may be performed safely and efficiently. A

    documented tailboard talk should be held with all

    involved in the project prior to the commencement of

    work. This includes workers at both the pulling and

    tensioning ends. The details of the tailboard talk

    should include all known hazards, and the barriers that

    will be used to protect workers and the public. All

    workers must understand the procedures and theirrespective duties and responsibilities before work

    commences. Should it become necessary to change

    the original job plan, all workers should be brought

    together and the new plan explained thoroughly to

    them.

  • 7/27/2019 Conductor Stringing

    8/42

    7

    103 COMMUNICATION AND TEAMWORK

    Effective communication is essential while the work is

    being performed. Operators at the pull in and pay

    out ends should be in constant communication withone another during the stringing operation. In addition,

    a competent person should follow the progress of the

    running board or rope/conductor connection. This

    person should be in constant communication with the

    puller/tensioner operators. Teamwork is essential to

    ensure the safe and efficient execution of the job.

    Various types of conductor stringing equipment are

    currently being used. However, it is imperative that only

    appropriate equipment in good repair be used for the

    stringing method to be followed on each particular job.

    This would apply to pulling lines, travellers, pulling

    devices, tensioning, grounding methods and braking

    devices, etc.

    Local conditions will determine the appropriate

    stringing method to be used. Before deciding on aparticular conductor stringing method, consider factors

    such as the length of pull, the location of other circuits,

    road crossings, etc.

    105 UTILITY WORK PROTECTION CODE

    During any stringing operation that is to be carried out

    in proximity to existing energized apparatus, the

    possibility exists that a conductor being pulled in could

    inadvertently contact the energized apparatus. There-

    fore, it is of the utmost importance that the person in

    charge of the work obtain suitable hold-off protection

    on all of the energized circuits or apparatus which

    could cause a hazard to the stringing operation.

    104 APPROPRIATE EQUIPMENT WORK METHODS

  • 7/27/2019 Conductor Stringing

    9/42

    8

    Any existing isolated lines in proximity to the stringing

    operation should be suitably tagged and grounded in

    accordance with the Utility Work Protection Code, or

    equivalent.

    106 WORK AREA PROTECTION

    Stringing operations may be carried out along busy

    thoroughfares and, because personnel and equipment

    may be situated in various locations along the route,

    proper work area protection is a prerequisite for the

    safe execution of the job.

    Work area protection should be established in accord-ance with the current Ministry of Transportation, Ontario

    (MTO), the Ontario Highway Traffic Act and local bylaws.

    107 PROTECTIVE COVER-UP DEVICES

    Whenever conductors are being installed or removed

    near energized conductors or apparatus, an electrical

    hazard is possible. The preferred course of action is to

    eliminate the hazard by re-routing the feed to providefor circuit isolation. In cases where isolation is not

    feasible, relocation of the conductors and appropriate

    cover-up would be the next choice. In some instances,

    appropriate cover-up is the only alternative. Always use

    cover-up of the appropriate voltage rating. Special

    attention should be given to locations where the

    conductor being pulled crosses any energized appara-

    tus.

    NOTE: To prevent rope burns to protective cover-up

    devices, ensure that the str inging rope and/or

    conductor being pulled in does not drag

    across the cover-up during the stringing

    operation.

  • 7/27/2019 Conductor Stringing

    10/42

    9

    SECTION II

    STRINGING PROCEDURES

    200 PERSONAL PROTECTION

    201 INITIAL PREPARATION

    202 PREPARATION FOR WORK

  • 7/27/2019 Conductor Stringing

    11/42

    10

    SECTION II

    STRINGING PROCEDURES

    200 PERSONAL PROTECTION

    During all stringing operations in proximity to energized

    apparatus, all personnel should follow the ground to

    ground rubber glove rule as set out in the Electrical

    Utility Safety Rules (EUSR). Also, personnel working in

    areas not protected by equipotential grounding and

    bonding should wear rubber gloves.

    201 INITIAL PREPARATION JOB PLANNING

    1. Ensure that work orders, detailed drawings, jobinstruction, etc. are prepared in advance.

    2. Ensure that any necessary applications for work

    protection are arranged for in advance.

    3. Decide on the safest and most practical way to do

    the job.

    4. Check each pole and span to determine what work

    can be performed prior to stringing.

    5. Decide on the most suitable locations for setting upthe stringing equipment.

    6. Ensure sufficient equipment, material and person-

    nel will be available for the job.

    7. Additional personnel may be required at various

    locations to protect the public from possible safety

    hazards arising during the stringing procedures.

    8. Extra traffic control devices may have to be obtained

    from other crews or rental centres.9. Obtain permits when stringing conductor over

    major thoroughfares, railroads, etc. Police or the

    railroad company may be required to assist. Make

    arrangements well in advance of the project.

  • 7/27/2019 Conductor Stringing

    12/42

    11

    202 PREPARATION FOR WORK

    1. One person should be in charge to supervise and

    co-ordinate the overall operation.

    2. Conduct a tailboard talk prior to the commence-

    ment of the job. If a change in procedure is neces-

    sary during the stringing operation, everyone

    should be informed of the change by means of

    additional tailboard talks.

    3. Items to be recorded and discussed during the

    tailboard talk include:

    (a) hazards of all types

    (b) work location for each crew member

    (c) methods of communication (two-way radio

    hand signals, etc.)

    NOTE: The person in charge of the overall job

    should be the only person to order the

    commencement of pulling. Anyone

    noting a problem must immediately

    communicate the need to cease

    pulling.

    Figure #1: Tailboard Talk decal

  • 7/27/2019 Conductor Stringing

    13/42

    12

    (d) traffic control

    (e) hazardous locations (road intersections or line

    intersections, etc.)

    (f) personal protective equipment

    (g) work protection in effect (hold-off, work permits,

    etc.)

    (h) emergency plan

  • 7/27/2019 Conductor Stringing

    14/42

    13

    SECTION III

    TEMPORARY GROUNDINGAND BARRICADING OF EQUIPMENT

    300 GENERAL PRECAUTIONS

    301 PROCEDURES FOR SETTING UPGROUND GRADIENT MATS

    302 PROCEDURE FOR SETTING UPSTRINGING EQUIPMENT

    303 PROCEDURE FOR SETTING UP FENCEBARRIERS

    304 PROCEDURE FOR GROUNDING THECONDUCTOR

  • 7/27/2019 Conductor Stringing

    15/42

    14

    SECTION III

    TEMPORARY GROUNDING AND

    BARRICADING OF EQUIPMENT

    300 GENERAL PRECAUTIONS

    Follow proper grounding procedures when stringingconductor in proximity to other energized circuits.Whenever stringing conductors, use grounds toensure there is no possibility of inducing a charge onto

    the conductors. Make consideration for induction fromhigh voltage circuits, even at distances of 150 m (500ft.) and more.

    Properly grounding equipment and conductors is

    essential. Therefore, appropriate sized ground leads,clamps, connections and reference to the systemprotective devices (i.e. fuses, reclosers, breakers andavailable fault current for the system) must be taken

    into consideration.

    Proper temporary grounding helps ensure the opera-tion of isolating devices and minimizes fault duration,

    which is the objective of grounding. However, the rapidrupturing of fuses or tripping of reclosers may notentirely eliminate the possibility of dangerous potentialrises. Therefore, good electrical connections must bemade from the system protection to the conductor at

    every opportunity throughout the project. The bestreturn route to the system protection is via the systemneutral. In some situations, it may be through groundprobes, or a combination of both.

    All workers (except those necessary to operate themachinery) should stand clear of conductive equip-

    ment during the stringing process. Those workersoperating machinery must be in an equipotential zone,

    where the possibility of step or touch potential differ-ences has been eliminated.

  • 7/27/2019 Conductor Stringing

    16/42

    15

    Equipotential zones are created by bonding and/or

    grounding all metallic apparatus together (i.e. conduc-

    tors, ground gradient control mats, reel stands, pullers

    and tensioners).

    301 PROCEDURES FOR SETTING UP GROUND

    GRADIENT MATS

    The purpose of the ground-gradient mat is to provide

    an equipotential zone of adequate size upon which all

    of the conductor stringing machinery can be be situ-

    ated and all work activities, such as reel changing and

    splicing, can be performed where no potential differ-ences could occur. If contact with another circuit

    occurs, there is still the possibility of a potential rise of

    tremendous magnitude before the system protection

    activates no matter how well this equipment is

    connected. The key to a safe work zone is to minimize

    the possibility of this happening. Should an incident

    occur that causes a potential rise, no one working in a

    properly constructed equipotential zone will sustain

    current flow through their bodies. Where there is no

    current flow, there can be no electrical injury.

    NOTE: The mat should be large enough to carry out

    all work without stepping off the mat.

    At the tension (pay out) end, work includes operating

    the machine, changing reels and splicing conductors.

    A space of 2.4 to 3 m (8 to 10 ft.) is necessary to splice

    conductors behind a tension machine, without step-

    ping off the mat.

    1. A common ground-gradient control mat is a grid ofmetal galvanized steel, or high-flex copper braid,

    strategically positioned on fabric. The design of the

    mesh should be arranged so that workers will

    always be bridging the grid with their feet, whether

  • 7/27/2019 Conductor Stringing

    17/42

    16

    they are standing or walking on the mat. To accom-

    plish this, the steel mat typically consists of a

    minimum No. 10 gauge (0.1350) galvanized steel

    wire, constructed in a 5 cm (2 in.) square mesh, 1.5m by 6 m (5 ft. by 20 ft.), or as required (ie. circum-

    stances dictate the length and width of the mat). In

    fact, most stringing operations require two or three

    such mats bonded together. Ground gradient mats

    should be laid into position whenever there are

    adjacent circuits and/or the possibility of induction.

    All conductor stringing equipment and related

    activities should be carried out on the mats.

    2. IHSA recommends that a 1/0 high flex copper cablebe positioned around the perimeter of each mat.

    The cable shall be affixed to the mesh of the mat at

    intervals not exceeding 0.90 m (3 ft.) to ensure

    continuity at all times. A flex copper lead of at least

    the same dimension or greater, should be con-

    nected to a common point on the tensioning

    machine.

    NOTE 1: If the pulling machine will have direct

    contact with a conductor (when pullingout existing conductors, and the pulling

    line is metallic, or when the new con-

    ductor has to be brought to the puller)

    the puller shall also be placed onto a

    ground gradient mat.

    NOTE 2: Ground rods must be used when only

    delta connected circuits are involved. At

    each of the four corners of the layout,

    ground rods are driven and connectedto the wire lead around the perimeter of

    the mat. Where practical, drive as many

    ground rods as necessary to obtain a

    megger reading of 25 ohms or less.

  • 7/27/2019 Conductor Stringing

    18/42

    17

    302 PROCEDURE FOR SETTING UP STRINGING

    EQUIPMENT

    After the ground gradient mats have been properly

    installed to the dimensions required for the work area,

    move the tension device, reel trailers and all related

    equipment into place onto the mat. Any metallic

    equipment on the mat must be bonded together by

    suitable connectors to the lead running around the

    perimeter of the mat, using 1/0 copper leads to the

    grounding lugs on the equipment.

    NOTE 1: The first and last travellers of the stringing

    project should be grounded.

    NOTE 2: Whenever another circuit t raverses theconductor being strung, the travellers on

    either side must be grounded.

    NOTE 3: If the pulling rope is metallic , wet, contami-

    nated with dir t or aluminum, or the conduc-

    tor is to be pulled to the pulling machine, it

    must be placed on a ground gradient mat

    in the same manner as the tension ma-

    chine.

    Pullers and tensioners shall be anchored, regardless

    of the tension anticipated during the conductor string-

    ing project. Weight change from the conductor at the

    pay out end, or a sudden stop, could cause these

    machines to shift. When the stringing equipment is

    sitting on a ground gradient mat, it is critical that

    conductive wire rope or chains do not extend beyond

    the ground gradient mat. The use of web slings and

    insulators will isolate the machines from the anchor.

    303 PROCEDURES FOR SETTING UP BARRIERS

    1. Nonconductive barriers should be installed around

    the perimeter of the ground mat, to prevent person-

    nel from straying on and off the mat except at a

    controlled location. This controlled location is a 0.9

  • 7/27/2019 Conductor Stringing

    19/42

    18

    m (3 ft.) opening for entry/exit. The barrier system

    will also remind personnel that they should not

    hand tools into and out of the zone when stringing

    is in progress.

    2. Approximately 0.9 to 1.2 m (3 to 4 ft.) outside this

    barrier, another barrier (rope, tape, barricades, etc.)

    should be installed around the enclosure Dan-

    ger Live Apparatus signs should be hung on this

    barrier.

    3. At the entry/exit point, a pieceof plywood 0.9 m by

    1.8 m by 1.3 cm (3 ft. by 6 ft. by in.), covered by a

    nonconductive rubber or plastic mat, should be

    placed so that one end is on the ground mat and

    the other is clear of the barrier around the enclo-

    sure. This is to protect personnel from step

    potentials when entering or leaving the enclosure.

    No personnel may enter or leave the enclosure

    when stringing is in progress. (See Figure #2)

    304 PROCEDURES FOR GROUNDING/BONDING

    DURING STRINGING OPERATIONS

    Considerable emphasis is placed on isolation tech-

    niques and grounding procedures when using large

    hydraulically-driven tension machines. However, there

    is a tendency not to take the same precautions when

    involved with routine stringing operations using small

    tension brakes or reel brakes, in conjunction with reel

    trailers even though the stringing may be done in the

    area of energized equipment. The same precautions

    should apply to routine stringing operations near

    energized equipment as apply to major stringing jobsusing large hydraulically-driven tension machines.

    The grounding/bonding of tensioning machines,

    pulling machines, ground gradient mats, conductors,

    and travellers is to create an equipotential work zone.

  • 7/27/2019 Conductor Stringing

    20/42

    19

    This is a very important component in providing a safe

    work zone for crew members and the general public.

    Every effort taken during preparation to eliminate a

    potential difference throughout the project will help

    prevent injury should something go wrong.

    Sometimes, through equipment failure, loss of control,

    missed communication, oversights or misjudgements,

    the conductor being strung contacts something that isenergized. Equipment may be damaged, power

    interrupted, and the project delayed. However, if this

    unplanned event causes no personal injuries, the

    grounding/bonding has worked as designed.

    Figure #2

    Second physical

    barrier

    Ground matwire fabric

    First physicalbarrier

    1/0 strandedcopper bondinglead, threadedaround perimeterof mat andconnected tosystem neutral

    Plywood covered with rubber mats, used to provide

    entranceway in and out of enclosure

    Equipmentrequiringground

    mat

    protection

    Work area

    inside

    second

    physicalbarrier

    Setting up ground gradient mat area for stringing

  • 7/27/2019 Conductor Stringing

    21/42

    20

    All grounding/bonding connections must be regarded

    the same as making electrical connections. The lower

    the resistance and the more direct path to the system

    protection (fuses, reclosers, etc.), the more rapid theinterruption. Therefore, the preferred connections

    would always be to the system neutral, when available.

    In locations where a system neutral is not available, a

    series of ground probes with 25 ohms or less resist-

    ance is the next best choice. In rural areas, a combi-

    nation of ground probes and the non multi-grounded

    system neutral is necessary.

    A ground gradient mat shall be used for the placementof the tension machine.

    NOTE: The mat should be large enough to carry out

    all work without stepping off the mat.

    At the tension (pay out) end, work includes operating

    the machine, changing reels and splicing conductors.

    A space of 2.4 to 3 m (8 to 10 ft.) is necessary to splice

    conductors behind a tension machine, without step-

    ping off the mat.

    In most instances, two or three separate mats will

    need to be positioned to adequately encompass the

    equipment placed upon it. Each mat used must be

    bonded to a common bus to ensure an equipotential

    work zone is created.

    Bonding cable of 1/0 bare, braided or stranded copper

    is threaded around the perimeter of the mat, then the

    mat and lead (bonding cable) are connected together

    with an appropriate connector, approximately every 0.9

    m (3 ft.).

    At an appropriate location, an extra flex lead, equipped

    with an approved type grounding clamp should be

    connected from the bonding lead to the system neutral.

  • 7/27/2019 Conductor Stringing

    22/42

    21

    This lead should be a minimum of 1/0 extra flex

    copper, and should be treated as a possible energized

    conductor.

    NOTE: Ground rods are required when working

    with delta connected circuits. At each cor-

    ner of the mat, ground rods would be

    driven and connected to the bonding cable.

    Where practical, sufficient ground rods

    should be driven to obtain a megger reading

    of 25 ohms or less.

    Grounding/Bonding During Stringing Operations

    To achieve the goal of establishing a safe work envi-ronment, the following setup would be considered as

    necessary. (See Figure #3)

    At the Reel

    This is the first of a series of grounds to be applied.

    Even though there are several types of tension ma-

    chines in use, a standard method is used to ground

    Figure #3

    Conductor Travelling Ground

    1/0 HighFlex Copper

    Connect Tail ofConductor toReel Stand

    Connect toSystem NeutralWhenever Available

    Connect toDriven GroundRods when noNeutral isavailable

    Neutral

    1

    2

    3

    4

    Each section ofGrounding Matconnects to CommonGrounding Point

    Connect to systemneutral wheneveravailableNeutral

    Connectto driven

    ground rodwhen noneutral isavailable

    ConductorTravelling ground

    Connect tail ofconductor toreel stand

    Each section ofgrounding matconnects tocommongrounding point

    1/0 extraflex copper

  • 7/27/2019 Conductor Stringing

    23/42

    22

    the conductor on the tension stringing reels. On the

    large hydraulic tension machines, a bonding lead is

    connected from the tail of the conductor (projecting

    through the reel) to the ground lug provided on thedrive arm of the tensioner. Internally, on the drive shaft,

    a collector ring provides an electrical path, through a

    set of brushes and extra flex copper, to an external

    ground lug on the tensioner.

    NOTE: This is the only opportunity to ground covered

    conductor dur ing the stringing procedure.

    Ahead of the Reel (Travelling Ground)

    This is the second opportunity to ground the conductor.It maintains a high integrity connection to system pro-

    tection throughout the entire run. To help ensure this:

    a) the full capacity leads and clamps should be

    thoroughly inspected and adequately tightened;

    b) the entire circumference of the wire is involved;

    c) the mechanism is spring loaded to accommodate

    all irregularities in the conductor.

    This ground will ensure continuity with the

    equipotential zone around the tensioner. It will alsoensure the conductor is grounded as it passes up

    through any underbuilt circuits. It is also move-able

    and remains on the conductor tail as the conductor is

    cut and lowered down through any underbuilt circuits.

    The travelling ground is connected to the tension

    machine using a 1/0 extra flex copper lead attached to

    a common grounding point. (See Figure #4)

    The ground gradient mat(s) are also connected to the

    common grounding point. Another 1/0 lead is con-nected to either the system neutral or to ground

    probes, as discussed earlier.

  • 7/27/2019 Conductor Stringing

    24/42

    23

    First and Last Traveller

    This is the third and last

    point in the run to

    ground the conductor.The conductor's angle of

    deflection at these

    travellers allows for

    greater surface contact

    between the conductor

    and grounded travellers.

    Pressure and increased

    contact area between

    these travellers and theconductor is desirable

    to provide a good path to

    ground. These may be

    the only travellers in the

    run that are able to be grounded.

    When the conductor is cut after dead-ending, the

    grounded traveller continues to provide some contact

    with ground.

    NOTE: Travellers with protective coatings on the

    sheaves are not designed to be grounded.

    General Rule: Fifth Traveller Grounding

    This grounding will provide additional paths to ground

    throughout the run.

    In circumstances where induction could be present,

    these multiple grounds will help ensure continual

    draining of induced voltage. Should an inadvertent

    contact occur, these grounds will help isolate the

    offending circuit more rapidly. This is also the rationale

    for grounding both sides of traversing energized

    circuits.

    Figure #4

  • 7/27/2019 Conductor Stringing

    25/42

    24

    All workers must understand when grounding any

    apparatus they are making electrical connections. The

    same care is to be taken as if the device was being

    connected to an energized medium to carry current.

    The fault current during a short circuit could rise to tens

    of thousands of amps. Any underrated, loose, or

    corroded connections will fail, some with catastrophic

    results.

    The more paths to ground the better. The better the

    connections, the more rapid the protection system will

    operate; thereby providing a safer work environment.

    (See Figure #5)

    Figure #5

    When full puller/tensioner machines are not used,

    other types of tension devices are used, as shown in

    Figure #6. Regardless of the type of tensioning or

    pulling device used, the grounding procedure should

    be adequate to protect the workers and the general

    public. Equipotential work zones are always the

    objective when grounding systems are being installed.

    PullerGrounded

    25 OHMs

    25OHMs

    TravellerGrounded

    ConductorGrounded

    TravellerGrounded Equipotential Work Zone

    TravellerGrounded(Every 5th Structure)

    Pulling End

    Last Traveller 1st Traveller

    Tension End

    Pullergrounded

    25 ohms

    Pulling End

    Last Traveller First Traveller

    TravellerGrounded

    Traveller Grounded(every fifthstructure)

    TravellerGrounded Equipotential Work Zone

    25ohms

    Tension End

    Conductor

    Grounded

  • 7/27/2019 Conductor Stringing

    26/42

    25

    Figure #6

    Vertical pivoting action

    Horizontal pivoting

    action

  • 7/27/2019 Conductor Stringing

    27/42

    26

  • 7/27/2019 Conductor Stringing

    28/42

    27

    SECTION IV

    CONVENTIONAL STRINGING METHODS

    400 GENERAL

    401 TENSION BRAKE DEVICES

    402 PULLING DEVICES

    403 MISCELLANEOUS EQUIPMENT

    404 REMOVING OLD CONDUCTORS

  • 7/27/2019 Conductor Stringing

    29/42

    28

    SECTION IV

    CONVENTIONAL STRINGING METHODS

    400 GENERAL

    Conventional stringing methods would apply in cases

    where constant, positive control of the conductor is not

    required. In some instances (to clear driveways, trees,

    etc.), a certain amount of conductor tension is neces-

    sary. Most tension brake devices are suitable for this

    application. However, in situations where absolute

    control of the conductor is necessary, E&USA recom-

    mends the use of full puller/tensioner conductorstringing machines.

    401 TENSION BRAKE DEVICES

    1. Several types of mechanical and hydraulic tension

    brakes are available that will provide a certain

    degree of control over the

    conductor during a stringing

    operation. However, they do

    not have the capability of

    reversing the direction of thepull.

    2. Reel brakes in various

    forms are used extensively

    for conventional stringing

    operations. Tension is

    maintained by an adjustable

    spring and brake band, and

    the unit can be mounted on

    all types of conductor reels.(See Figures #7 and #8)

    3. A type of tension brake

    device that will mount on a

    truck or reel trailer is

    Figure #7

    Figure #8

  • 7/27/2019 Conductor Stringing

    30/42

    29

    available. This unit will handle conductor sizes up

    to 556 circular mils. The braking action is applied

    by placing the conductor between a series of

    bogey wheels and then adjusting a crank to forcethe wheels against the conductor. This unit is

    designed to swivel both horizontally and vertically to

    accommodate the pulling angle. (See Figure #9)

    4. Another type of braking system being used is the

    hydraulic disc brake. (See Figure #10) The use ofthis precision braking device is still categorized as

    conventional stringing because it cannot be

    reversed. This type of system can experience heat

    buildup, therefore, installing a conductor grip as an

    additional measure of safety is recommended if it

    is left unattended. A pressure decline during

    cooling could allow unexpected pay out.

    Figure #9

    Horizontal pivoting action

    Vertical pivoting action

  • 7/27/2019 Conductor Stringing

    31/42

    30

    402 PULLING DEVICES

    1. When an appreciable degree of conductor tension

    is required during a stringing operation, the con-

    ductors can be pulled effectively using a capstan

    head in conjunction with a truck-mounted deck

    winch. The capstan head is not to be confusedwith the collapsible takeup reel, which is not

    designed to safely withstand any significant degree

    of tension. Its use should be restricted to slack

    stringing operations or for installing pulling ropes.

    Collapsible takeup reels should not have a build-

    up of rope on them. They should only have enough

    turns placed on them to effect the desired tension.

    (Between three and six turns should be sufficient.)

    Rope allowed to accumulate under tension willcause the reel to implode.

    2. Boom tip winches should not be used to pull

    conductor, since most are not designed for the

    continuous operation typical of an extensive

    Figure #10

  • 7/27/2019 Conductor Stringing

    32/42

    31

    conductor stringing job. Such continuous operation

    could cause winch components to overheat, which

    could result in total loss of control of the conductor.

    403 MISCELLANEOUS EQUIPMENT

    1. In order to carry out a conductor stringing operation

    in a safe and efficient manner, various additional

    pieces of equipment are necessary. This would

    include appropriate travellers, conductor pulling

    rope, pulling grips, swivels, connectors, a banding

    tool and bands, running board, etc.

    2. Travellers should be of the proper type and size for

    each application and conductor size, and inspectedprior to use. Normally, the type of travellers shown

    in Figure #11 are used throughout the run. How-

    ever, severe corners and the first and last struc-

    tures require larger travellers, as shown in Figure

    #12. Along the run, the sheave size should range

    from 10 to 17 cm (4 to 7 in.) with a load rating

    Figure #11

    Grounding Traveller

  • 7/27/2019 Conductor Stringing

    33/42

    32

    capacity of 1134 kg. (2,500

    lbs.). Where severe angle

    changes occur, use a

    larger traveller.

    Sheave size should range

    from 25 to 50 cm (10 to 20

    in.) with a load rating

    capacity of 1814 kg.

    (4,000 lbs.). Three

    sheave travellers are

    available for simultane-

    ous multi-conductor pulls

    using a running board. Ifthe conductors are being strung individually, use

    single sheave travellers. All travellers should be

    equipped with a device which prevents the conduc-

    tor from jumping out of the traveller.

    3. Use an adequately sized synthetic pulling rope for

    conductor stringing operations. The length of pull,

    size and type of conductor being strung, and the

    degree of tension involved will determine the

    minimum size of rope.4. Use appropriate sized conductor pulling grips to

    join the conductor to the pulling rope. Use a free

    running swivel between the pulling rope and the

    conductor pulling grip to prevent rotation of the

    rope. Using a swivel to join the pulling grip on the

    pulling rope with the pulling grip on the conductor,

    will prevent build up of excessive torque. When

    pulling conductor, the torque builds up rapidly as a

    result of the pull on the synthetic rope by the pullingequipment. Using a straight pulling rope connector

    would not allow this torque to dissipate. Two

    recommended methods of attaching the conductor

    to the pulling rope are:

    Figure #12

  • 7/27/2019 Conductor Stringing

    34/42

    33

    - to connect the swivel to a manufacturer ap

    proved eye splice on the end of the rope, or

    - to install a manufacturer approvedpulling grip

    onto the pulling rope and apply locking as permanufacturers specifications bands (See

    Figure #13)

    Some types of pulling grips are equipped with a

    permanent swivel on one end, however, a high

    quality ball bearing swivel should also be used.

    (See Figure #18)

    When using a running board for multiconductor

    stringing operations, swivels are necessary at all

    running board connections to help prevent runningboard rotation and conductor entanglement.

    5. Secure the tail end of all pulling grips to the con-

    ductor (using a locking band) to prevent them from

    accidentally slipping off. Locking bands must be

    installed on the open end of all pulling grips, 2.5

    cm (1 in.) from the end (see Figure #13). This is to

    prevent the edges of the grip from catching on the

    travellers and pulling the grip off. It is recom-

    mended that the front (pulling end) of the grip be

    Figure #13

  • 7/27/2019 Conductor Stringing

    35/42

    34

    taped so the conductor will not come through the

    aluminum shoulders on the grip.

    (a) Conductor pulling grips should be banded as

    shown in Figure #14.

    Figure #14

    (b) Conductor pulling grips that will run backward

    or be reversed should also be taped, to prevent

    any possibility of snagging, which could causesudden release. (See Figure #15)

    Figure #15

    (c) Conductor pulling grips that are worn or

    frayed at the wire ends should have another

    band applied before the taping process isdone. (See Figure #16)

    Figure #16

    404 REMOVING OLD CONDUCTORS

    Existing conductors will need to be replaced. Since the

    existing conductor is already in position, it could beused to pull in the conductor pulling rope or the new

    conductor.

    Several factors should be considered before proceed-

    ing with this approach, including:

    Double Bands End of Conductor

  • 7/27/2019 Conductor Stringing

    36/42

    35

    - size and type of existing conductor

    - age and condition of existing conductor

    - age and condition of the existing structures includ-

    ing guys

    - location of other energized circuits

    - degree of tension required while pulling

    - size of new conductor to be installed

    The old conductor should be visually inspected and

    analyzed for defects prior to untying or unclamping.

    Defects can be caused by age, lightning, accidental

    contacts from trees, hoisting booms, etc.

    If the conductor is of adequate strength and in goodcondition, it may be used to pull in the pulling rope or

    the new conductor.

    Grounding should be the same as it would be for

    stringing new conductor, with one exception: the pulling

    and pay out ends will have to be set up exactly as

    discussed in Section 304 of this guide.

    Automatic type sleeves should be removed before

    proceeding. Non-compression (automatic) sleeves

    are reliant upon multiple fingers gripping the outside

    sur-face of the conductor strands. The tension is

    constant and the loading is linear (in-line). As the

    tension increases, the fingers grip more firmly into the

    outside strands as they are forced into the tapered

    barrel of the sleeve. Axial loading and fluctuations in

    loading will cause failure (e.g. sudden release of

    tension could cause the fingers to lose their grip), and

    axial loading will cause the hollow barrel of the centre

    to collapse.

    Preparing the old conductor for removal

    1. Automatic sleeves should be replaced with either

    compression sleeves or conductor pulling grips.

    Defects found during the visual inspection and

  • 7/27/2019 Conductor Stringing

    37/42

    36

    dead-ends should be removed, and the conductor

    connected end-to-end.

    2. Installing conductor pulling grips back-to-back will

    act as a temporary solution. However, doing so

    requires that the grip leads be attached together.

    This can be done in

    several ways:

    (a) An alloy steel

    connector of the

    appropriate

    strength can be

    used if it is wire

    on either side. (See Figure #17)

    (b) An alloy steel swivel of the appropriate strength

    can be used if it is a wire-to-wire situation and

    should be used if rope is on one side and wireon the other. (See Figure #18)

    (c) An approved alloy connecting link may be used

    where a swivel is not required. (See Figure #19)

    NEVER run swivels or

    connecting links onto

    bullwheels or conductor

    reels. They are not

    designed for side loading,

    which would happenwhen wrapped around a

    bullwheel or reel.

    NEVER use a non-rated

    threaded link for conductor stringing.

    Figure #17

    Figure #18

    Figure #19

  • 7/27/2019 Conductor Stringing

    38/42

    37

    SECTION V

    TENSION STRINGING METHODS

    500 GENERAL

    501 MISCELLANEOUS EQUIPMENT

    502 PULLING ROPES

  • 7/27/2019 Conductor Stringing

    39/42

    38

    SECTION V

    TENSION STRINGING METHODS

    500 GENERAL

    Although there has been a reasonable degree of

    success tension stringing with conventional braking

    devices, these devices should not be used during

    operations where the absence of constant, positive

    control of the conductor could create a safety hazard.

    501 MISCELLANEOUS EQUIPMENT

    Hydraulically-driven puller/tension machines, like the

    one shown in Figure #20, are the accepted standardfor true tension stringing operations. At least two

    Figure #20

  • 7/27/2019 Conductor Stringing

    40/42

    39

    machines are necessary for single conductor stringing

    one as a pulling device and the other as a tensioner.

    Both machines are essentially the same. However, the

    pulling device would be adjusted to produce slightlymore tension than the tensioning device. Conse-

    quently, should the pulling line or conductor snag, the

    entire operation will cease without introducing a

    significant increase in line tension.

    One definite advantage of this type of machine is its

    ability to operate in either direction under desired

    tension or speed. Therefore, a snagged conductor or

    pulling line can be more easily cleared than with

    conventional types of equipment. Also, both machines

    will react immediately to remove unexpected slack.

    All travellers, swivels, connectors, running boards, and

    pulling grips that are normally used during conven-

    tional stringing operations may also be used in

    conjunction with tension stringing techniques, provided

    it is of adequate size and strength for the job at hand.

    502 PULLING ROPES

    1. During tension stringing operations, experience

    has shown that the main pulling rope (bull rope)

    can be installed more easily if a smaller diameter

    synthetic rope (pea line) is first installed through

    the travellers, and used to pull in the pulling rope.

    The suggested size for this pea line would be a

    minimum of 10 mm (3/8 in.) in diameter.

    2. The main pulling rope should be a synthetic rope of

    the appropriate size. Many stringing operations

    use a 19 mm (3/4 in.) diameter two-in-one braided

    rope. Several speciality ropes are being manufac-

    tured for conductor stringing. Double braid polyes-

    ter sheath, polyester core and hollow braided

    polyvinyl coated polyester ropes are preferred.

  • 7/27/2019 Conductor Stringing

    41/42

    40

    These ropes should have a minimum breaking

    strength of approximately 7,439 kg (16,400 lbs.),

    which will be adequate to safely handle most

    tension stringing operations on distribution plant.

    NOTE: Visually inspect the pulling rope before

    using it and remove from service any

    rope found to be damaged. Some types

    of rope can be field spliced; others re-

    quire sophisticated splicing procedures.

    These ropes may be joined using back-

    to-back conductor pull ing grips banded

    for security. Refer to the rope manufac-

    turer specifications for approved meth-ods.

  • 7/27/2019 Conductor Stringing

    42/42

    T 905-625-0100T 1-800-263-5024F 905-625-8998

    [email protected]

    Copyright 2011 All Rights Reserved

    Bare Hand Live Line

    Techniques

    Conductor Stringing

    Entry and Work in a

    Confined Space

    Excavating with

    Hydrovacs in the

    Vicinity of Underground

    Electrical Plant

    High Voltage Rubber

    Techniques up to 36 kV

    Hydraulics

    Ladder Safety

    Line Clearing Operations

    Live Line Tool Techniques

    Low Voltage Applications

    Pole Handling

    Ropes, Rigging and

    Slinging Hardware

    Temporary Grounding

    and Bonding Techniques

    Underground Electrical

    Systems

    Available Safe Practice Guides