CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN AND LICENSING MCWRA SMALL HYDRO WORKSHOP MARCH 22, 2013 HDR Engineering, Inc.

CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

  • Upload
    ngobao

  • View
    224

  • Download
    4

Embed Size (px)

Citation preview

Page 1: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

CONSIDERATIONS FOR

SMALL HYDROPOWER

SITING, DESIGN AND LICENSING

MCWRA SMALL HYDRO WORKSHOP

MARCH 22, 2013

HDR Engineering, Inc.

Page 2: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Agenda

Definitions of “Small Hydro”

Site Selection

Conventional vs. in-line/conduit projects

Power production estimates

Existing dams vs. new construction

Turbine Alternatives

Traditional vs. Emerging Turbine Technologies

Turbine Performance Comparisons

Licensing and Exemptions

Comparison of Exempt vs. Non-Exempt Regulatory Process

Overview of FERC License Exemption Criteria

Development Trends in California

Page 3: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Definitions of “Small Hydro”

Page 4: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Definitions of “Small Hydro”

Electrical capacity and physical size do no correlate

well in hydropower

Sometimes based on regulatory language and/or

perceived environmental impacts

Generally-accepted (US) terms based on capacity

Small Hydro – all projects <30 MW

Mini Hydro – 100 kW to 1 MW

Micro Hydro – all projects <100 kW

Page 5: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Site Selection

Page 6: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Site Selection

Conventional small hydro

Powering existing dams/diversions

“Minimum flow” units resulting from FERC relicensing process on existing projects

New diversion projects

In-line/conduit small hydro

Includes drop structures in existing canal/flume systems

Generally more scalable than conventional hydro

Often co-located with other necessary infrastructure

Transmission access considerations

Page 7: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Site Selection (cont’d)

Power Production Estimates

Head and flow exceedance

curves

Available hydrology

Influence of

snowpack/snowmelt

Consider minimum instream

flows for new diversions

Ungaged watersheds –

surrogate data methods

Page 8: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Site Selection (cont’d)

Modifications at Existing Dams

Don’t forget about water rights!

New Construction

Page 9: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Turbine Alternatives

Page 10: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Turbine Alternatives

Traditional Turbine Technologies

Reaction Kaplan/Propeller

Francis

Impulse Pelton

Turgo/Banki/Crossflow

Emerging Turbine Technologies

Natel hydroEngine

Reverse Archimedes Screw

Page 11: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Turbine Alternatives (cont’d)

Multiple unit dispatch can

improve low-end efficiencies

for reaction turbines

(trade-off with capital costs)

Page 12: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions

Page 13: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions

Licensing for “Major” Projects (>5 MW)

Integrated Licensing Process (ILP) vs. older processes

State and Federal fish and wildlife, cultural and water

resource agencies have jurisdiction over license

conditions

Typically 7-8 year process, not withstanding 401 water

quality certification

30 to 50 year license term

Page 14: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions (cont’d)

Page 15: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions (cont’d)

Exemptions for Small (<5 MW) and Conduit Hydro

Based on Traditional Licensing Process

4-6 month typical turn-around for exemptions

(sometimes faster)

Less resource agency scrutiny, particularly for conduit

projects (Section 30(c) conditions)

Issued in perpetuity

Small Hydro: Powerhouse must be <500’ from existing

dam, and >36% of head must be provided by the dam

Page 16: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions (cont’d)

Key Differences between 5 MW

and Conduit Exemptions

Category 5 MW

Exemptions

Conduit

Exemptions

Location Existing dam or

natural water

feature

Any manmade

water conveyance

not primarily used

for hydro

Max Capacity 5 MW 15 MW (private)

40 MW (muni)

Land Ownership Not Required Required

NEPA Eligibility Yes Categorically

Exempt

Page 17: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Licensing and Exemptions (cont’d)

Ways to Expedite Exemption Applications

Unlikely to affect T&E species or need fish passage

Little change to range and timing of flows

Develop stakeholder consensus early in process

Applicant owns all lands needed for construction and

O&M

Application is complete

Page 18: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Development Trends in California

Page 19: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Development Trends in California

1980s small hydro boom (PURPA), 1990s-2000s market limitations, 2010s growth led by conduit projects and new renewables legislation

Size distribution of projects by type are remarkably similar, and conduit projects are (surprisingly) larger

0

2

4

6

8

10

12

14

1980s 1990s 2000s 2010s

Pro

ject

s p

er

Year

0

1000

2000

3000

4000

5000

6000

7000

8000

0 20 40 60 80 100

Au

tho

rize

d C

apac

ity

(kW

)

Percent Exceedance

Conduit Non-Conduit

Page 20: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

Development Trends in California

(cont’d)

Renewable Portfolio Standards eligibility

Small Hydro >30 MW nameplate capacity

Cannot have adverse impact on instream beneficial uses or cause change in volume/timing of flows (limits eligibility to run-of-river)

Benefits of RPS certification and RECs

Renewable Energy Credits (RECs) – current values range from $10-50/MWh

RECs can be sold “bundled” or “unbundled”

Public awareness

Page 21: CONSIDERATIONS FOR SMALL HYDROPOWER SITING, DESIGN · PDF fileconsiderations for small hydropower siting, design and licensing mcwra small hydro workshop march 22, 2013 hdr engineering,

End of Presentation